Quote:
Originally Posted by officedweller View Post
But you are right in that it'll be complicated to restart the tunnel for the UBC extension since it doesn't allow them to "bury" the TBMs for future restart (but the TBMs could just be rented anyways).
That's my issue right there (and it's practically a given the TBMs will be rented and not buried for future use). There won't be the option of continuing from Arbutus towards UBC, and how are they going to start at UBC / Jericho and then dig them out without causing problems at / near Arbutus station? I would have through they'd tunnel somewhat past Arbutus to minimize future disruptions.
Reply With Quote
     
     
  #1262  
Old Posted Apr 23, 2022, 4:14 AM
dpogue dpogue is offline
Registered User
 
Join Date: Aug 2013
Posts: 767
Quote:
Originally Posted by Sheba View Post
I find that confusing as Cypress Street is two blocks *before* Arbutus. You'd think they would tunnel past Arbutus to make it easier when they continue the tunnel to UBC.
There is a set of track switches just east of Arbutus station to allow for turning trains around. They're going to excavate the space required for those as part of the station block, rather than building the two tunnels and then needing to somehow excavate between them.
Reply With Quote
     
     
  #1263  
Old Posted Apr 23, 2022, 4:38 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,705
Quote:
Originally Posted by Sheba View Post
That's my issue right there (and it's practically a given the TBMs will be rented and not buried for future use). There won't be the option of continuing from Arbutus towards UBC, and how are they going to start at UBC / Jericho and then dig them out without causing problems at / near Arbutus station? I would have through they'd tunnel somewhat past Arbutus to minimize future disruptions.
Seems doubtful that they are rented. Most TBMs have 10,000 lifespans and while they might sell back some of the equipment back to the supplier/recycled it seems more likely they bought them. Each one costs probably around $20 million?

Quote:
That is why Herrenknecht – if so agreed – buys back the valuable components of the deployed machines from customers after tunnelling is completed in order to professionally rebuild them. This is particularly beneficial for many joint ventures, which do not really need the equipment purchased together for the duration of the project once it has ended. The bought back components are then rebuilt in Herrenknecht's rebuilding plant at various levels of quality, depending on the requirements of the next project. Remanufacturing is the highest level, the best way to preserve the existing value of these components and bring them to a completely new life cycle.
https://allaround.herrenknecht.com/en/is...ues-together/premium-by-definition.popup
Reply With Quote
     
     
  #1264  
Old Posted Apr 23, 2022, 7:10 AM
Tvisforme's Avatar
Tvisforme Tvisforme is offline
Registered User
 
Join Date: Sep 2014
Location: Metro Vancouver
Posts: 2,158
A couple of thoughts with respect to the TBMs:

- the brief mention about tunneling to Cypress doesn't preclude carrying on for a short distance west of Arbutus and parking the TBMs until the UBC phase begins construction. There's no reason to mention it in a news release since the only people who really care about those details are on sites like this one.

- even if they are currently planning to only go as far as Cypress, there's a lot of time between now and when tunnelling is complete. Odds are we'll have a much better idea about the UBC extension before then and the plans can be adjusted.
Reply With Quote
     
     
  #1265  
Old Posted Apr 23, 2022, 7:52 AM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,181
Quote:
Originally Posted by Tvisforme View Post
A couple of thoughts with respect to the TBMs:

- the brief mention about tunneling to Cypress doesn't preclude carrying on for a short distance west of Arbutus and parking the TBMs until the UBC phase begins construction. There's no reason to mention it in a news release since the only people who really care about those details are on sites like this one.

- even if they are currently planning to only go as far as Cypress, there's a lot of time between now and when tunnelling is complete. Odds are we'll have a much better idea about the UBC extension before then and the plans can be adjusted.
TMBs can't just be "parked" underground, they require the open tunnel for transportation of spoil and wall segments. They would also require a full overhaul if left alone for potentially 10 years.
Reply With Quote
     
     
  #1266  
Old Posted Apr 23, 2022, 4:37 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,705
Quote:
Originally Posted by Tvisforme View Post
A couple of thoughts with respect to the TBMs:

- the brief mention about tunneling to Cypress doesn't preclude carrying on for a short distance west of Arbutus and parking the TBMs until the UBC phase begins construction. There's no reason to mention it in a news release since the only people who really care about those details are on sites like this one.

