Quote:
Originally Posted by lrt's friend View Post
We have been waiting for this connection to the Queensway since the Greber Plan of the 1940s. The SJAM was opened to Carling Avenue in 1967.
The 416 freeway corridor was originally slated for Merivale but when that got built up it got moved to the Woodroffe corridor. The wide greenspace where the pathway runs through Bel Air Park was somewhat reserved as its junction with the Queensway. I believe the parkway wasn't supposed to connect with the Queensway but rather split off from the proposed 416 at about where Baseline station is, much like the Aviation parkway is accessible from the 417 but not from what is now the 174. Of course this all got canned when they decided to eventually move the routing of the 416 much farther west in the late 1980s.
Reply With Quote
     
     
  #1822  
Old Posted Nov 25, 2019, 7:40 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,613
I'm still wondering about how the LRT route between Cleary and New Orchard is shown on GeoOttawa. Normally they seem to be fairly accurate on indicating where the tracks are laid right down to the switch placement, but they are still shown far apart here, as wide as a centre platform apart between the entire length from Sherbourne to Woodland.
Reply With Quote
     
     
  #1823  
Old Posted Nov 25, 2019, 8:05 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,084
Quote:
Originally Posted by Kitchissippi View Post
I'm still wondering about how the LRT route between Cleary and New Orchard is shown on GeoOttawa. Normally they seem to be fairly accurate on indicating where the tracks are laid right down to the switch placement, but they are still shown far apart here, as wide as a centre platform apart between the entire length from Sherbourne to Woodland.
In terms of track geometry, keeping them wide apart like that keeps the tracks straight and in theory allows for faster speeds through the tunnel.
Reply With Quote
     
     
  #1824  
Old Posted Nov 25, 2019, 8:13 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Quote:
Originally Posted by Kitchissippi View Post
I'm still wondering about how the LRT route between Cleary and New Orchard is shown on GeoOttawa. Normally they seem to be fairly accurate on indicating where the tracks are laid right down to the switch placement, but they are still shown far apart here, as wide as a centre platform apart between the entire length from Sherbourne to Woodland.
Good Day.

Yes, this has been noted before. It is a good question, but.....

There is still a pocket track indicated east of Limebank station, and as per the Trillium Line Stage 2 thread, we have been told that this was inaccurate and to await an update in which it would be removed. We yet await that update. (We know not their update/maintenance program/schedule.)

So this may be a similar inaccuracy, based upon best-info-available at the time of the last modification, by those maintaining GeoOttawa.

Or it's something else entirely (only City, the original three proponents, and the now selected EWC know for sure <snort>).

Possibly we will get more and better info at the yet-to-be-announced info session for Dominion to Algonquin ? (hope hope hope ?) !

EnJoy?
Reply With Quote
     
     
  #1825  
Old Posted Nov 25, 2019, 8:17 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Quote:
Originally Posted by OCCheetos View Post
In terms of track geometry, keeping them wide apart like that keeps the tracks straight and in theory allows for faster speeds through the tunnel.
Good Day.

I'd go with you on that except that would mean excavating way much more material, which is more expensive....
Reply With Quote
     
     
  #1826  
Old Posted Nov 25, 2019, 8:35 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
Quote:
Originally Posted by PHrenetic View Post
Good Day.

I'd go with you on that except that would mean excavating way much more material, which is more expensive....
It's a bit of a toss-up. Maybe it's somehow cheaper to build one straight cut-and-cover tunnel instead of having catchments at each end of the stations for the tracks to come back together. Had they opted for side platforms, they could have built a narrower cut-and-cover tunnel with simple station boxes (or "U" since they are open-trench), but then we'd incur extra expenses by doubling vertical circulation.

The wide tunnel also provides a centre pathway for maintenance workers and emergency evacuations. That might have been part of the equation.

My fear is that the Byron Linear Park will never be restored to its former glory due to the shallow depth of the soil. Had the tunnel been narrower, there might have been more space.
Reply With Quote
     
     
  #1827  
Old Posted Nov 25, 2019, 8:56 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Quote:
Originally Posted by J.OT13 View Post
It's a bit of a toss-up. Maybe it's somehow cheaper to build one straight cut-and-cover tunnel instead of having catchments at each end of the stations for the tracks to come back together. Had they opted for side platforms, they could have built a narrower cut-and-cover tunnel with simple station boxes (or "U" since they are open-trench), but then we'd incur extra expenses by doubling vertical circulation.

The wide tunnel also provides a centre pathway for maintenance workers and emergency evacuations. That might have been part of the equation.

My fear is that the Byron Linear Park will never be restored to its former glory due to the shallow depth of the soil. Had the tunnel been narrower, there might have been more space.
Good Day.

Yes, it is a back-and-forth discussion with no hard info. We Shall See.

As for the depth, , shared and agreed. Even shallow-root tree species will experience difficulty.

NoJoy!
Reply With Quote
     
     
  #1828  
Old Posted Nov 25, 2019, 9:22 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,084
Quote:
Originally Posted by PHrenetic View Post
Good Day.

