  #1221  
Old Posted Mar 6, 2019, 7:52 PM
lrt's friend lrt's friend is offline
 
Join Date: Dec 2006
Posts: 12,814
Quote:
Originally Posted by JohnnyRenton View Post
I think the best they can do right now is to tweak some of the details of the plan with SNC so that they can try to reduce some of the redundant work they will need to do when they go back to the line in 5 or 10 years. Cancelling would result in a $36 million payment, and at 6% of the projected cost of the project, I can see it being a hard sell to spend that money on nothing. I wont lie. I will probably take a bit of pleasure in watching all these "unforeseen" problems pop up, and the surprise of citizens and politicians alike. It will still be sad, and an unnecessary waste of some of the money, but totally predictable.
I am planning to picket the opening ceremony. (Phase 2 Trillium Line)

"20 years and still no downtown service"
"20 years and still not double tracked"

Of course, even under the best of circumstances, it is moving beyond 20 years.
Reply With Quote
     
     
  #1222  
Old Posted Mar 6, 2019, 7:55 PM
JohnnyRenton JohnnyRenton is offline
 
Join Date: Nov 2018
Posts: 253
From @KatePorterCBC:

".@dianedeans won't vote for LRT2. "It's not because I don't want LRT. I do." She has no confidence, from the non-answers of staff and outside advisors today, that all the bids met the 70% minimum. She wonders how SNC-Lavalin made it through. #ottcity"

I know it wont make any difference in the end but it at least makes smile a bit that she is standing up against some of the issues with phase 2, and the whole process behind it.

Also via @KatePorterCBC:

"@KeithEgli says one reason he ran for #OttCity council in 2010 was the cancellation of the original north-south light rail. "As soon as we cancel, we have three proponents legally obligated to be paid $12M, so $36M." "We have momentum, we're moving perfect. Is it perfect? No.""

It is such a shame that some of those voting in favour of the project are doing so despite its flaws. No one is praising it. People are just accepting a second best, so-so solution in the seeming hopes that it will "get sorted out" one day.
Reply With Quote
     
     
  #1223  
Old Posted Mar 6, 2019, 8:04 PM
OTSkyline OTSkyline is offline
 
Join Date: Jun 2012
Posts: 2,830
I live right next to the T-Line, at Walkley... It's painful watching the trains go by everyday but not stop, so I definitely hope and am looking forward to a Walkley Station being built. Right now I can take the bus on the transitway to get downtown (which is either 0 or 1 transfer at Hurdman) which will inevitably go to 1 if/when the station opens here (LRT to Bayview, then transfer). But at least it will hopefully be a better, more comfortable and more predictable ride.

If they are to upgrade the SE transitway from buses to LRT, my idea would be to have the Carling LRT cross to billings, then go up the SE transitway to join Hurdman. But that's not a huge priority IMO.. could be phase 3 or 4 or 5..
Reply With Quote
     
     
  #1224  
Old Posted Mar 6, 2019, 8:59 PM
Truenorth00 Truenorth00 is offline
 
Join Date: May 2017
Posts: 29,133
Quote:
Originally Posted by JohnnyRenton View Post
I recognize that upgrading the T-Line and using it to provide LRT service to the south end is hugely problematic, and expensive. And even a $1 billion dollar investment it might at best double track and modernize the existing line, and get a double tracked line to the branch south of South Keys, but probably get it to either the airport or Riverside, and wouldn't get it interlined. You need more money than that. And if you go with the option of just using the existing funds, and doing what you can to extend it as far as possible, and doing all the engineering works needed to avoid a second shutdown, you might only get to South Keys. I've never suggested the city should spend more money than is already allocated for the T-Line. That is why I suggested the city pause the project to re-evaluate; because I don't think the project as is is good value for money and a total rethink is in order.
And if they had completely put off Trillium upgrades till they had more capital to do it properly, just imagine what people like lrt's friend would be saying on here.

They split the difference and gave you a half baked single-track DMU line because that's probably going to meet demand for decades (2048 by their estimation). This is what happens when politics and emotions intrude instead of letting planners build higher-order transit solely based on cost and ridership considerations.

As they say, "be careful what you wish for..."