- even if they are currently planning to only go as far as Cypress, there's a lot of time between now and when tunnelling is complete. Odds are we'll have a much better idea about the UBC extension before then and the plans can be adjusted.
They specifically have mentioned it being removed from the tunnel in all their press releases. You can't just park a TBM underground for a few years and magically restart it. And you'll still have to deal with a pit at Arbutus to remove all the dirt/store tunneling lining (assuming you are planning on finishing the subway while they finish the extension to UBC).
Reply With Quote
     
     
  #1267  
Old Posted Apr 23, 2022, 4:56 PM
Tvisforme's Avatar
Tvisforme Tvisforme is offline
Registered User
 
Join Date: Sep 2014
Location: Metro Vancouver
Posts: 2,158
Quote:
Originally Posted by jollyburger View Post
They specifically have mentioned it being removed from the tunnel in all their press releases. You can't just park a TBM underground for a few years and magically restart it. And you'll still have to deal with a pit at Arbutus to remove all the dirt/store tunneling lining (assuming you are planning on finishing the subway while they finish the extension to UBC).
Sorry, my bad, I completely missed the last line of the release quoted in this thread. In terms of storing, I was thinking about a situation where the decision to start the UBC extension is made while the Broadway subway is still under construction, and not not keeping it there on spec. That should have been made more clear in my post.

Is it possible that they will dig (by other means) at least a few dozen metres or more past the western end of the Arbutus station given the likelihood of a UBC project? Otherwise, even if you come from the west, you're still looking at a lot of disruption to Arbutus Station when the tunnels connect. It is hard to imagine closing that station for an extended period once new travel patterns have been extablished.
Reply With Quote
     
     
  #1268  
Old Posted Apr 23, 2022, 5:26 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,705
Quote:
Originally Posted by Tvisforme View Post
Sorry, my bad, I completely missed the last line of the release quoted in this thread. In terms of storing, I was thinking about a situation where the decision to start the UBC extension is made while the Broadway subway is still under construction, and not not keeping it there on spec. That should have been made more clear in my post.

Is it possible that they will dig (by other means) at least a few dozen metres or more past the western end of the Arbutus station given the likelihood of a UBC project? Otherwise, even if you come from the west, you're still looking at a lot of disruption to Arbutus Station when the tunnels connect. It is hard to imagine closing that station for an extended period once new travel patterns have been extablished.
The only problem in that scenario is that they would still need to do all the geotechnical work for the tunnel and not sure if they can do it without the station blocks pre-built or not.

You assume that they will build out the system to accommodate the extension without any long-term disruptions at Arbutus (I think that's why they've mentioned the Jericho Lands as the staging ground for the TBMs)
Reply With Quote
     
     
  #1269  
Old Posted Apr 23, 2022, 5:37 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,705
This document has the best description of the plans for west of Arbutus (not sure if they've changed it). Didn't see any diagrams with the switches east of the station that someone mentioned previously.

Quote:
Once the Tunnel Boring Machines are removed, the final stretch of the tunnel between Cypress and Arbutus will be excavated with mining equipment. A tail track that extends underground west of Arbutus Street will also be mined. The tail track allows trains to park off the main line and switch to the opposite side of the track. This work will be completed entirely underground.
https://www.broadwaysubway.ca/app/upload...on-Overview-Arbutus-v03-20211123-WEB.pdf
Reply With Quote
     
     
  #1270  
Old Posted Apr 23, 2022, 5:38 PM
Changing City's Avatar
Changing City Changing City is offline
Registered User
 
Join Date: Nov 2016
Posts: 8,257
Quote:
Originally Posted by jollyburger View Post
The only problem in that scenario is that they would still need to do all the geotechnical work for the tunnel and not sure if they can do it without the station blocks pre-built or not.

You assume that they will build out the system to accommodate the extension without any long-term disruptions at Arbutus (I think that's why they've mentioned the Jericho Lands as the staging ground for the TBMs)
They will presumably also have to tender the construction of the extension. There's no guarantee it would be the same contractor for the tunneling, and a different contractor would make their own equipment arrangements.

There wouldn't seem to be a major problem in running the boring machine from Jericho to the end of the Arbutus tail track, extracting it, reassembling it and then starting again at Jericho, going west. It adds to the cost somewhat, but reduces the complexity overall. There would have to be a surface extraction pit at, or near Arbutus, and maybe a bit of cut-and-cover (or mined, as they're currently planning) if they stop short of the station box, but I assume that's all do-able.
__________________
Contemporary Vancouver development blog, https://changingcitybook.wordpress.com/ Then and now Vancouver blog https://changingvancouver.wordpress.com/
Reply With Quote
     
     
  #1271  
Old Posted Apr 23, 2022, 5:45 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,705
Sounds like the tail tracks are east of the station though. But you assume they will mine out to the West of Arbutus.
Reply With Quote
     
