Epcor Tower's ground floor poured
The Edmonton Journal
Friday, April 17, 2009

Ken Cantor at the construction site in February; ...
CREDIT: Rick MacWilliam, The Journal

CREDIT: Larry Wong, The Journal, file
... A mockup of the finished tower
Construction on Epcor Tower has reached a lofty milestone -- ground level.
"We poured main-floor slabs last (week)," said Ken Cantor, commercial manager for developer Qualico.
"That's the first main-floor office tower slab to get poured in over 20 years."
Construction of the 28-storey tower, at 10423 101st Street, started in May 2008.
It's the first phase of Qualico's multi-use Station Lands project and Edmonton's first new downtown office highrise since Commerce Place opened in 1990.
Crews excavated a pit where work proceeded on four underground parking levels and an underground portion of the city's northwest light-rail transit line.
"It probably took $50 or $60 million just to get the structure up to grade."
In the next several days, work begins on core walls and main-floor columns.
The tower is scheduled for completion in 2011, but nearly 70 per cent of its office space has been pre-leased by the federal government and Epcor.
Cantor said discussions are ongoing with other prospective tenants. "We're almost at the point where if we brought in another large tenant, we'd probably seriously be looking at the next stage of Station Lands instead of trying to shoehorn them into the Epcor Tower."
That next stage could be another tower or podium space, Cantor said.
© The Edmonton Journal 2009
Copyright © 2009 CanWest Interactive, a division of CanWest MediaWorks Publications, Inc.. All rights reserved.
CanWest Interactive, a division of CanWest MediaWorks Publications, Inc.. All rights reserved.
http://www2.canada.com/components/print.aspx?id=b1b5c90d-b8d5-4078-9ecb-28f57cfaaa85&sponsor=