  #241  
Old Posted Dec 26, 2022, 7:43 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
Have moved some of the 25th floor wall forms up on the east side. Still working on forming the 25th floor slab on the west side. Exterior window and cladding has restarted with progress on the south side up to 3rd floor now.
Reply With Quote
     
     
  #242  
Old Posted Jan 31, 2023, 7:20 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
Have now got around half the 25th floor walls and posts poured. The 24th and 25th floors have custom forming and a step back for the 25th floor. Taking more time to complete also due to the weather. They are also up to the 8th floor now installing the exterior windows and cladding.
Reply With Quote
     
     
  #243  
Old Posted Feb 1, 2023, 8:06 PM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 11,998
How many floors will this thing have?
Reply With Quote
     
     
  #244  
Old Posted Feb 1, 2023, 8:12 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
They are on the finishing up last residential floor now - 25
Just the mechanical penthouse left and this is topped out.
https://l360arch.com/signature-downtown-highrise-project-revs-up-core-construction-boom/




Quote:
Originally Posted by ssiguy View Post
How many floors will this thing have?
Reply With Quote
     
     
  #245  
Old Posted Feb 5, 2023, 4:43 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
They have moved up some of the wall forming for the mechanical penthouse now on the east side. This is just weeks away from being topped out.
Reply With Quote
     
     
  #246  
Old Posted Mar 5, 2023, 8:24 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
Some structural steel now up for the mechanical penthouse. Exterior windows and cladding is slowly going on and they are now up over the 10th floor.
Reply With Quote
     
     
  #247  
Old Posted Mar 29, 2023, 5:14 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
Looks like the last of the concrete forming of walls and posts on the mechanical penthouse is done now. Structural steel has been going on and today it looked like they were lifting a elevator motor assembly into place. Should see the HVAC chiller lifted and installed into place soon and the penthouse exterior sheeting soon afterwards. They are more then halfway now with the exterior windows and balcony door cladding installation.
Reply With Quote
     
     
  #248  
Old Posted Apr 11, 2023, 3:24 PM
johnnyhamont's Avatar
johnnyhamont johnnyhamont is offline
Registered User
 
Join Date: Dec 2015
Posts: 1,116
Photo from last week on Flickr. Nice to see this at full height!

Reply With Quote
     
     
  #249  
Old Posted Apr 18, 2023, 6:19 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
They had the tree topping ceremony for the mechanical penthouse roof.
About 60% of the exterior windows and cladding now installed.
Reply With Quote
     
     
  #250  
Old Posted May 11, 2023, 1:49 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,772
Drove by this project yesterday and they have installed quite a bit of the cladding now. This has to be one of the best projects I've seen in London in a while. It's very central in the downtown, replaces a parking lot and it looks taller than it really is because it is so slender. Fingers crossed that all three towers are built.
Reply With Quote
     
     
  #251  
Old Posted May 11, 2023, 7:10 PM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 11,998
I'm surprised they haven't already started the other 2 buildings. With vacancies so low and the population soaring, you would think they would go ahead.
Reply With Quote
     
     
  #252  
Old Posted May 11, 2023, 7:25 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,772
Quote:
Originally Posted by ssiguy View Post
I'm surprised they haven't already started the other 2 buildings. With vacancies so low and the population soaring, you would think they would go ahead.
I'm guessing because of higher interest rates and banks reluctant to lend in this economy.
Reply With Quote
     
     
  #253  
Old Posted May 11, 2023, 9:23 PM
Djeffery's Avatar
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,363
And the guy building it isn't a Tricar or Old Oak size company. As far as I know, the only other thing he has built is the reservoir hill building. He probably doesn't have the financial capacity to build more than one at a time. Hopefully with 2 complete buildings generating cash flow that the bank will finance him being able to build the other 2 as it would be a huge pain I think to do those one at a time.
Reply With Quote
     
     
  #254  
Old Posted May 11, 2023, 9:59 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
I would be surprised if the current working space isn't cleaned up and fresh pavement put down and returned to parking use for a number of years. Ayerswood financed the first 25s tower before the interest rate climb and inflation hit. Phase 2 is supposed to be even taller and more expensive to build and financing it will be a lot tougher. I am going to be very interested to see the leasing rate on this first building. How many units will sit vacant this time next year will be telling.
Reply With Quote
     
     
  #255  
Old Posted May 13, 2023, 4:37 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
Looks like they have finally lifted the rooftop HVAC chillers to the mechanical penthouse. Took a while. Should see them finally enclosing the penthouse walls soon.
Reply With Quote
     
     
  #256  
Old Posted May 21, 2023, 3:14 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
They have now got the windows and cladding on the west side installed upto the 24th floor. Still working on the mechanical penthouse.
Reply With Quote
     
     
  #257  
Old Posted Jun 7, 2023, 8:17 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
They are making good progress installing the exterior cladding on the mechanical penthouse enclosing it from the elements. Continuing to install the window and exterior cladding on the south side now.
Reply With Quote
     
     
  #258  
Old Posted Jun 13, 2023, 5:35 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
This news report has nice photo of the top of the building.


https://london.ctvnews.ca/controversy-ar...t-grant-falls-short-of-support-1.6438739
Reply With Quote
     
     
  #259  
Old Posted Jun 14, 2023, 1:40 PM
Blitz's Avatar
Blitz Blitz is offline
Registered User
 
Join Date: Jul 2001
Location: Windsor, Ontario
Posts: 4,634
Here's a look at the progress of the 3 new towers downtown.

Reply With Quote
     
     
  #260  
Old Posted Jun 14, 2023, 2:02 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,531
Nice photo and also captures the heavy lift crane being used to install the new Ridout bridge structure.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 3:40 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.