The demolition of the 75 year-old Salvation Army Temple at 301 E Hastings has been approved, despite its appearance on Heritage Vancouver’s Top 10 Watch List in 2016, & 2024. However, this site won’t sit empty for long.
A Navigation Hub could soon open here to provide an opportunity for individuals experiencing chronic homelessness to be “intensely supported” until at least 2027, while Vancouver Coastal Health’s long discussed redevelopment plans for this site are finalized.
Location: The People's Glorious Republic of ... Sigh...
Posts: 8,491
Quote:
Originally Posted by csbvan
Not a big fan of any of that.
The literal gravity of the plan could create a black hole.
__________________
If it seems I'm ignoring what you may have written in response to something I have written, it's very likely that you're on my Ignore List. Please do not take it personally.
Reconfiguration of the office lobby at 1200 Burrard (TD Bank) at Denman/Burrard.
Quote:
- Enlarging the main lobby of the building combined with an opportunity to include a coffee kiosk within the lobby
- Tenant improvement to update the interior finishes combined with the addition of a new contemporary exterior façade design complete with steel and glass canopies.
- Redesign the current plaza design to provide more opportunity for the public to sit, enjoy and inhabit
- Provide a new universal washroom in the main lobby to replace two existing accessible washrooms
- Reconfigured mail boxes and mail service room
- Upgrade of the lobby's electrical, HVAC and fire suppression system
- Reinstallation of plaza membrane, replacing plaza finishes and removing / replacing the existing plaza trees
- New accessible main entry combined with vestibule with additional convenience entrees/exits and a separate TD bank entry
- Upgrades to provide a new accessible / universal washroom, a reconfigured mail room and a service spaces
I have to admit that the steel columns and bolts are smaller than I would have anticipated for a building of this scale. Clearly, the structural engineers have signed off, but it's not quite what I was expecting.
__________________ VANCOUVER | Beautiful, Multicultural | Canada's Pacific Metropolis
I have to admit that the steel columns and bolts are smaller than I would have anticipated for a building of this scale. Clearly, the structural engineers have signed off, but it's not quite what I was expecting.
I guess because there's so many steel columns the load is spread and they can use smaller hardware. I agree though, my (non-qualified) brain looks at it and thinks they should be bigger.
Anyone have an Update on the 1210-seymour-st Building? They demolished the old Building in the last couple of months. But left the original concrete slab but then work has stopped. Nothing over the last Month.
Thanks for your time
Just noticed driving by that they now have an Excavator on site. I assume they are getting ready to remove the concrete Slab. Not sure how far down they will go or if there will be any parking or not.
Just noticed driving by that they now have an Excavator on site. I assume they are getting ready to remove the concrete Slab. Not sure how far down they will go or if there will be any parking or not.
They got another new street occupancy permit
Quote:
Permission to close and occupy the sidewalk and curb lane to store 8'x14'6" ESC tank, and after hours pedestrian provision on the 500 block of Davie St as per accepted TMP.