Quote:
Originally Posted by JohnnyRenton View Post
It is easy to say that now because it is so far out. If the line has double, triple, or more, in terms of ridership, it becomes a much harder sell.
Absolutely disagree. At triple today's ridership, the Trillium Line would still have a fraction of what the Transitway does today. And we still shut down large chunks of the Transitway. If they ever extend Confederation all the way to Barrhaven, shutting down the Trillium Line will be quite easy. All feeder traffic can be directed away. This is something a lot of people don't get about the Trillium Line. Not a lot of it is walk on ridership. It's either fed by buses or park n ride traffic. Those riders can be reasonably moved to alternative lines for a few years.

Quote:
Originally Posted by JohnnyRenton View Post
Everyone lost that. There is nothing special about them.
And they gained transfers in the process. You aren't actually gaining a transfer. You've always had to transfer at Bayview.

Quote:
Originally Posted by JohnnyRenton View Post
No, I don't think that. In fact I would say I am pretty aware of that fact. Hence why I think it is worth deciding whether the city should spend anything on the proposed Trillium Line plan.
Ask lrt's friend and all those southern residents if they'd rather have this investment or zero investment.

Quote:
Originally Posted by JohnnyRenton View Post
And as for future funding, the city probably can't do anything else itself for a while, unless it finds an additional funding model to raise more funds. But to think no level of government is going to fund anything for 15 or 20 years is also a stretch given that transit has become an important investment, by the higher levels, with each decade that passes. So I think trying to funnel all the money into the C-Line today because the city might not see another drop of funding for 25 years is kind of disingenuous. There will be more money, just nothing beyond phase 2 is secured or in the works as of today.
The city has taken on so much debt between stage 1 and 2, that it can't really afford major works. And there's still expensive transitways and possibly in-median LRT on Carling to fund. It'll be pretty unprecedented for the feds and Queen's Park to pay entirely for a transit expansion without municipal contribution. I'll bet that's aimed at getting funding for Barrhaven and Kanata. That means nothing for Trillium for probably two to three decades.


Quote:
Originally Posted by JohnnyRenton View Post
And this is the funny thing, we are actually both in agreement, just in our own ways, and from our own perspectives. You don't think the Trillium Line should see additional expansion because it could impact the C-Line.
Actually, I just wish they spent all of it on twin-tracking and airport expansion. Even electrification isn't really necessary for these ridership levels (and arguably could have been funded by the city itself in due course). I just disagree with going all the way down to Leitrim and Riverside South. That bit is dubious to me. But that's how politics works and I understand this. Toronto ended up building a subway to Vaughan so it could get funding for a subway extension to York U.

Quote:
Originally Posted by JohnnyRenton View Post
And just as making cuts to the C-Line will impact ridership, having a value engineered trillium line that can't offer high frequencies, capacities, and simply terminates at Bayview, is a recipe for low ridership.
On one hand you say low ridership and on other, both you and lrt's friend say ridership could triple. Which is it?

I'd argue that Trillium is going to provide great return on investment. Ridership will probably double within 5 years after launch and probably triple today in 10-20 years. That will have been great return on what was spent.

Quote:
Originally Posted by JohnnyRenton View Post
I would also add that having both the SE Transitway, and an extended T-Line, is kind of redundant. And dumb. You would actually have two pieces of transit infrastructure that don't take people directly downtown ....
This obsession with getting downtown is going to be hugely problematic in the long run. Good transit systems are designed to let you go anywhere in the city. And by accident, the Trillium Line and Southeast Transitway are well positioned for development of the areas just outside downtown. Coming from Toronto where both the GO Train and TTC subway network are very downtown centric, I see this as an advantage, not a flaw.

Quote:
Originally Posted by JohnnyRenton View Post
The T-Line has always been problematic in a lot of ways. If it wasn't it would have been expanded by now. And the fact that no one, on a forum with people who crazy about transit and rail projects, has really come out and said this is a great project, should be a clear sign that something is wrong. And I think the problem is that the city, and lots of citizens, have been pushing a vision of the T-Line that doesn't actually make sense.
Not every project is going to be "great". But we shouldn't let perfect be the enemy of good. Trillium Stage 2 is moving the ball forward and will make it easier for some people to commute. It will also show that demand exists beyond just Carleton in that corridor, and help make the case for that eventual investment that twins the tracks.
Reply With Quote
     
     
  #1225  
Old Posted Mar 6, 2019, 9:01 PM
JohnnyRenton JohnnyRenton is offline
 
Join Date: Nov 2018
Posts: 253
Approved...

