Transit commissioner timed the ride, end-to-end. Just under 21 minutes.

Was that with normal stops, or did they do an express trip? If it was with normal stops, that is faster than expected and will help improve capacity.
     
     
  #11742  
Old Posted Aug 23, 2019, 7:20 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,773
Manconi is talking about the 12 days and the 13 trains. Missed a big chunk because I had to take a call.
     
     
  #11743  
Old Posted Aug 23, 2019, 7:20 PM
corynv corynv is offline
Registered User
 
Join Date: Jun 2018
Posts: 171
Quote:
Originally Posted by roger1818 View Post
Was that with normal stops, or did they do an express trip? If it was with normal stops, that is faster than expected and will help improve capacity.
The end-to-end video Otrain fans did from the simulator was about 21 minutes. So i'd assume normal stops.
     
     
  #11744  
Old Posted Aug 23, 2019, 7:21 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,799
Quote:
Originally Posted by J.OT13 View Post
Manconi is talking about the 12 days and the 13 trains. Missed a big chunk because I had to take a call.
He said something about the city's "current requirement" being 13 double trains.
     
     
  #11745  
Old Posted Aug 23, 2019, 7:24 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,773
Quote:
Originally Posted by bradnixon View Post
He said something about the city's "current requirement" being 13 double trains.
Sounds like a moving target. They we're always pretty adamant about 15 up until now.

We still have a month and a half to make adjustments and get ALL trains ready4rail.
     
     
  #11746  
Old Posted Aug 23, 2019, 7:25 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,773
Fare freeze ending October 1.
     
     
  #11747  
Old Posted Aug 23, 2019, 7:29 PM
Badyouken's Avatar
Badyouken Badyouken is offline
Registered User
 
Join Date: Feb 2016
Posts: 239
Quote:
Originally Posted by corynv View Post
The end-to-end video Otrain fans did from the simulator was about 21 minutes. So i'd assume normal stops.
A journalist was saying that they did not open the doors, but no clarity on whether the stops were just as long or shorter.
     
     
  #11748  
Old Posted Aug 23, 2019, 7:29 PM
corynv corynv is offline
Registered User
 
Join Date: Jun 2018
Posts: 171
Where are you listening to this? Only article i found just covered the handover, and ended after that, and haven't been able to find another place.
     
     
  #11749  
Old Posted Aug 23, 2019, 7:32 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,799
Jeff Leiper just asked about 15 trains.

Manconi's answer was that they have demonstrated 15 trains, and 15 trians was the forecast of what was required at the start of the project, but ridership has gone down so now 13 trains are all that will be needed.
     
     
  #11750  
Old Posted Aug 23, 2019, 7:33 PM
Badyouken's Avatar
Badyouken Badyouken is offline
Registered User
 
Join Date: Feb 2016
Posts: 239
Quote:
Originally Posted by bradnixon View Post
Jeff Leiper just asked about 15 trains.

Manconi's answer was that they have demonstrated 15 trains, and 15 trians was the forecast of what was required at the start of the project, but ridership has gone down so now 13 trains are all that will be needed.
I mean, maybe ridership has gone down because bus service is not so great lately...
     
     
  #11751  
Old Posted Aug 23, 2019, 7:34 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,773
Quote:
Originally Posted by corynv View Post
Where are you listening to this? Only article i found just covered the handover, and ended after that, and haven't been able to find another place.
O-Train Fans.

https://www.pscp.tv/w/1vAxRqaPnzVJl

I assume Shane will post the entire video later.
     
     
  #11752  
Old Posted Aug 23, 2019, 7:34 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by bradnixon View Post
He said something about the city's "current requirement" being 13 double trains.
Doing some quick math, if the end to end time is actually 21 minutes, and you assume a 2 minute dwell time at each end, it works out as follows:
End to end			21	min
turn around time 2 min
Total round trip 46 min
trips per hour per train 1.30
Number of trains 13
Total trips per hour 16.96
Train Capacity 600 people
Total Capacity 10,174 PPHPD
A bit shy of the 10,700 promised, but not too far off.
     
     
  #11753  
Old Posted Aug 23, 2019, 8:03 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,773
Maconi's a little flip-floppy on this one. On the one hand, he says 15 trains was never in the contract, and then he says ridership has gone down, so we don't need 15 trains.

