LRT
● Valley Line Southeast
○ The project is delayed as TransEd finalizes a repair design for the piers.
○ TransEd is fully responsible for all repairs, including all costs.
● Valley Line West
○ Construction is well underway.
○ Crews spent most of 2022 preparing two key areas: Lewis Farms Storage
Facility & Transit Centre and the area along 87 Avenue that will be home to an elevated guideway near West Edmonton Mall and the Misericordia Hospital.
● Capital Line South extension
○ Early works are underway (mainly near 23 Avenue/111 Street).
○ In early 2023, the City is planning to release the RFP for the design-build
contract.
○ Major construction is anticipated to start in 2024.
○ The Phase 1 extension is anticipated to open in 2028.
● Metro Line Northwest extension
○ Crews made significant progress this season on Phase 1 (NAIT to Blatchford).
○ Solar panels will be installed later this year on the two new stations in
Blatchford.
● LRT Renewal
○ Crews completed a number of renewal projects this year, including the Century Park Station platform renewal.
○ Crews are performing elevator upgrades at Bay, Corona, Central and University Stations, as well as escalator replacements at Central Station.
○ The Stadium Station Redevelopment project is nearing completion.
https://www.edmonton.ca/sites/default/fi...eet-2022-Construction-Season-Wrap-Up.pdf