     
  #1272  
Old Posted Apr 23, 2022, 5:45 PM
Tvisforme's Avatar
Tvisforme Tvisforme is offline
Registered User
 
Join Date: Sep 2014
Location: Metro Vancouver
Posts: 2,158
Quote:
Originally Posted by jollyburger View Post
This document has the best description of the plans for west of Arbutus (not sure if they've changed it). Didn't see any diagrams with the switches east of the station that someone mentioned previously.



https://www.broadwaysubway.ca/app/upload...on-Overview-Arbutus-v03-20211123-WEB.pdf
Thanks!
Reply With Quote
     
     
  #1273  
Old Posted Apr 23, 2022, 9:55 PM
swimmer_spe swimmer_spe is offline
BANNED
 
Join Date: Apr 2014
Posts: 10,743
Quote:
Originally Posted by madog222 View Post
TMBs can't just be "parked" underground, they require the open tunnel for transportation of spoil and wall segments. They would also require a full overhaul if left alone for potentially 10 years.
By the time the tunneling stops, could we see the extension from UBC approved and see the TBMs refitted and used for the next phase?
Would it save any money?
Reply With Quote
     
     
  #1274  
Old Posted Apr 23, 2022, 11:01 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,712
The graphic I posted states removal of the TBM at the road deck at Cypress.

TBM removal seems to be possible in tight spaces - like was done for Canada Line.
Reply With Quote
     
     
  #1275  
Old Posted Apr 24, 2022, 6:17 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888
Quote:
Originally Posted by madog222 View Post
TMBs can't just be "parked" underground, they require the open tunnel for transportation of spoil and wall segments. They would also require a full overhaul if left alone for potentially 10 years.
Here's my dream: prov/feds find half-a-billion under the mattress or something and they just continue drilling westward from Arbutus. Use Shell gas station on NW corner of Broadway and Arbutus and maybe the two storey property to the west of that as a new western location for spoil removal and tunnel segments as they continue to drill.

Then at Alma and Broadway they could use the former gas station site on the SE corner to remove the TBM or what not.

Couldn't make it much further than that for $500m I'm assuming but at least the hard part, the drilling would be done, figure out the station, track laying, etc money later.

I mean come on, the TBM will be right there at Broadway and Arbutus, keep the party rolling. It'll be a long time before they can get the $2B-$3B+ together to extend all the way to UBC. It'd be more likely to happen by splitting it up, which isn't everyone's favourite solution, but more west is still more best.
Reply With Quote
     
     
  #1276  
Old Posted Apr 24, 2022, 6:26 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888
Traffic deck completed at Main Street. Anyone around there for pictures?

https://www.broadwaysubway.ca/construction/current-work/

"On the night of April 19, the traffic deck will be completed, and four lanes of traffic will be opened on E. Broadway between Main and Quebec streets.
Upon completion on the morning of April 20, the traffic deck will have four lanes (2 westbound, 2 eastbound"
Reply With Quote
     
     
  #1277  
Old Posted Apr 24, 2022, 6:37 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,181
Quote:
Originally Posted by Jimbo604 View Post
Traffic deck completed at Main Street. Anyone around there for pictures?

https://www.broadwaysubway.ca/construction/current-work/

"On the night of April 19, the traffic deck will be completed, and four lanes of traffic will be opened on E. Broadway between Main and Quebec streets.
Upon completion on the morning of April 20, the traffic deck will have four lanes (2 westbound, 2 eastbound"
I would if I was in town, to keep up I have been following on CoV traffic cameras.

https://trafficcams.vancouver.ca/mainBroadway.htm
Reply With Quote
     
     
  #1278  
Old Posted Apr 24, 2022, 7:55 PM
Nicholas Hui Nicholas Hui is offline
Registered User
 
Join Date: Oct 2020
Posts: 12
If you go to YouTube, the latest video about the Broadway Subway station construction was on April 17, 2022. These YouTube videos were uploaded by Hello World
Reply With Quote
     
     
  #1279  
Old Posted Apr 26, 2022, 9:23 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,181
Traffic deck at Oak is now open, straight to four lanes though one turns into a left turn lane at Oak. I'm guessing they will expand to five lanes wide on the west end.


Image from BC Moti https://www.flickr.com/photos/tranbc/52031944084/in/dateposted/
Reply With Quote
     
     
  #1280  
Old Posted Apr 26, 2022, 10:02 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,705
They couldn't make it a little wider?
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 11:12 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.