Quote:
Originally Posted by The Jabroni
Yup, totally can see the tether. Crane raising is literally imminent.
|
I am surprised the crane was not placed inside the concrete elevator shaft.
The CIBC centre in Toronto is being built with a concrete core and steel structure. I sadly must mention the whole project including excavation, concrete core, steel construction and all glass curtain walls in excess of 40 stories is now completed having commenced construction well after the start of 360 Main. The delay can be a result of trades, material, weather, and of course permitting and inspections. I cannot begin to imagine the cost overruns not just in these items but also the interest and financing. While I am overjoyed at the construction of this project, the financial pain to Artis is huge and may I say embarrassing for such a storied enterprise.
It is VERY challenging to take on a project like this in Winnipeg. I hope things may finally pick up speed as we head into spring.