Quote:
Originally Posted by officedweller
I meant in control of the work (and [with liability for] any delays).
|
Gotcha. Do we know there's any delay overall? The most recent notice (in April) said "Elsie, the first tunnel boring machine (TBM), will be arriving at Broadway-City Hall Station soon and will undergo regular maintenance below the traffic deck in the station area. Concurrently, Phyllis, the second TBM, will be starting her second leg of tunnelling, from Mount Pleasant Station towards Broadway-City Hall Station".
We know Phyllis has now made it to the station, and that the timetable was described in October last year "Tunnel boring activities will take place 24/7 for approximately the next fourteen months during excavation of both tunnels." We're just over half way through that period, and so far they've tunneled about 2 km, with about 3 km to go, so they might still make that schedule. The remaining tunnel is a straight shot down Broadway, (although they could still hit some unexpected geology).