Old Posted Jan 3, 2023, 6:20 AM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,799
Quote:
Originally Posted by Hooknose View Post
... imagine if both TBMs were side by side at Main Street ... The numbers don't line up for that to be a strong possibility but it would be fun.
I suspect they will actively modulate the progress of the TBMs to avoid having that happen just because it would complicate things to have them both in the same station pit at the same time because there would be no space for anything else in the pit.
Reply With Quote
     
     
  #1742  
Old Posted Jan 3, 2023, 7:05 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,780
There's a few break throughs that happened at the same time not sure how common it is for them to be in the same station pit at the same time.

Toronto
Quote:
In November 2011, Yorkie began the first northern tunnel drive from a launch shaft near the future Pioneer Village Station and broke through at the extraction shaft on Keele Street at Murray Ross Parkway — north of Finch West Station — on November 29, 2012, after placing 1,110 rings. Torkie began tunnelling in February 2012 and also broke through at the extraction shaft on November 29, after placing 1,119 rings. This made project history as the first double-TBM breakthrough, a rare occurrence in North America. Yorkie and Torkie completed 1.7 kilometres (1.05 miles) of twin tunnels on these two drives. (You can view a video of the double breakthrough here.)
HK

http://dragageshk.com/news-post/hong-kongs-first-double-tbm-breakthrough-takes-place-in-tmclk/

India

Quote:
This is the first double TBM break through in India and only the second in the World, the first such being recorded during work on the 8.6km Toronto-York Spadina subway extension in 2002.
https://tunnellingjournal.com/delhis-double-breakthrough/

Norway

https://www.facebook.com/ghellaspa/posts...pTvLZxVeFeMNja7Y-pJRrYiOEATfH5H-Hc4&_rdr
Reply With Quote
     
     
  #1743  
Old Posted Jan 5, 2023, 1:38 AM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,207
Updated schedule has start of service for February 7th 2026, a 6 week delay.

[/url]

From the Nov 2022 monthly status report. https://www.broadwaysubway.ca/app/upload...-Monthly-Status-Report-November-2022.pdf
Reply With Quote
     
     
  #1744  
Old Posted Jan 5, 2023, 2:29 AM
Tvisforme's Avatar
Tvisforme Tvisforme is offline
Registered User
 
Join Date: Sep 2014
Location: Metro Vancouver
Posts: 2,177
Quote:
Originally Posted by madog222 View Post
Updated schedule has start of service for February 7th 2026, a 6 week delay...
Finally, something that makes the realization it's now 2023 more palatable...
Reply With Quote
     
     
  #1745  
Old Posted Jan 5, 2023, 12:27 PM
Hooknose Hooknose is offline
Registered User
 
Join Date: Mar 2017
Posts: 248
Quote:
Originally Posted by madog222 View Post
Updated schedule has start of service for February 7th 2026, a 6 week delay.

[/url]

From the Nov 2022 monthly status report. https://www.broadwaysubway.ca/app/upload...-Monthly-Status-Report-November-2022.pdf
Great image on the slated progress for the Broadway line. Thanks.

Did you notice that all the "planning" , detailed and otherwise will be finished in about two to three months.

Dear me, whatever are all those planners going to do? It is three years until the builder will have the line finished.

I know this is thread that might be better off being put on the Metro discussion but still, great image to start us off.

Whatever are all those good folks (planners) going to be doing for three years.
Reply With Quote
     
     
  #1746  
Old Posted Jan 5, 2023, 6:57 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888
I hope that somehow find some efficiencies to pull it back into 2025 so I can think in my mind "only two more years to go" even though that would be all of 23, 24 and 25. So really three years. Two years just sounds better.

Also some quick estimating "half way" between Emily Carr Station and Main Street station is very roughly Dude Chilling Park / 8th and Brunswick, I would say.
Reply With Quote
     
     
  #1747  
Old Posted Jan 7, 2023, 5:09 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,780
Video update on station construction

https://www.youtube.com/@helloworldconstruction/videos
Reply With Quote
     
     
  #1748  
Old Posted Jan 8, 2023, 12:06 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,780
The other guy filming the station construction also updated his YouTube channel

https://www.youtube.com/@Flames237/videos
Reply With Quote
     
     
  #1749  
Old Posted Jan 8, 2023, 6:01 AM
NicholasHui NicholasHui is offline
Registered User
 
Join Date: Oct 2020
Posts: 39
Broadway City Hall Station excavation at the east side is mostly completed with concrete in progress well. The west side still is under excavation as mentioned on the video https://www.youtube.com/watch?v=w5wHk0nTl7I&list=PL3ds3GlHtgFpgxdPAZXWsNaRgoY4x3MTE&index=28 as of January 2, 2023 I posted.