Not much else to say about that. As long as it was bundled in with the C-Line (which I learned during the council meeting, it 100 percent was), there was zero chance this could have been pulled back and redone. Ottawa has provided a lot of good lessons in how to do public transit. I guess it is time they offer a lesson on what not to do lol
Reply With Quote
     
     
  #1226  
Old Posted Mar 6, 2019, 9:17 PM
OCCheetos OCCheetos is offline
 
Join Date: Aug 2017
Posts: 2,118
Quote:
Originally Posted by J.OT13 View Post
Don't have the full context, but I'm assuming a councillor asked the question to Swail. This is classic;

"Dow's Lake tunnel won't be twinned for LRT2, Swail says because Dow's Lake is not a pinch point. #ottcity"
https://twitter.com/KatePorterCBC/status/1103363309695193088

Well no — Sherlock! You're running the trains at the low-low frequency of 12 minutes. We should be striving to increase the frequency to deliver better service. We should be doing everything we can as part of this 2 year shut-down to prevent any further long-term shut-down in the future!
To be fair, Dow's Lake really isn't a pinch point. Higher frequencies are absolutely possible without touching the tunnel (especially because it's one of the areas where trains can reach top line speed).

Walkley and Gladstone are. Gladstone was cheap to double track because the trench was basically already wide enough, but Walkley isn't and that's where the problem lies.
Reply With Quote
     
     
  #1227  
Old Posted Mar 6, 2019, 10:20 PM
JohnnyRenton JohnnyRenton is offline
 
Join Date: Nov 2018
Posts: 253
Quote:
Originally Posted by Truenorth00 View Post
And if they had completely put off Trillium upgrades till they had more capital to do it properly, just imagine what people like lrt's friend would be saying on here.

They split the difference and gave you a half baked single-track DMU line because that's probably going to meet demand for decades (2048 by their estimation). This is what happens when politics and emotions intrude instead of letting planners build higher-order transit solely based on cost and ridership considerations.

As they say, "be careful what you wish for..."
I might be passionate about the subject, but I can also look at quite rationally and logically. I have worked in logistics for well over a decade, and have a background in GIS. So developing models to determine things like transit ridership is actually something I am capable of doing and understanding. I also know that models can say whatever you want them too. Not saying that was what happened in this case, but they are far from perfect.

Taking a more specific consideration into account, it wouldn't be surprising if their models didn't show massive ridership growth for the south end because of the existence of an alternate route, the SE Transitway. Unlike the C-Line, where the Transitway is being completely wiped out and replaced with LRT, which means it will capture all of the existing Transitway demand, and then some, the N-S LRT route wont. A lot of people are still going to find the bus is a better option (relative to what is being offered), so they will just stick with that.

And this is a case where your statement about emotions and politics plays true. The city has had this attachment to the Trillium Line since it started out as a pilot project, and in 2006, and 2010, and now 2019, has tried to find ways to integrate it into a larger LRT network. But using it for the N-S route doesn't actually make a lot of sense. It wont provide the best service, relative to a converted SET. It will likely be more costly. It will use an older technology, which means it wont be compatible with lower platforms, just no interlining, nor will it be able to take advantage of the efficiency gains of automated systems. The desire to "do something" with the T-Line, in part because it "is there" has partly contributed to the slapdash plan that was just approved.

Quote:
Originally Posted by Truenorth00 View Post
Absolutely disagree. At triple today's ridership, the Trillium Line would still have a fraction of what the Transitway does today. And we still shut down large chunks of the Transitway. If they ever extend Confederation all the way to Barrhaven, shutting down the Trillium Line will be quite easy. All feeder traffic can be directed away. This is something a lot of people don't get about the Trillium Line. Not a lot of it is walk on ridership. It's either fed by buses or park n ride traffic. Those riders can be reasonably moved to alternative lines for a few years.
They shut down the Transitway because there were zero ways around it. Just as there is no way around the fact that the T-Line needs to be closed for the planned expansion. But image if some sections of the new C-Line had to be closed a second time? People would be livid. Yes, people are making a sacrifice with closures while the C-Line is being built. But they also know they will only have to do that once.

