View Poll Results: Based on options for Broadway Corridor Study, what is your preferred choice?
BRT: Commercial to UBC 25 6.16%
LRT A: Commercial to UBC OR Commercial via VCC to UBC 31 7.64%
LRT B: Main St. to UBC AND Commercial to UBC 18 4.43%
RRT: Commercial to UBC OR VCC to UBC 283 69.70%
COMBO: RRT to Arbutus/LRT to Main St via Arbutus 39 9.61%
BUS: Enhanced Bus Service for all buses to UBC 10 2.46%
Voters: 406. You may not vote on this poll

Closed Thread

 
Thread Tools Display Modes
     
     
  #10881  
Old Posted Oct 1, 2020, 11:59 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888
     
     
  #10882  
Old Posted Oct 2, 2020, 12:50 AM
djh djh is offline
Registered User
 
Join Date: Jul 2003
Location: Vancouver
Posts: 1,977
Quote:
Originally Posted by Jimbo604 View Post
From the project website: broadwaysubway.ca





Source: https://www.broadwaysubway.ca/about/stations/
This diagram only just crystallized for me that the station entrance will have to be incorporated into the current rebuild/renovation of the RBC building, happening right now on the Northeast corner of Broadway/Granville.

Will the RBC developers be doing the station entrance build, or will they be leaving that as an unfinished raw "black box" with Translink's construction team coming in to do the work at a later date?

It also presumes that the two parties have been talking and coordinating their work for a long time. Positioning of walls, floors, support columns and beams, etc. I didn't realise detailed station planning had been done as long ago as when the plans for the RBC building had been submitted.
     
     
  #10883  
Old Posted Oct 2, 2020, 1:50 AM
VancouverOfTheFuture's Avatar
VancouverOfTheFuture VancouverOfTheFuture is offline
Registered User
 
Join Date: Apr 2014
Posts: 3,481
Quote:
Originally Posted by BCPhil View Post
I can't help but think people defend using LRT on Broadway by saying it's capable of RRT stats, do so only because they can't admit it's not the right choice. Because in their minds admitting it's the wrong choice would mean it's the wrong choice always. And if it's the wrong choice always, then that means the only choice is Skytrain. And if Skytrain is the only choice, then my desired 3rd string transit line won't happen because Skytrain is too expensive for it. Therefore I have to campaign against Skytrain to validate LRT as a choice, a choice I need for my transit line I want built.
yes, this. hits the nail on the head. or should i say screws the screw in with the right screw driver.


as for the stations, single entrances, on one end of long platforms. sigh.
     
     
  #10884  
Old Posted Oct 2, 2020, 5:30 AM
waves's Avatar
waves waves is offline
waves
 
Join Date: Jun 2015
Location: North Vancouver
Posts: 382
Quote:
Originally Posted by djh View Post
This diagram only just crystallized for me that the station entrance will have to be incorporated into the current rebuild/renovation of the RBC building, happening right now on the Northeast corner of Broadway/Granville.

Will the RBC developers be doing the station entrance build, or will they be leaving that as an unfinished raw "black box" with Translink's construction team coming in to do the work at a later date?

It also presumes that the two parties have been talking and coordinating their work for a long time. Positioning of walls, floors, support columns and beams, etc. I didn't realise detailed station planning had been done as long ago as when the plans for the RBC building had been submitted.
The details for this station were posted a while ago. I can't remember the source, but I did manage to download them a while ago. I have reuploaded them to my own imgur to share with you:





Source: imgur.com, waves.
     
     
  #10885  
Old Posted Oct 2, 2020, 5:47 AM
Feathered Friend Feathered Friend is offline
Registered User
 
Join Date: Jun 2016
Posts: 2,551
Quote:
Originally Posted by djh View Post
This diagram only just crystallized for me that the station entrance will have to be incorporated into the current rebuild/renovation of the RBC building, happening right now on the Northeast corner of Broadway/Granville.

Will the RBC developers be doing the station entrance build, or will they be leaving that as an unfinished raw "black box" with Translink's construction team coming in to do the work at a later date?

It also presumes that the two parties have been talking and coordinating their work for a long time. Positioning of walls, floors, support columns and beams, etc. I didn't realise detailed station planning had been done as long ago as when the plans for the RBC building had been submitted.
Some extra info from last year's UDP review:

Quote:
This was fortunate for the applicant team, as they were unapologetic in their belief that the sense of motion created by the vertical fins was necessary to relate to the transit station below. That section will be designed by a different architectural firm, which explains why key infrastructure, like the fire command post and standpipe access, have yet to be programmed into this concept. Many believed this actually presented an interesting opportunity, and none were concerned about the lane closure.