I'd go with you on that except that would mean excavating way much more material, which is more expensive....
Straight tracks do cost less to maintain in the long run, which could also have had an influence.
Reply With Quote
     
     
  #1829  
Old Posted Nov 26, 2019, 1:40 AM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,553
Quote:
Originally Posted by OCCheetos View Post
Straight tracks do cost less to maintain in the long run, which could also have had an influence.
Better for the tracks and better for the trains
Reply With Quote
     
     
  #1830  
Old Posted Nov 26, 2019, 3:39 AM
Southpaw78 Southpaw78 is offline
Registered User
 
Join Date: May 2009
Location: Ottawa
Posts: 200
Can anyone share info on the track between Pinecrest and Queensway stations? I understand it's to go along the north side of the Queensway, but when you look at what real estate is there, it doesn't remotely seem wide enough to accommodate 2 tracks.
Reply With Quote
     
     
  #1831  
Old Posted Nov 26, 2019, 4:15 AM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,553
Quote:
Originally Posted by Southpaw78 View Post
Can anyone share info on the track between Pinecrest and Queensway stations? I understand it's to go along the north side of the Queensway, but when you look at what real estate is there, it doesn't remotely seem wide enough to accommodate 2 tracks.
I think Queensway station is no more. Queensview will be the next station after Lincoln Fields going West. Go to http://maps.ottawa.ca/geoOttawa/ and click on "More Layers" and "Rail implementation office". You get a really detailed look at track and station placement. The segment in question:

Reply With Quote
     
     
  #1832  
Old Posted Nov 26, 2019, 4:21 AM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,084
You can also go here: https://map.otrainfans.ca/#14.45/45.35832/-75.78806/-30

The data is pulled from geoOttawa but doesn't require flash and is a bit easier to use.
Reply With Quote
     
     
  #1833  
Old Posted Nov 26, 2019, 4:26 AM
GoTrans GoTrans is offline
Registered User
 
Join Date: Jan 2010
Posts: 691
Quote:
Originally Posted by J.OT13 View Post
It's a bit of a toss-up. Maybe it's somehow cheaper to build one straight cut-and-cover tunnel instead of having catchments at each end of the stations for the tracks to come back together. Had they opted for side platforms, they could have built a narrower cut-and-cover tunnel with simple station boxes (or "U" since they are open-trench), but then we'd incur extra expenses by doubling vertical circulation.

The wide tunnel also provides a centre pathway for maintenance workers and emergency evacuations. That might have been part of the equation.

My fear is that the Byron Linear Park will never be restored to its former glory due to the shallow depth of the soil. Had the tunnel been narrower, there might have been more space.
The also have to consider the space required for snow accumulation in the open trenches where the stations are.
Reply With Quote
     
     
  #1834  
Old Posted Nov 26, 2019, 4:49 AM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 8,836
I still say it was a mistake to not design so as to allow for the continued existence of Queensway station. It makes it a lot harder for future Ottawa to repurpose some Queensway lane-mile-time for bus transit.
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
Reply With Quote
     
     
  #1835  
Old Posted Nov 27, 2019, 12:40 AM
VANRIDERFAN's Avatar
VANRIDERFAN VANRIDERFAN is offline
Registered User
 
Join Date: Jan 2007
Location: Regina
Posts: 5,431
Would there be any chance that they would loop the LRT over to Carling Campus for phase 3? Or is that just crazy talk?
Reply With Quote
     
     
  #1836  
Old Posted Nov 27, 2019, 1:19 AM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,084
Quote:
Originally Posted by VANRIDERFAN View Post
Would there be any chance that they would loop the LRT over to Carling Campus for phase 3? Or is that just crazy talk?
At this point Stage 3 is generally pretty set in stone in the alignment department. The EA was completed last year. A few alignments that looped up North were considered, but none of them were kept. You can see the final proposed alignment here.
Reply With Quote
     
     
  #1837  
Old Posted Nov 27, 2019, 2:17 AM
Southpaw78 Southpaw78 is offline
Registered User
 
Join Date: May 2009
Location: Ottawa
Posts: 200
Quote:
Originally Posted by OCCheetos View Post
You can also go here: https://map.otrainfans.ca/#14.45/45.35832/-75.78806/-30

The data is pulled from geoOttawa but doesn't require flash and is a bit easier to use.
Thanks for this! It does show it clearly and makes sense now that I see the alignment come out beside the OC Transpo and Leons. Also appreciate the clarification that Queensway station will be no more and Queensview isn't replacing it.
Reply With Quote
     
     
  #1838  
Old Posted Nov 27, 2019, 4:18 AM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 8,836
I really hope between now and opening day they come up with better station names than "Cleary" and "New Orchard".
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
Reply With Quote
     
     
  #1839  
Old Posted Nov 27, 2019, 1:27 PM
VANRIDERFAN's Avatar
VANRIDERFAN VANRIDERFAN is offline
Registered User
 
Join Date: Jan 2007
Location: Regina
Posts: 5,431
Quote:
Originally Posted by OCCheetos View Post
At this point Stage 3 is generally pretty set in stone in the alignment department. The EA was completed last year. A few alignments that looped up North were considered, but none of them were kept. You can see the final proposed alignment here.
Well since I'll be long retired and living in a different part of the country by the time Stage 3 is built it really doesn't matter to me.
In the spring, summer and fall it will be a nice walk from Moodie to Carling. Winter will not be nice at all, especially since they don't want to plow the trails.
Reply With Quote
     
     
  #1840  
Old Posted Nov 27, 2019, 1:29 PM
Dengler Avenue's Avatar
Dengler Avenue Dengler Avenue is offline
Road Engineer Wannabe
 
Join Date: Sep 2017
Location: Côté Ouest de la Rivière des Outaouais
Posts: 8,607
Will the Baseline spur only run up to Lincolnfield then turn around?
__________________
My Proposal of TCH Twinning in Northern Ontario
Disclaimer: Most of it is pure pie in the sky, so there's no need to be up in the arm about it.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 6:30 AM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.