Most recent City of Moncton construction update:
PROJECT BY THE NUMBERS:
- In addition to stairs and elevators, the facility is equipped with two escalators to quickly transport spectators from the street level entrance lobby to the upper concourse level.
- The washroom facilities located on the concourse level alone have in total of 68 toilets and 26 urinals, along with three family washrooms.
- A structural steel rigging grid (structure that allows for hoisting or hanging equipment from the building) located in the roof trusses covers more than 2/3 of the arena surface and has a capacity in excess of 100,000 lbs. This allows major events to quickly set up and dismantle their staging equipment.
- Four spotlight platforms are located off the catwalk in the roof trusses to enhance lighting capacity during shows and events.
- Four large main staircases allow people to quickly and safely exit the building.
- Two exterior entrances provide access to the box office and one exterior entrance accesses the merchandizing store allowing for people to visit these areas when the facility is not hosting an event.
- To date, the contractor has recorded over 90,000 man hours worked on site.
- There are approximately 110 tradespersons working onsite daily.
CONSTRUCTION OF THE FACILITY
WHERE ARE WE?
– Approximately 80% of the high dome type bowl roof is installed.
- The structural steel is complete, miscellaneous metals such as interior handrails will continue to be installed for several months.
- The exterior metal siding on the bowl level is being installed on the north side of the building facing Main Street.
- Glass is being installed in the club lounge facing the plaza and the main entrance area facing Main Street.
- The catwalk, which allows access over the event surface, is being installed.
- The mechanical air handling equipment located on the roof tops have begun to arrive on site and are to be placed in position by the end of the month.
- Interior walls have begun on the media level.
- Sprayed on fireproofing material is being applied to the structural steel. This spray maintains required fire separations between building levels and allows the structure to withstand a fire.
- Temporary heat is installed on the event (lowest) level. This will allow the construction work (interior) to continue throughout the winter months.
- The Downtown Centre construction project is currently on schedule.
WHAT IS PLANNED
FOR THE NEXT 4 WEEKS?
- The building will be weather tight allowing work to continue through the winter.
- Exterior siding will continue to be installed on the perimeter of the bowl section.
- Roofing will be completed on the bowl roof.
- Exterior glass will be completed in the club lounge and main entrance.
- Some exterior, but mostly interior masonry work will continue on the event level.
- Water and sewer work will continue on the future street extension (south side of the building facing the rail tracks).
- Sprayed on fireproofing material will continue on the west side (Sobeys) of the building.
- Mechanical and electrical work will continue on all levels.
INTERESTING FACTS
1) There are six windows on the south end of the concourse measuring almost 5m wide and 5m tall. These allow for a view of the Petitcodiac River from the concourse level and enable natural light to flow into the building.
2) A full commercial kitchen is located in the south end of the event (lowest) level. It services the concession stands, club lounge, suites and special events areas. Additionally, there are localized food preparation areas to support the main kitchen.
3) During events, portable concession stands will be used to compliment the permanent concession stands located throughout the concourse level.
4) The club lounge is a two story space starting on the concourse level and extending through the suite level. It has a full glass view overlooking the adjacent plaza and east towards City Hall.
Interesting view of the main entry lobby area.
Future club lounge
East side perspective
Something tells me I'm not going to miss the old Coliseum