For Arbutus Station, the supporting columns of the northwest side of the traffic deck is completed. https://www.youtube.com/watch?v=MxAcFjI-nEE&list=PL3ds3GlHtgFpgxdPAZXWsNaRgoY4x3MTE&index=31&t=512s
Reply With Quote
     
     
  #1750  
Old Posted Jan 10, 2023, 4:47 PM
mattropolis's Avatar
mattropolis mattropolis is offline
matt in the city
 
Join Date: May 2004
Location: BC
Posts: 393
Bus stop in front of Broadway City Hall!?

I think they are building a bus stop in front of Broadway City Hall. If so, that is great. Having to walk a block west to catch the eastbound 99 is a drag.

My photos.
Fri Jan 6, 2023


Mon Jan 10
Reply With Quote
     
     
  #1751  
Old Posted Jan 10, 2023, 10:41 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,207
Quote:
Originally Posted by mattropolis View Post
I think they are building a bus stop in front of Broadway City Hall. If so, that is great. Having to walk a block west to catch the eastbound 99 is a drag.
Yup, too bad it's taken so long with the sewer work. The bridge deck itself was ready back in August.


Traffic Decking by B.C. Ministry of Transportation and Infrastructure, on Flickr

Quote:
Originally Posted by madog222 View Post

Last edited by madog222; Jan 10, 2023 at 11:00 PM.
Reply With Quote
     
     
  #1752  
Old Posted Jan 11, 2023, 3:58 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,768
Broadway Subway twitter posted Jan 9th (but October pics):

South Granville Station:


At the start of 2022, shallow excavation was underway on Broadway at the future South Granville Station block.
Now, this traffic deck is complete, & excavation for the #BroadwaySubwayProject continues about 10 metres under the street while people move above!
https://twitter.com/broadwaysubway_

Arbutus Station:


Back in January 2022, crews were just beginning to drill and excavate for the traffic deck at the Arbutus Station block.
Today, the traffic deck is nearly complete, with 4 lanes of traffic moving on Broadway. Once completed, work on the station can continue below the street!
https://twitter.com/broadwaysubway_
Reply With Quote
     
     
  #1753  
Old Posted Jan 13, 2023, 6:14 PM
John Q. Citizen John Q. Citizen is offline
Registered User
 
Join Date: Jan 2023
Posts: 1
Traffic Cams

Does anyone know why all of the CoV traffic cams (where the stations are located) have been disabled? the Contractor does not have construction cams and the amount of viewable progress online is disappointing for a project of this scope.
Reply With Quote
     
     
  #1754  
Old Posted Jan 13, 2023, 7:28 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,780
Quote:
Originally Posted by John Q. Citizen View Post
Does anyone know why all of the CoV traffic cams (where the stations are located) have been disabled? the Contractor does not have construction cams and the amount of viewable progress online is disappointing for a project of this scope.
Seems like it's system maintenance because a large number of cameras are offline including ones not near any construction sites.
Reply With Quote
     
     
  #1755  
Old Posted Jan 13, 2023, 10:36 PM
NicholasHui NicholasHui is offline
Registered User
 
Join Date: Oct 2020
Posts: 39
Update: At Broadway City Hall Station, they have the crane at the site. They also did some pedestrian pattern change as well.

At Oak-VGH Station, they have the pedestrian bridge opened for eastbound pedestrian traffic for direct access through to business and other areas.
Reply With Quote
     
     
  #1756  
Old Posted Jan 13, 2023, 11:03 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,780
Quote:
The traffic deck will be fully complete once additional panels are installed to allow the eastbound bus stop to be relocated in front of the Broadway-City Hall Station entrance.
https://www.broadwaysubway.ca/construction/current-work/
Reply With Quote
     
     
  #1757  
Old Posted Jan 14, 2023, 12:19 AM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,207
TBM pit as of today. The tail end of Phyllis is still being constructed.

The plexiglass had some rain droplets


Photo by me.
Reply With Quote
     
     
  #1758  
Old Posted Jan 14, 2023, 1:51 PM
Hooknose Hooknose is offline
Registered User
 
Join Date: Mar 2017
Posts: 248
I thought Phyllis had launched

Quote:
Originally Posted by madog222 View Post
TBM pit as of today. The tail end of Phyllis is still being constructed.

The plexiglass had some rain droplets


Photo by me.
I thought Phyllis had already launched and was proceeding to Main Street.

How here I see an image where the tail end of Phyllis was still being assembled.

I have to ask, "which is it"?

Is Phyllis moving or is it just "trembling in place"?

I have an inquiring mind.
Reply With Quote
     
     
  #1759  
Old Posted Jan 14, 2023, 3:29 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,780
Quote:
Originally Posted by Hooknose View Post
I thought Phyllis had already launched and was proceeding to Main Street.

How here I see an image where the tail end of Phyllis was still being assembled.

I have to ask, "which is it"?

Is Phyllis moving or is it just "trembling in place"?

I have an inquiring mind.
The tail is probably longer than the pit so as it starts the bore they keep on adding components.
Reply With Quote
     
     
  #1760  
Old Posted Jan 14, 2023, 4:20 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888
Only two more weeks until first bore is supposed to reach Main Street station (project estimate). The excitement builds!!
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 3:12 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.