Quote:
Originally Posted by Stainer View Post
Hey is anyone able to confirm that this foundation going in under the elevated guideway at Fraser and Earl Finning Way is for one of the substations/power feed station?



Also confirming that there are only 2 substations/power feed points, with the other being located at Arbutus?

I haven't been able to find it confirmed in any of the documents that I have.

Cheers
Is that a piece of track with fasteners sitting on the concrete pad on the right side of your photo?

This could be for testing/training/trialing rail installation on both flat and superelevated sections.
Reply With Quote
     
     
  #2922  
Old Posted Aug 18, 2024, 10:55 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,777
And the section on the left is sloped which seems weird. It seems like those sections have been placed there since Spring.

Back in July it seems like they were setting up some kind of of scaffolding for a concrete form hanging off the side of the guideway above where these "foundations" are placed. There's also a gap in those supports above that section.

• Video Link


And back in April it seems like the supports were setup but removed later to do the additional concrete work.

• Video Link
Reply With Quote
     
     
  #2923  
Old Posted Aug 18, 2024, 11:11 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,207
I don't think that is related, the section the protrudes out should be for a switch machine like here:
https://maps.app.goo.gl/LTTF6AqztNfm2e5g6?g_st=ac
Reply With Quote
     
     
  #2924  
Old Posted Aug 19, 2024, 1:32 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,777
Quote:
Originally Posted by madog222 View Post
Is that a piece of track with fasteners sitting on the concrete pad on the right side of your photo?

This could be for testing/training/trialing rail installation on both flat and superelevated sections.
Seems like the most plausible reason. Forming looks similar too



https://x.com/broadwaysubway_/status/1815477506390061162/photo/1
Reply With Quote
     
     
  #2925  
Old Posted Aug 19, 2024, 4:09 AM
Stainer Stainer is offline
Registered User
 
Join Date: Jan 2024
Posts: 57
Quote:
Originally Posted by jollyburger View Post
Seems like the most plausible reason. Forming looks similar too

*snip*

https://x.com/broadwaysubway_/status/1815477506390061162/photo/1
That looks like the most reasonable answer to me, great find!

Reminds me of the smaller one they have at Commercial-Broadway on platforms 3/4 on the east end.

Quote:
Originally Posted by madog222 View Post
I don't think that is related, the section the protrudes out should be for a switch machine like here:
https://maps.app.goo.gl/LTTF6AqztNfm2e5g6?g_st=ac
Was thinking the same thing that this would be for future switch equipment. Looking at it from above it lines up right.

Thanks for your help everyone!
Reply With Quote
     
     
  #2926  
Old Posted Aug 20, 2024, 10:10 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,207
Quote:
Crews are building the train platform at the future South Granville Station.

This is where passengers will wait for their next SkyTrain. The tracks will be built along each side, with the platform in the middle.

https://x.com/broadwaysubway_/status/1825941287083630598
Reply With Quote
     
     
  #2927  
Old Posted Sep 2, 2024, 5:18 AM
Lexus's Avatar
Lexus Lexus is offline
Registered User
 
Join Date: Jul 2018
Location: Vancouver | BC | Canada
Posts: 2,845
2024, Sep 1

Main St.

Untitled by Lexus LX, on Flickr
Reply With Quote
     
     
  #2928  
Old Posted Sep 5, 2024, 8:22 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,207
Reply With Quote
     
     
  #2929  
Old Posted Sep 10, 2024, 8:49 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,777
September newsletter

Quote:
Planned construction activities for the next three months include:

Installing tracks on the elevated guideway;
Constructing the concrete bases that will hold the SkyTrain tracks in the tunnels;
Constructing the walls and columns at all six new underground stations;
Constructing the concourse floor at all six new underground stations;
Constructing the station roof at Great Northern Way-Emily Carr, Mount Pleasant, Broadway-City Hall and Arbutus stations;
Excavating the tail tracks at Arbutus Station; and
Excavating and constructing the underground passenger connections between the Millennium Line extension and the Canada Line at Broadway-City Hall Station.
https://app.webtrackz.com/?q=email/view/14U6K4yY9lOgsO0T9RrdVKbn4S6M05tTPkkI9VYijNbG8LSbgiqv17sg
Reply With Quote
     
     
  #2930  
Old Posted Sep 10, 2024, 9:23 PM
BaddieB BaddieB is offline
Registered User
 
Join Date: Sep 2021
Posts: 653
Budget wise, where is this project in terms of how much money has been spent on it. 40%? 70%?
Reply With Quote
     
     
  #2931  
Old Posted Sep 10, 2024, 9:28 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,207
Quote:
Originally Posted by BaddieB View Post
Budget wise, where is this project in terms of how much money has been spent on it. 40%? 70%?
From the July status report $1.57B has been spent of the $2.827B budget which is 55%.

