Quote:
Originally Posted by OTA in Winnipeg View Post
^Is that a fin I see on the west side as well?
Yes
Reply With Quote
     
     
  #5862  
Old Posted Jan 13, 2021, 6:17 PM
buzzg buzzg is offline
Registered User
 
Join Date: Apr 2013
Posts: 7,834
Is this Winnipeg's first non-value engineered fin?!?! Seems like every project has one in the render and they never get built...
Reply With Quote
     
     
  #5863  
Old Posted Jan 13, 2021, 6:45 PM
Wigglez's Avatar
Wigglez Wigglez is offline
Source?
 
Join Date: Sep 2008
Location: Winnipeg
Posts: 662
Quote:
Originally Posted by buzzg View Post
Is this Winnipeg's first non-value engineered fin?!?! Seems like every project has one in the render and they never get built...
Why do you think this project is taking so long, all of those fin physics needed to be assessed by a team of experts!
Reply With Quote
     
     
  #5864  
Old Posted Jan 13, 2021, 8:00 PM
dmacc dmacc is offline
Registered User
 
Join Date: Dec 2017
Location: Winnipeg
Posts: 1,712
Quote:
Originally Posted by CraneHoss View Post
Prep on the 14th. Jacking on the 15th.
Hope we're still on track!!!
Reply With Quote
     
     
  #5865  
Old Posted Jan 13, 2021, 10:45 PM
Malcsta's Avatar
Malcsta Malcsta is offline
Incurable optimist
 
Join Date: Apr 2020
Location: Winnipeg
Posts: 279
Theyre taking the tarps down!!!!! This must mean something
Reply With Quote
     
     
  #5866  
Old Posted Jan 14, 2021, 1:18 PM
OTA in Winnipeg OTA in Winnipeg is offline
Registered User
 
Join Date: Mar 2016
Location: Silver Heights
Posts: 1,798






Reply With Quote
     
     
  #5867  
Old Posted Jan 14, 2021, 2:44 PM
Biff's Avatar
Biff Biff is offline
What could go wrong?
 
Join Date: Jun 2004
Location: Winnipeg
Posts: 9,938
Quote:
Originally Posted by Malcsta View Post
Theyre taking the tarps down!!!!! This must mean something
It means the tarps will no longer be up.
Reply With Quote
     
     
  #5868  
Old Posted Jan 14, 2021, 3:29 PM
DonaldSmith's Avatar
DonaldSmith DonaldSmith is offline
Registered User
 
Join Date: Oct 2012
Location: Wpg, Mb
Posts: 433
FYI crane sections are on site this AM.
Reply With Quote
     
     
  #5869  
Old Posted Jan 14, 2021, 3:33 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,373
They still have to move the crane jump section to the top and install the bracing to the building. So maybe not today.

Looks like there may be a person inside the jump section right now, but it's hard to tell in the image.
Reply With Quote
     
     
  #5870  
Old Posted Jan 14, 2021, 3:34 PM
buzzg buzzg is offline
Registered User
 
Join Date: Apr 2013
Posts: 7,834
Earls is still on track for Feb 1 move-in. It's interesting, they said everything is ahead of schedule compared to what they were initially told.
Reply With Quote
     
     
  #5871  
Old Posted Jan 14, 2021, 5:26 PM
borkborkbork's Avatar
borkborkbork borkborkbork is offline
Registered User
 
Join Date: Jul 2014
Posts: 1,761
Quote:
Originally Posted by buzzg View Post
Is this Winnipeg's first non-value engineered fin?!?! Seems like every project has one in the render and they never get built...
ray wan's lifelong dream has been fulfilled
Reply With Quote
     
     
  #5872  
Old Posted Jan 14, 2021, 6:18 PM
WinCitySparky's Avatar
WinCitySparky WinCitySparky is offline
Registered User
 
Join Date: Jan 2019
Posts: 2,416
Quote:
Originally Posted by buzzg View Post
Earls is still on track for Feb 1 move-in. It's interesting, they said everything is ahead of schedule compared to what they were initially told.
The space still has a significant amount of work left to have it be occupiable. Their fit up crews may be coming in Feb 1 but it sure won’t be even close to the finishing stages. Building power isn’t even on yet.
Reply With Quote
     
     
  #5873  
Old Posted Jan 14, 2021, 6:25 PM
buzzg buzzg is offline
Registered User
 
Join Date: Apr 2013
Posts: 7,834
Quote:
Originally Posted by WinCitySparky View Post
The space still has a significant amount of work left to have it be occupiable. Their fit up crews may be coming in Feb 1 but it sure won’t be even close to the finishing stages. Building power isn’t even on yet.
That's what I mean, they're getting the keys.
Reply With Quote
     
     
  #5874  
Old Posted Jan 14, 2021, 7:02 PM
Biff's Avatar
Biff Biff is offline
What could go wrong?
 
Join Date: Jun 2004
Location: Winnipeg
Posts: 9,938
The crane tether (anchor) is going in now. Raise mechanism is....raised.
Reply With Quote
     
     
  #5875  
Old Posted Jan 14, 2021, 8:22 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,373
How many levels is the building going to have? 40 or 42? Thread title says 42 but I thought that changed.
Reply With Quote
     
     
  #5876  
Old Posted Jan 14, 2021, 8:23 PM
3de14eec6a 3de14eec6a is offline
Registered User
 
Join Date: Jan 2016
Posts: 206
Quote:
Originally Posted by Biff View Post
The crane tether (anchor) is going in now. Raise mechanism is....raised.
You deserve a raise for raising awareness of this.
Reply With Quote
     
     
  #5877  
Old Posted Jan 14, 2021, 9:49 PM
Winnipegger Winnipegger is offline
Registered User
 
Join Date: May 2007
Location: Winnipeg
Posts: 837
Quote:
Originally Posted by bomberjet View Post
How many levels is the building going to have? 40 or 42? Thread title says 42 but I thought that changed.
As per the original rumour, the building has been capped at 20 stories. The parts above 20 stories in all the pictures posted here are due to holograms.
Reply With Quote
     
     
  #5878  
Old Posted Jan 14, 2021, 10:08 PM
drew's Avatar
drew drew is offline
the first stamp is free
 
Join Date: Feb 2004
Location: Hippyville, Winnipeg
Posts: 8,930
Quote:
Originally Posted by bomberjet View Post
How many levels is the building going to have? 40 or 42? Thread title says 42 but I thought that changed.
IIRC:

40th floor is the last residential (occupied) floor.

41 and 42 are mechanical floors.
Reply With Quote
     
     
  #5879  
Old Posted Jan 14, 2021, 10:28 PM
WinCitySparky's Avatar
WinCitySparky WinCitySparky is offline
Registered User
 
Join Date: Jan 2019
Posts: 2,416
Quote:
Originally Posted by drew View Post
IIRC:

40th floor is the last residential (occupied) floor.

41 and 42 are mechanical floors.
Yup
Reply With Quote
     
     
  #5880  
Old Posted Jan 15, 2021, 12:06 AM
Malcsta's Avatar
Malcsta Malcsta is offline
Incurable optimist
 
Join Date: Apr 2020
Location: Winnipeg
Posts: 279
Quote:
Originally Posted by WinCitySparky View Post
Yup
So how tall will these floors be?
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Manitoba & Saskatchewan
Forum Jump



Forum Jump


All times are GMT. The time now is 12:57 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.