Looks like they made a lot of progress this week. Basement wall forming is up for a good chunk of the site.

Ritsman looking like your February or March grade level prediction might be a bit pessimistic. Should be quite a bit sooner than that.

Reply With Quote
     
     
  #362  
Old Posted Nov 20, 2021, 3:17 PM
Markus83's Avatar
Markus83 Markus83 is offline
Registered User
 
Join Date: May 2015
Location: Hamilton
Posts: 478
Quote:
Originally Posted by TheHonestMaple View Post
That's actually an old picture of Marquee Residence. Was hurting my brain there for a sec trying to figure out from where that picture was taken haha, realized it wasn't McMaster Grad Residences.
Ohh SHit you're right LoL!
Reply With Quote
     
     
  #363  
Old Posted Nov 20, 2021, 5:32 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Taken November 20, 2021.

They made significant progress this week. Wall forming has gone up on the east side of the site. This project should reach grade level quite soon at this pace.



Reply With Quote
     
     
  #364  
Old Posted Nov 21, 2021, 2:59 AM
Beedok Beedok is offline
Exiled Hamiltonian Gal
 
Join Date: Jun 2012
Posts: 6,829
The urban fabric really is healing so dramatically with all the parking that’s filling in.
Reply With Quote
     
     
  #365  
Old Posted Nov 25, 2021, 3:30 PM
Wigs's Avatar
Wigs Wigs is offline
Great White North
 
Join Date: Nov 2003
Location: Niagara Region
Posts: 15,465
Quote:
Originally Posted by Beedok View Post
The urban fabric really is healing so dramatically with all the parking that’s filling in.
Love to see it, Hamilton!
Reply With Quote
     
     
  #366  
Old Posted Nov 25, 2021, 6:03 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Taken today. Notice the removable floor forms sitting in a pile at the bottom of the image and on the truck to the left. This should be at grade level very soon.

Reply With Quote
     
     
  #367  
Old Posted Nov 25, 2021, 7:12 PM
LikeHamilton's Avatar
LikeHamilton LikeHamilton is offline
Registered User
 
Join Date: Apr 2006
Location: Hamilton, Ontario
Posts: 2,756
Quote:
Originally Posted by TheHonestMaple View Post
Taken today. Notice the removable floor forms sitting in a pile at the bottom of the image and on the truck to the left. This should be at grade level very soon.

I do like the row of cranes in this picture. Be even better when there is a 5th one.
Reply With Quote
     
     
  #368  
Old Posted Nov 26, 2021, 10:00 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Floor forms have begun to be installed today. I suspect the ground level floor slab on the east side of the site will be poured sometime next week.

I also noticed that more parts of the second crane have been brought to site. Maybe that will go up next week as well.

Crazy how fast this project has been moving compared to Cobalt Residences.

Reply With Quote
     
     
  #369  
Old Posted Dec 3, 2021, 4:00 PM
Markus83's Avatar
Markus83 Markus83 is offline
Registered User
 
Join Date: May 2015
Location: Hamilton
Posts: 478
Taken yesterday. December 2, 2021 - Looks to be almost there at full grade.









Reply With Quote
     
     
  #370  
Old Posted Dec 3, 2021, 4:04 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
I guess your prediction was a little off Ritsman
Reply With Quote
     
     
  #371  
Old Posted Dec 3, 2021, 4:21 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Quote:
Originally Posted by TheHonestMaple View Post
I guess your prediction was a little off Ritsman
Its going a bit faster than I was expecting. I'll stick with prediction though that it won't fully be at grade until February (Feb 1) to give me as much time to be right. I'd be happy to eat my prediction though and split the difference between our predictions!
__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3...SIZNGfD4A&s=09

Last edited by TheRitsman; Dec 3, 2021 at 5:16 PM.
Reply With Quote
     
     
  #372  
Old Posted Dec 3, 2021, 4:27 PM
Markus83's Avatar
Markus83 Markus83 is offline
Registered User
 
Join Date: May 2015
Location: Hamilton
Posts: 478
LoL
Reply With Quote
     
     
  #373  
Old Posted Dec 3, 2021, 5:45 PM
urban_planner urban_planner is offline
Registered User
 
Join Date: Feb 2009
Posts: 822
I'm surprised we haven't seen that other crane up yet.
__________________
I think its the best city of its size on earth.
Reply With Quote
     
     
  #374  
Old Posted Dec 3, 2021, 6:53 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Quote:
Originally Posted by urban_planner View Post
I'm surprised we haven't seen that other crane up yet.
They seem to be doing this one in an odd manner. They had majority of the "raft" (thanks David, did a bit of research about that function) done for the tower portion, but were still digging dirt out where the parking lot will be until a few days ago, and may still be going.

Edit: just walked past and the excavator is still in the hole which tells me there is a bit more to dig up.
__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3...SIZNGfD4A&s=09

Last edited by TheRitsman; Dec 3, 2021 at 7:33 PM.
Reply With Quote
     
     
  #375  
Old Posted Dec 3, 2021, 8:04 PM
Innsertnamehere's Avatar
Innsertnamehere Innsertnamehere is online now
Registered User
 
Join Date: Jan 2010
Location: Hamilton
Posts: 12,731
Focusing on the tower side of the project as that is the critical path to completion. The podium can play catch-up later.
Reply With Quote
     
     
  #376  
Old Posted Dec 3, 2021, 8:07 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Wouldn't even be surprised if this one overtakes Cobalt.
Reply With Quote
     
     
  #377  
Old Posted Dec 5, 2021, 5:25 PM
TheHonestMaple's Avatar
TheHonestMaple TheHonestMaple is offline
Registered User
 
Join Date: Aug 2016
Posts: 1,833
Taken December 5, 2021.





Reply With Quote
     
     
  #378  
Old Posted Dec 20, 2021, 4:32 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Second crane is started:





__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3...SIZNGfD4A&s=09
Reply With Quote
     
     
  #379  
Old Posted Dec 21, 2021, 4:04 PM
TheRitsman TheRitsman is offline
Registered User
 
Join Date: Sep 2017
Location: Hamilton
Posts: 3,055
Second crane is fully up. Too bad it's like a week after Platinum's came down since the crane count hasn't changed as a result.

__________________
Hamilton Downtown. Huge tabletop skyline fan. Typically viewing the city from the street, not a helicopter. Cycling, transit and active transportation advocate 🚲🚍🚋

Follow me on Twitter: https://x.com/ham_bicycleguy?t=T_fx3...SIZNGfD4A&s=09
Reply With Quote
     
     
  #380  
Old Posted Dec 21, 2021, 5:07 PM
johnnyhamont's Avatar
johnnyhamont johnnyhamont is offline
Registered User
 
Join Date: Dec 2015
Posts: 1,115
Ritsman, this is going to be an amazing vantage point from which to get progress shots over the course of this project! Once it rises above the King St storefronts, you'll have to collect monthly photos in a powerpoint or something and share that when the project is done.

Quote:
Originally Posted by TheRitsman View Post
Second crane is fully up. Too bad it's like a week after Platinum's came down since the crane count hasn't changed as a result.

Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Hamilton > Downtown & City of Hamilton
Forum Jump



Forum Jump


All times are GMT. The time now is 2:39 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.