Originally Posted by madog222
Speaking of skytrain noise. The friction modifier program is launching and scheduled to achieve the target CoF in March 2028 (from the attached document).
http://discovery.ariba.com/rfx/15862196
Also, the attached document includes this table breaking down expected travel distance by each car type.
Mark I significantly phased out by 2026 and fully retired by 2027.
Mark II shows a significant change in 2030, I assume that is a retirement of the 200 series (2001) leaving the 300 series (2009) "Mark 2.5" in service.

|
Great find with that table! Cool to see how service on the system overall is going to dramatically increase even as the system gets longer.
Doing the math:
With 61.9km system length for Expo + Millennium currently, increasing to 67.6 with the Broadway subway completed in 2026, and 83.6km with the SLS completed in 2028/2029.
2023:
51/61.9km = 0.823
2026:
72/67.6km = 1.065 or a 29% increase in service per system km over today's usage.
2028/2029:
77/83.6km = 0.921, a 14% decrease over 2026 in service per system km, or a 12% increase over current service per system km.
2032:
91/83.6km = 1.088 or a 32% increase in service per system km over today's usage.