Quote:
Originally Posted by Truenorth00 View Post
Ask lrt's friend and all those southern residents if they'd rather have this investment or zero investment.
People will almost always take something over nothing. It is human nature. Look at a lot of the councillors thoughts about phase 2. There were a lot of reservations and questions about it all. Especially in the south end where they have waited a decade for LRT to start making its way there. And even with this investment, less than 10% of the overall spending on LRT so far has been for transit in the south end. They would have the right to be upset, just like they have the right to be upset about a questionable plan being pushed through with almost time to even consider it and address legitimate issues that people are bringing up.

Quote:
Originally Posted by Truenorth00 View Post
The city has taken on so much debt between stage 1 and 2, that it can't really afford major works. And there's still expensive transitways and possibly in-median LRT on Carling to fund. It'll be pretty unprecedented for the feds and Queen's Park to pay entirely for a transit expansion without municipal contribution. I'll bet that's aimed at getting funding for Barrhaven and Kanata. That means nothing for Trillium for probably two to three decades.
Urban transit hasn't really been on the table for the past decade. So yeah, I totally agree that after what will likely be a 15 year, $8-10 billion dollar investment in bringing LRT to the suburbs (coming from all levels of government) the urban section of the Trillium Line wont see any upgrades again for several decades (unless it is part of some federally funded interprovincial transit program, which is not likely). As I mentioned in another thread, Barrhaven and Kanata will get their extensions, there will be a "fix the south" type investment to connect the airport and southern suburbs into a converted SET and modernize the southern end of the line, and that is it. Carling. The urban section of the T-Line. An extension to Gatineau. None of that will even be on the table (unless they are part of some one off special projects).

Quote:
Originally Posted by Truenorth00 View Post
Actually, I just wish they spent all of it on twin-tracking and airport expansion. Even electrification isn't really necessary for these ridership levels (and arguably could have been funded by the city itself in due course). I just disagree with going all the way down to Leitrim and Riverside South. That bit is dubious to me. But that's how politics works and I understand this. Toronto ended up building a subway to Vaughan so it could get funding for a subway extension to York U.
I would argue that if the plan was actually thoughtful and considered, those extensions could have worked. A single track for each branch to the airport and Riverside could have been a perfect starting point for those services. But the fact that even when we disagree, we still agree that the plan isn't great, kind of sums up what a mess it is.

Quote:
Originally Posted by Truenorth00 View Post
On one hand you say low ridership and on other, both you and lrt's friend say ridership could triple. Which is it?

I'd argue that Trillium is going to provide great return on investment. Ridership will probably double within 5 years after launch and probably triple today in 10-20 years. That will have been great return on what was spent.
What would the increase in ridership be if the T-Line was essentially left untouched (save the addition of a station at Walkley and Gladstone), and instead the SET was converted to LRT and used to provide service to the airport and further south? How much more efficiency would they have been able to gain in providing bus services if they had that LRT line feed passengers into and reduce the number of longer distance bus trips? Ridership should double almost overnight just due to the increase in stations and places served, along with marginal frequency increases. But having the T-Line simply be a line that runs between Bayview and a station on part of an SET LRT line, with a few more local stations, and slightly improved frequency, could very well have doubled ridership as well.

Quote:
Originally Posted by Truenorth00 View Post
This obsession with getting downtown is going to be hugely problematic in the long run. Good transit systems are designed to let you go anywhere in the city. And by accident, the Trillium Line and Southeast Transitway are well positioned for development of the areas just outside downtown. Coming from Toronto where both the GO Train and TTC subway network are very downtown centric, I see this as an advantage, not a flaw.
That is where the majority of suburban commuters want to go though. I know the point you are trying to make, and it isn't that I disagree with you. But talking about transit and development will lead to a very long deviation....

