Some Feb 4 updates at the project website:
https://www.broadwaysubway.ca/construction/current-work/
Emily Carr:
"• February: Continuing bulk excavation; completing water line relocation along Earl Finning Way; completing the relocation of utilities on Carolina Street and E. 1st Ave; beginning the installation of the elevated guideway columns; and conducting geotechnical surveys.
• March - April: Continuing the construction of the elevated guideway columns; commencing station concrete work; and managing the arrival and assembly of the first tunnel boring machine"
Main Street:
"• February: Completing the south side excavation of the road surface; increasing traffic from three to four lanes onto the completed traffic deck; and beginning excavation under traffic deck for the underground station."