As the passenger volume here is expected to be similar to the Expo Line’s Stadium-Chinatown station, the public realm factored heavily in the consensus
https://cityduo.wordpress.com/2019/10/08...support-for-moderate-income-aspirations/
     
     
  #10886  
Old Posted Oct 2, 2020, 5:49 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,721
The developer is PCI, I think.
     
     
  #10887  
Old Posted Oct 2, 2020, 5:56 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,712
The diagrams were from Daily Hive..

https://dailyhive.com/vancouver/skytrain-broadway-extension-station-design-renderings

The guy who found prints in the dumpster also mentioned this:

Quote:
The first page of PCI’s explanatory notes, which accompany the blueprints, refers to “Integration Works” including “those works and elements of the Head House or related to the integration of the Head House into the PCI Development not included in the Finishing Work”.

“Head House” is an architectural term commonly used by the railroad industry to denote an element of a train station, such as an entrance.

The PCI Integration Works detailed on the blueprints are indicated in the explanatory notes as including:

street level entrance to the Head House situated at the corner of West Broadway and Granville Street;
head house structure;
entrance plaza;
stairs, escalator and elevator providing access to the station concourse level;
and connection opening to the station concourse.
https://www.straight.com/life/1261101/ho...s-show-granville-subway-station-new-west
     
     
  #10888  
Old Posted Oct 2, 2020, 6:05 AM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,158
The million dollar question: is the station separate from the tower, or does construction have to wait for the rezoning approval which has to wait for the corridor plan?

Quote:
Originally Posted by VancouverOfTheFuture View Post
as for the stations, single entrances, on one end of long platforms. sigh.
It's either that, an entrance in the middle of the block, or a cut n cover in the middle of the street. Least horrible option.

Or maybe there'll be a mezzanine level?
     
     
  #10889  
Old Posted Oct 2, 2020, 6:19 AM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,158
Quote:
Originally Posted by BCPhil View Post
I can't help but think people defend using LRT on Broadway by saying it's capable of RRT stats, do so only because they can't admit it's not the right choice. Because in their minds admitting it's the wrong choice would mean it's the wrong choice always. And if it's the wrong choice always, then that means the only choice is Skytrain. And if Skytrain is the only choice, then my desired 3rd string transit line won't happen because Skytrain is too expensive for it. Therefore I have to campaign against Skytrain to validate LRT as a choice, a choice I need for my transit line I want built. It's a brain disease...

... I call this disease zwei syndrome.
I'm not trying to downplay the victims of Zwei syndrome, but there's plenty of others:

- Europhilia: (French/Dutch/Swiss/Czech city) has pretty streetcars, why don't we have pretty streetcars?

- Newurbanimania: Streetcars create happy little villages... somehow. Crowds of people stuck at the intersection make the villages look alive. This is the future of urban living.

- Cyclemyopia: The city should be bike-sized - if it's not within twenty blocks like my regular bike ride, why should it be easy to reach at all?

- Authoriphobia: TransLink and (politician/council) are corrupt to the core, and anything they say is good should be questioned to the last detail!

- Affluenza: I'll take anything that doesn't Bring Drugs, Bring Crime, They're Rapists (TM) into my neighbourhood and lowers my property values!

Of course, there's a lot of overlap, but hey, it's a developing field.
     
     
  #10890  
Old Posted Oct 2, 2020, 6:32 AM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,790
Quote:
Originally Posted by dleung View Post
What's the rationale behind keeping the platforms between streets rather than centering them at the station entrances?
Just because the ground level entrance is at one end of the station doesn't mean that the platforms need to be accessed from one end. The ticketing hall, escalators and stairways mean that platform access will be considerably offset from the ground level entrance.
     
     
  #10891  
Old Posted Oct 2, 2020, 7:19 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,721
Probably so the excavation disrupts fewer intersections.

BTW - Escalators on platforms are usually staggered from station-to-station to prevent crowding at one place in trains.
Repeat customers always know where to stand in their train so they are at the base of the escalator when they arrive at their station.
     
     
  #10892  
Old Posted Oct 2, 2020, 7:24 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,721
Quote:
Originally Posted by Migrant_Coconut View Post
The million dollar question: is the station separate from the tower, or does construction have to wait for the rezoning approval which has to wait for the corridor plan?
You can see the tower core in the plans, waiting for the tower phase.
The tower elevator shaft with the single elongated 'X' looks wide enough for 3 elevators.

     
     
  #10893  
Old Posted Oct 2, 2020, 7:32 AM
Feathered Friend Feathered Friend is offline
Registered User
 
Join Date: Jun 2016
Posts: 2,551
Quote:
Originally Posted by Migrant_Coconut View Post
The million dollar question: is the station separate from the tower, or does construction have to wait for the rezoning approval which has to wait for the corridor plan?



It's either that, an entrance in the middle of the block, or a cut n cover in the middle of the street. Least horrible option.