https://www.broadwaysubway.ca/news-information/monthly-status-reports/
Reply With Quote
     
     
  #2932  
Old Posted Sep 11, 2024, 12:13 AM
BaddieB BaddieB is offline
Registered User
 
Join Date: Sep 2021
Posts: 653
Quote:
Originally Posted by madog222 View Post
From the July status report $1.57B has been spent of the $2.827B budget which is 55%.

https://www.broadwaysubway.ca/news-information/monthly-status-reports/
Thanks! I didn't know these reports existed. It seems like this will be on budget. I don't know how they can burn through a full $1.3B when the tunnels are already bored and the stations are already excavated.
Reply With Quote
     
     
  #2933  
Old Posted Sep 11, 2024, 12:37 AM
dleung's Avatar
dleung dleung is offline
Registered User
 
Join Date: Nov 2009
Location: Toronto
Posts: 6,554
makes it all the more insane that Langley skytrain will cost over double this for 1/4 the ridership
Reply With Quote
     
     
  #2934  
Old Posted Sep 11, 2024, 2:16 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,777
Quote:
Originally Posted by dleung View Post
makes it all the more insane that Langley skytrain will cost over double this for 1/4 the ridership
Field of Dreams build it and they will come. RIP James Earl Jones
Reply With Quote
     
     
  #2935  
Old Posted Sep 11, 2024, 2:48 AM
BaddieB BaddieB is offline
Registered User
 
Join Date: Sep 2021
Posts: 653
Quote:
Originally Posted by dleung View Post
makes it all the more insane that Langley skytrain will cost over double this for 1/4 the ridership
The original Expo Line from Downtown to New West is a good proxy for what the SLS extension will look like. Unless Vancouver decides to massively upzone the 41/49th corridor from Oakridge to Metrotown in exchange for funding that line, I say the SLS is a good use of funds.
Reply With Quote
     
     
  #2936  
Old Posted Sep 11, 2024, 8:13 PM
mcj mcj is offline
Registered User
 
Join Date: Dec 2021
Location: New West
Posts: 1,240
Quote:
Originally Posted by dleung View Post
makes it all the more insane that Langley skytrain will cost over double this for 1/4 the ridership
Langley skytrain is starting procurement/construction in 2024. This started that process in 2019. Almost like something happened in the last 5 years that made things much more expensive...

Perhaps if Dianne Watts didn't try to push the envelope on the idiotic LRT plans, the Langley extension could have nominally costed something similar to this if it were built a decade ago. But should've, could've, would've.
Reply With Quote
     
     
  #2937  
Old Posted Sep 11, 2024, 8:33 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,695
Quote:
Originally Posted by mcj View Post
Langley skytrain is starting procurement/construction in 2024. This started that process in 2019. Almost like something happened in the last 5 years that made things much more expensive...

Perhaps if Dianne Watts didn't try to push the envelope on the idiotic LRT plans, the Langley extension could have nominally costed something similar to this if it were built a decade ago. But should've, could've, would've.
Just wait until the updated budget numbers start coming in for the Massey Tunnel 2.0.
Reply With Quote
     
     
  #2938  
Old Posted Sep 11, 2024, 9:28 PM
chowhou's Avatar
chowhou chowhou is offline
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,868
The SLS is also 2x the price for 3x the distance (elevated vs tunneled however), nearly 2x the stations, and 3x the bus exchanges. Maybe the ridership projections aren't as justifiable, but it's fairly reasonable for it to be 2x the price I'd say.
Reply With Quote
     
     
  #2939  
Old Posted Sep 11, 2024, 9:58 PM
CanSpice's Avatar
CanSpice CanSpice is offline
Registered User
 
Join Date: Dec 2014
Location: New Westminster, BC
Posts: 2,729
Quote:
Originally Posted by chowhou View Post
The SLS is also 2x the price for 3x the distance (elevated vs tunneled however), nearly 2x the stations, and 3x the bus exchanges. Maybe the ridership projections aren't as justifiable, but it's fairly reasonable for it to be 2x the price I'd say.
They have to build an OMC for it too, or is that a separate budget? Does the Broadway Tunnel budget include an OMC?
Reply With Quote
     
     
  #2940  
Old Posted Sep 11, 2024, 10:00 PM
mcj mcj is offline
Registered User
 
Join Date: Dec 2021
Location: New West
Posts: 1,240
Quote:
Originally Posted by CanSpice View Post
They have to build an OMC for it too, or is that a separate budget? Does the Broadway Tunnel budget include an OMC?
OMC is a separate scope for both. OMC4 could be considered the OMC for Broadway, kind of.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 8:31 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.