Quote:
Originally Posted by RetiredGuy
I recall reading one of the counselors asking why the valley line west could not be built so that parts of the line could be active sooner. As the west line is an extension of the east line, could the part say from 102 street to 107 street be put in operation sooner and then other extensions would follow. Is that what will happen or the west line won't be operational until all of it is complete?
|
That won't happen because:
1. the contract is to build the entire thing at once
2. (and here is the bigger issue) the City still needs to figure out how to operate the entire valley line as one entity. The MWLRT is a P3 while the WLRT is more of a traditional model.
Basically the MWLRT is a privately owned line and they're gonna need a 1000 page agreement to merge the two lines operationally.
Honestly it will be a nightmare coming to an agreement between TransEd and ETS once it comes down to operation logistics.
I've heard from teachers in P3 schools where they can't even use push pins on walls because that 'affects' the integrity of the building value.
The City needs to work on the agreement now - else the reality come 4 years from now, without such an agreement, is that the Lewis Estate ETS run train will stop at Alex Decoteau Park and go back towards Lewis Estates again, while the MWTC train will stop at city Centre and head back towards MWTC. That's the reality of these P3 or DBFOT contracts. The consortiums will do everything to protect the value of their infrastructure and investment. The are first and foremost accountable to the shareholders not the stakeholders.