Or maybe there'll be a mezzanine level?
Again, based on what was said at the UDP review, it seems this station will be completed well in advance of the line. There's no rezoning needed, as the surface building is going ahead under the existing zoning, but it is designed to allow for an expansion in the future.
     
     
  #10894  
Old Posted Oct 2, 2020, 11:58 AM
scryer scryer is offline
Registered User
 
Join Date: Feb 2014
Posts: 1,964
I'm late to the party but for all of the LRT discussion on Broadway:



Someone mentioned it before that LRT has a time and a place and I agree. IMO, it's a very niche technology and a very niche transit solution that gets marketed incorrectly to the public and is implemented inappropriately across the world.

Now back to the topic at hand...
__________________
There is a housing crisis, and we simply need to speak up about it.

Pinterest - I use this social media platform to easily add pictures into my posts on this forum. Plus there are great architecture and city photos out there as well.
     
     
  #10895  
Old Posted Oct 2, 2020, 1:21 PM
Rico Rico is offline
Registered User
 
Join Date: Feb 2012
Posts: 319
Quote:
Originally Posted by scryer View Post
I'm late to the party but for all of the LRT discussion on Broadway:



Someone mentioned it before that LRT has a time and a place and I agree. IMO, it's a very niche technology and a very niche transit solution that gets marketed incorrectly to the public and is implemented inappropriately across the world.

Now back to the topic at hand...
As someone who likes Skytrain I am going to disagree. LRT is quite a flexible concept, Skytrain is definitely more niche on the grand scale. That said history and the layout of Vancouver corridors has made Skytrain the right choice for us in many applications and without any question the right choice for Broadway.
     
     
  #10896  
Old Posted Oct 2, 2020, 2:52 PM
scryer scryer is offline
Registered User
 
Join Date: Feb 2014
Posts: 1,964
Quote:
Originally Posted by Rico View Post
As someone who likes Skytrain I am going to disagree. LRT is quite a flexible concept, Skytrain is definitely more niche on the grand scale. That said history and the layout of Vancouver corridors has made Skytrain the right choice for us in many applications and without any question the right choice for Broadway.
That's why the meme says "LRT on Broadway" .

RRT isn't really a limited niche though like LRT is in terms of RRT's main function. RRT of all technologies (whether it's heavy metro or automated) requires grade-separation from regular traffic in order for it to work as a rapid transit solution. Whereas LRT's functions are a lot murkier; and I wouldn't call them flexible because a lot of their functions can be addressed by BRT solutions. We have to remember that people use transit for its real-world purposes, not because it's "easy" to implement on paper. I, myself, am not necessarily anti-LRT in all contexts but LRT is such a misused technology in a lot of places that Metro Vancouver should really tread carefully with it. But that's a discussion for the Arbutus Greenway thread.
__________________
There is a housing crisis, and we simply need to speak up about it.

Pinterest - I use this social media platform to easily add pictures into my posts on this forum. Plus there are great architecture and city photos out there as well.

Last edited by scryer; Oct 2, 2020 at 3:28 PM.
     
     
  #10897  
Old Posted Oct 3, 2020, 6:32 AM
scottN scottN is offline
Registered User
 
Join Date: Mar 2019
Posts: 286
Quote:
Originally Posted by dleung View Post
What's the rationale behind keeping the platforms between streets rather than centering them at the station entrances? I'm assuming there isn't any disruption at grade besides at the station entrance/staging areas?
I think they are trying to only disrupt 1 major street instead of 2 when the dig the big hole in the ground.
     
     
  #10898  
Old Posted Oct 3, 2020, 7:03 AM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,158
To clarify, the station is about a block long: they can dig 1/2 of the block, the intersection, and 1/2 of the other block.... or they can dig one whole block and leave the intersection alone.
     
     
  #10899  
Old Posted Oct 3, 2020, 7:21 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,721
I think the concern would be disrupting multiple major north-south arterials roughly at the same time if they dug under intersections.

Canada Line had bailey bridges over the open cut - can't recall if they were 2 lanes wide or 4 lanes wide.
King Ed was probably 4 lanes. ... but even those would still slow down traffic (including buses) and probably restrict turns.
     
     
  #10900  
Old Posted Oct 3, 2020, 2:35 PM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,790
Quote:
Originally Posted by Rico View Post
As someone who likes Skytrain I am going to disagree. LRT is quite a flexible concept, Skytrain is definitely more niche on the grand scale.
Skytrain is essentially LRT that takes advantage of grade separation to automate its operation and enable the use of LIM (Linear Induction Motor) technology. Skytrain's original designation was "ALRT", for "Advanced LRT". The concept was to keep Skytrain cars smaller and lighter than traditional heavy rail in order to reduce construction costs for elevated and tunneled guideways. Part of that reduction in costs comes from the smaller LIM-powered cars' ability to take tighter corners and use steeper grades.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 7:55 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.