broadwaysubway.ca. Some of the work coming up... Broadway going to be a mess for a few months to come. Sounds like eastern stations are the most ahead with decking with each station westward less far along.
Great Northern Way-Emily Carr Station:
• Water line relocation along Earl Finning Way (lot between Emily Carr and Tim Horton's):
Notice and Map
Mount Pleasant Station:
• November – December: Installing the traffic deck on E. Broadway between Main and Quebec streets; beginning excavation on the south side of E. Broadway; and excavating the ventilation shafts on Quebec Street.
• January: Completing the traffic deck; and beginning bulk excavation below the traffic deck.
Broadway City Hall Station:
• November: Removing portions of the centre median between W. 7th and W. 12th avenues; relocating sewer lines beneath Cambie Street between W. 10th Ave and W. Broadway; relocating utilities along W. Broadway between Alberta and Cambie streets; excavating the north side of W. Broadway; building the traffic deck between Alberta and Cambie streets; conducting geotechnical surveys; and installing monitoring devices.
• December – January: Continuing the installation of the traffic deck.
Oak VGH Station:
• November: Relocating utilities during the day and some nights; conducting geotechnical surveys; installing monitoring devices; and relocating sewer lines under the intersections of W. Broadway and Laurel and Oak streets.
• December – February: Continuing to build the traffic deck.
South Granville Station:
• November: Drilling structural supports for the traffic deck; relocating utilities; conducting geotechnical surveys; and installing monitoring devices.
• December – January: Continuing to build the traffic deck.
Arbutus Station:
• November – December: Relocating fire hydrants and utilities; installing temporary light poles; shifting traffic north; closing portions of Maple Street; conducting geotechnical surveys; and starting the drilling of structural supports for the traffic deck.
• January – Spring 2022: Continuing to build the traffic deck.