Le Phare in Québec City reduced to 45 floors (±173m)
https://www.journaldequebec.com/2020/05/04/le-phare-passe-de-65-a-45-etages
''The main tower of Le Phare de Québec will peak at 45 floors, 20 less than expected. Major changes, including the arrival of a new business partner, are on the menu of the private megaproject, Le Journal learned.
The vast project will have 60% fewer offices than expected. The housing units will be reduced and the 1250-seat auditorium will simply not see the light of day. Also, the total number of parking spaces will be lowered. However, it is planned that the hotel capacity will be increased.
The last version of Le Phare, on which we were able to get our hands, therefore has very little to do with that unveiled, with great fanfare, in early 2015. Five years ago, we were talking about a new "symbol For Québec City and we praised the advent of the tallest skyscraper east of Toronto.
Admittedly, there is always talk of four towers to be built in Sainte-Foy, at the head of the bridges. But the main tower will only be 45 stories high. The other three towers were to rise to 51, 30 and 18 floors, respectively, according to the latest plans unveiled by Groupe Dallaire in June 2018. However, the new sketches consulted suggest that these heights will also be revised downwards.
New main partner
If the Dallaire Group remains a financial partner of the project, we note the advent of a new main partner - COGIR Immobilier - which manages, among other things, nearly 20,000 housing units in Quebec, Ontario and the United States, including a network of 50 private residences for seniors.
More specifically, DevMcGill, COGIR's development division, will now be in charge. DevMcGill is behind the luxurious mixed Humaniti project in the Quartier international de Montréal.
Ready for late 2024?
The promoters of the Le Phare now wish to relaunch the project quickly so that construction can begin in October 2021. Hopefully, work is planned to be completed in three years, ie towards the end of 2024.
Regulatory changes will be required. We mention in particular the withdrawal of the obligation to build an interchange for the tram. This is a formality, since the Labeaume administration announced in early 2020 that this pole will not ultimately be located under Le Phare.
Despite the current health crisis, promoters are seeking various regulatory amendments by the end of 2020. They also hope for a "light" citizen consultation process. According to them, the new version of the project meets most of the civic criticism heard over the years.
The main grievances raised from the start are the height of the project and the risk of increased traffic congestion in an already very busy area of the city.''