Quote:
Originally Posted by J.OT13
Going back to this quote, and I really don't want to re-open the Bank Street debate on the Confed thread, but you made it seem like heavy rail subway and underground light-metro was basically the same price on that fantasy thread, so which is it?
|
We were discussing a comparison to surface running LRT as the alternative. From that perspective whether you build a $250M/km light metro or $300M/km heavy rail metro underground, it really isn't going to change the reality that surface LRT would be $80-100M/km (and on the lower end if cars are removed entirely).
With regards to the Confederation Line, the difference would have been really close to a wash, given that we have 3 underground stations that could have gone down to 80m platforms.
Quote:
Originally Posted by J.OT13
Ottawa had a very tight budget to work with. Toronto (or Metrolinx in the case of the Ontario Line) basically has a blank cheque. The original plan was a heavy rail subway and Ford came in proposing the Ontario Line. Maybe scaling back the project from fully underground heavy rail allowed for climate controlled stations and a longer route.
|
Budgets have very little to do with this. Metrolinx changed the concept from using existing heavy rail subway cars because they figured out that smaller trains at higher frequencies gave them the same capacity, while reducing station boxes to smaller than any TTC station today. The climate conditioning is an added bonus. The big difference that Ford brought in was a willingness to remove rolling stock compatibility from the rest of the TTC network. It's likely that in due course the rest of the TTC network will be upgraded to allow for the same rolling stock.
I would argue Ottawa could have done the same and built a light metro. Any climate conditioning would have been a really easy bonus. Heck, worst case scenario, the sacrificed Tunney's Pasture in Stage 1 to pay for it. I would bet money, once it was built, the enthusiasm to expand would have made up any lost ground anyway.
Quote:
Originally Posted by J.OT13
I'm of the opinion that a light-metro with full automation and shorter platforms would have been better than what we built. I don't think platform screen doors and climate control is the end all be all.
|
Nobody ever suggested it was "the end all be all". But the thinking process that led to our bureaucrats basically ignoring what are now norms on most new systems or new lines, is what we should worry about. It will undoubtedly lead to similarly bad decisions in the future.
Quote:
Originally Posted by J.OT13
Nice to have, but I see dollar signs. Neither of us claim to be transit costing experts, so we'll have to agree to disagree on this one.
|
REM: ~$7B for 67km and 26 fully enclosed climate controlled stations.
O-Train: ~$7B for 65km and 41 stations.
But REM has had to build so much more in grade separation from scratch than OC Transpo built in Ottawa. So I am not sure the cost argument really holds.
Quote:
Originally Posted by bradnixon
There's probably a bunch of ways it could have been better- everything can always be better. But hand-wringing about the system that we have and acting as though we could have had some kind of magical, perfect system where $ is no object is silly.
|
Poor decisions are never random. They are usually the result of a corporate culture and decision making process that leads to such. Automatically writing off something as expensive with no investigation is an example of this.
Like I wrote earlier, I attended some of the pre-definition public consultations for the LRT before it even had a name, in the O'Brien era. At the time, one of the potential bidders kinkisharyo specifically suggested a light metro system, enclosed stations, etc. It is amazing to me that they understood what we needed, told us, and then our spec writers completely ignored all of that, based on the vague idea that we would run LRT on suburban avenues.