The PTH 101 Red River bridge would probably be staged like this. They build 2 new structures on the north and south sides for the collector lanes. Detour the current traffic pattern over to that. Then rehab the existing bridge. Like keep the piers, and build a new 6 lane superstructure. They're reconfiguring the Main St over pass to accommodate the rail overpass. They both need to go over or both under. There was an RFP in ~2015 to re-route that track elsewhere but it was never awarded.
But IIRC there was already a project on the books for that PTH 101 bridge, so maybe they do the rehab ahead of time. The PTH 100 bridge is being rehab sometime sooner.
|