If the line is faster than originally promised (we've heard a lot of 24-25 minutes, not 21), then we're pretty close to achieving the capacity stated in the contract, as per Roger above. But if we can only achieve 13 because the other trains are not "ready for prime-time", then we don't have functional spares. Before the 12 days started, Manconi was always crystal clear that we needed to see 15. Hard to buy his explanations.
     
     
  #11754  
Old Posted Aug 23, 2019, 8:13 PM
zzptichka zzptichka is offline
Registered User
 
Join Date: Dec 2015
Location: Outaouias
Posts: 2,363
So we build LRT to increase ridership but LRT only works if ridership goes down. The Manconi Paradox.
     
     
  #11755  
Old Posted Aug 23, 2019, 8:59 PM
Proof Sheet Proof Sheet is offline
Registered User
 
Join Date: May 2009
Posts: 2,985
Quote:
Originally Posted by J.OT13 View Post
From Joanne Schnurr's Twitter:

"Ottawa Mayor Jim Watson and city councillor Eli El-Chantiry on the LRT as we learn what date the Confederation Line will launch. “it feels like Christmas morning” Watson says. ⁦@ctvottawa⁩"


https://twitter.com/JoanneCTV/status/1164946791260925955
Eli El-Chantiry looks like he'd rather be anywhere else ...LRT isn't really part of his wards outlook.
     
     
  #11756  
Old Posted Aug 23, 2019, 9:03 PM
lrt's friend lrt's friend is online now
Registered User
 
Join Date: Dec 2006
Posts: 12,776
Is 21 minutes going to be the norm in real operations? We can hope. The faster the trains will be, the better the customer experience.

The city really needs a win on this to demonstrate that the $2.1B was worth spending. If we can move people to and from downtown faster despite the transfer penalty, then we will see a real benefit. Hopefully, we will see the end of the ridership slump but they have to get the bus connections right as well. That will be equally important.

I am out of town that weekend so I will miss the excitement. I look forward to giving it a try. Being a south ender, I will check out both the Bayview and Hurdman connections.
     
     
  #11757  
Old Posted Aug 23, 2019, 9:12 PM
HighwayStar's Avatar
HighwayStar HighwayStar is offline
Registered User
 
Join Date: Jul 2014
Location: PHX (by way of YOW)
Posts: 1,200
Quote:
Originally Posted by lrt's friend View Post
I am out of town that weekend so I will miss the excitement. I look forward to giving it a try. Being a south ender, I will check out both the Bayview and Hurdman connections.
As fate would have it, that's the one weekend I'm back in Ottawa since leaving in June Wifey is going to get dragged around a lot
     
     
  #11758  
Old Posted Aug 23, 2019, 9:20 PM
lrt's friend lrt's friend is online now
Registered User
 
Join Date: Dec 2006
Posts: 12,776
Quote:
Originally Posted by HighwayStar View Post
As fate would have it, that's the one weekend I'm back in Ottawa since leaving in June Wifey is going to get dragged around a lot
The irony of it all, is that I will be escaping Ottawa by rail for an extended weekend and leaving the day before launch. Ottawa will be different when I get back. On return, maybe I should just dump my bags in my vehicle at the VIA station and give it a whirl.

At one point Route 97 was going to be extended to the VIA Station, which would have been a nice feature for us southenders. I presume that got canned somewhere along the way.
     
     
  #11759  
Old Posted Aug 23, 2019, 10:26 PM
Badyouken's Avatar
Badyouken Badyouken is offline
Registered User
 
Join Date: Feb 2016
Posts: 239
Same here, I'm out of town that weekend, so am trying to figure out when I'll first ride it.

Otherwise, I'm just looking forward to it.

I must say, half the fun of these things is the hype and talking about it on these boards. I'll be happy to transition to discussion of Stage 2, once we're all used to Stage 1. But for now, the idea of underground stations in Ottawa - those public spaces I enjoy so much in other cities - is exciting.
     
     
  #11760  
Old Posted Aug 23, 2019, 11:20 PM
sseguin sseguin is offline
Registered User
 
Join Date: Aug 2018
Posts: 309
Quote:
Originally Posted by J.OT13 View Post
O-Train Fans.

https://www.pscp.tv/w/1vAxRqaPnzVJl

I assume Shane will post the entire video later.
Indeed. The video (much higher quality and a tighter shot) is coming in the next few hours.

The doors did not open. And the stops were all the same at about 15 seconds each.

An end to end video from today’s ride is coming shortly as well.

Last edited by sseguin; Aug 24, 2019 at 12:11 AM.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 12:27 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.