Originally Posted by DKaz
It's just crazy that in the 21 months I've been in Edmonton, there hasn't been a great deal of progress. Downtown Edmonton street crossings complete, elevated guideway mostly complete, and the storage and maintenance facility. But other than that much of downtown Edmonton has been ripped up for forever as with much of the alignment all the way to Millwoods. They need to make it a hard goal to pour all concrete by the end of the year.
|
A lot of progress the last couple of weeks. much of downtown track bed is poured. The section from 97 east to the tunnel is back filled and it appears they are getting the sub base ready for the track base. Winspear section is being worked on again. great sections along the whole length now tarped over. Bridge is about 1/2 way across now.
Looks like they are getting ready for another set of cables.
The Churchill surface platforms are formed and will be getting concrete this week.