Quote:
Originally Posted by Truenorth00 View Post
Not every project is going to be "great". But we shouldn't let perfect be the enemy of good. Trillium Stage 2 is moving the ball forward and will make it easier for some people to commute. It will also show that demand exists beyond just Carleton in that corridor, and help make the case for that eventual investment that twins the tracks.
I agree with that sentiment. But there are degrees of "not perfect". The C-Line isn't perfect. But it is close enough that it is easy to just let them slide. The T-Line project isn't great. It isn't even good. It is kind of a terrible.

Now, having said all that, I am over it. The plan was approved and it is going ahead. But more than that, all the discussion I have had here, and with people elsewhere, have made me realize that the T-Line isn't the right choice of infrastructure for creating a modern, high capacity, N-S transit line, for the reasons I have stated above, along with others. So the fact that this plan boxed the T-Line into a state of semi-irrelevancy might well be a good thing in the long run. That might be me trying to put an optimistic spin on things in light of the outcome. But just as the city already had a transit network heading into Orleans, Barrhaven, and Kanata, it already has one for the south, and that is probably the one should ultimately be used, and a better, more suitable purpose for the T-Line can be figured out.

Edit; I would also that there is a big wild card factor, which is the reality when the various phases come online. Public perception, cost savings, rider experience, time saved, time lost, ease or challenge of use. All these factors are going to have a big impact on what the public is willing to fund, and accept, in the future.

Last edited by JohnnyRenton; Mar 6, 2019 at 10:50 PM.
Reply With Quote
     
     
  #1228  
Old Posted Mar 6, 2019, 11:36 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
 
Join Date: Nov 2005
Posts: 4,703
Keeping the SE Transitway (especially the Heron to Hurdman section) is essential to the Baseline BRT concept. Without it it loses its connectivity. Along with the Hospital Link and the potential to push a transit corridor to Innes Road, in the future we could regain a flexible east-west bus rapid transit spine that bypasses downtown but intertwines with the LRT lines.



I think this would be a great way of diversifying the city's public transportation system to be less dependent on one particular mode.
Reply With Quote
     
     
  #1229  
Old Posted Mar 8, 2019, 1:50 PM
Multi-modal Multi-modal is offline
 
Join Date: Jul 2014
Posts: 1,154
I sent in some questions regarding the Trillium Line about a week ago, through my Councillor Shawn Menard. The answers have finally come back and I thought I'd share them here:
Councillor Menard, please see responses in red below. Thanks, Chris

Q1) It is my understanding that at the public information session Chris Swail confirmed that the decision to have the Trillium Line run at-grade through Riverside South means that, in addition to the Limebank Road overpass, the four planned north-south collector roads between Limebank Road and Earl Armstrong Road will each require an overpass to carry vehicles, cyclists, and pedestrians over the Trillium Line. This raises concerns regarding connectivity in Riverside South (again, see attached document), but it is also concerning from a financial perspective. Do City staff have an estimate for the future cost of these four overpasses, and were these costs considered when it was decided the Trillium Line would run at-grade through Riverside South rather than elevated?
A1) Yes. These costs have been considered with respect to decisions around the Trillium Line alignment. The alignment will be built such that it can accommodate station entrances from these future bridges for the north-south collector roads that are planned in association with the Riverside South CDP between Bowesville and Limebank. In addition, other infrastructure to service growth in this area is being coordinated with the build.

Q2) As I was have long suspected, it was confirmed that the portion of single track line at Walkley Road / Walkley Station is the limiting factor that will prevent the City from reducing the frequency of Trillium Line service to below 12 minutes. Are City staff confident that maintaining a single track at Walkley Road will allow them to consistently hit 12 minute frequencies? Are they more confident than when they promised 10 minute frequencies in 2015?
A2) Yes. Operational considerations were prioritized in the planning the Trillium Line Extension Project. The passing tracks at Brookfield, Carleton and Gladstone are being extended and a new train control system across the entire alignment (new and existing) will be implemented to achieve more reliability and to improve performance such that trips can recover time within a single trip should they experience delays.

Q3) I have been told City staff claimed that the Walkley overpass may be replaced in 2038 (I assume because it will need to be replaced anyway at that time), which will allow double tracking of this portion of railway. My question is what would be the cost of replacing this overpass today?
A3) In order to achieve 12-minute headways required to double Trillium Line capacity day-one, we do not need to replace the overpass. The 2038 date is related to when the City projects ridership growth could require us to move to 10-minute headways, which will require double-tracking at Walkley Station. The rough order of magnitude estimate for these works—new bridge, double track, west side platform and station connection) is $15-20 million.

Q4) In the event of future modification to the Trillium Line (examples include replacing the Walkley overpass as mentioned above, replacement of the Carling Avenue overpass, and relocation of Carling Station for better integration with the new hospital campus) can we expect the line to - once again - be shut down? Is this acceptable?
A4) There are ways these works (listed above) could be constructed with minimal operational impact (weekend and overnight work, for example). And these projects will be guided by future Council decisions.

Q5) It appears the new east platform for the Trillium Line at Bayview Station will have no elevators or escalators, instead it seems that passengers transferring to the Confederation Line will have to walk around the end of the Trillium Line (outside of the fair paid zone?) to access the west side's elevators / escalators. Is this correct?
A5) The primary purpose of the eastern platform at Bayview Station, is to provide redundancy and be available to park an out-of-service train. It will also support a potential future extension north to Gatineau. Day-to-day operations will prioritize the use of the western platform during normal operations, which provides for a more efficient transfer to Confederation Line. It is correct that there are no elevators or escalators direct from the Trillium Line new east platform up to the Confederation Line platforms. Should passengers be required to get off at Bayview on the new east platform, they would be required to walk around the end of the Trillium Line within the fare paid zone to the west side’s elevators and escalators up to transfer to Confederation Line. Weather protection for this connection is also being provided.

Q6) The new extension of Raven Road for the replacement bus service seems to benefit southbound transit vehicles only. I would assume northbound buses are delayed more trying to turn left at the Sunnyside Avenue intersection? (Note that I meant turning eastbound-left at Sunnyside, but the answer to this question does clear up a lot of my confusion regarding the R2 detour)
A6) The extension of Raven Road benefits both northbound and southbound buses on the R2 (formerly Route 107) detour; and the benefit to northbound buses will actually be greater.
Northbound R2 buses currently drive north on Bronson all the way to Sunnyside, and have to contend with the lengthy queue to turn left into the Carleton Campus. Once they get into the campus, they have to drive down University Drive, turn left on Campus Avenue, service the stop, continue south on Campus Avenue. and then head back north on University Drive and then turn left at Bronson to continue north.
Southbound R2 buses on Bronson turn right onto University Drive, turn left on Campus Avenue, service the stop, continue south on Campus Ave. and then head back north on University Dr, and then turn right at Bronson to continue south.
This constitutes a 2km loop in both directions.
With the Raven Road extension, northbound R2 buses will now be able to turn left from Bronson onto Raven Road, then turn right on University Drive service a stop adjacent to the Trillium Line station on the east side of Campus, continue north on University Drive and then turn left onto Bronson to continue north. This will eliminate the lengthy wait in the left turn queue at the Bronson/Sunnyside intersection, and also reduce the distance traveled within the Carleton Campus to 1.1km. Southbound R2 buses will have the same route as they do currently, except that instead of heading north on University Dr to exit the campus at Bronson/Sunnyside/University, they will instead be able to exit the campus at Raven Road/Bronson to continue south (reducing the distance traveled within the Carleton Campus to 1.6km).
Existing routes the use Carleton as a terminus (such as the 7, 10, 104) may continue to use the current routing, subject to OC Transpo operational decisions that are yet-to-be confirmed.
One of the biggest things learned, is that the Walkley overpass / second platform would only (only as a relative term) cost $15-20 M. I had always assumed it must be something more prohibitively expensive, something in the range of $50M.
Reply With Quote
     
     
  #1230  
Old Posted Mar 8, 2019, 2:41 PM
TransitZilla TransitZilla is offline
 
Join Date: Dec 2006
Posts: 2,801
Quote:
Originally Posted by Multi-modal View Post
I sent in some questions regarding the Trillium Line about a week ago, through my Councillor Shawn Menard. The answers have finally come back and I thought I'd share them here:
...

One of the biggest things learned, is that the Walkley overpass / second platform would only (only as a relative term) cost $15-20 M. I had always assumed it must be something more prohibitively expensive, something in the range of $50M.
Thanks a lot for posting this!

Based on the answer, it seems that the plan is consistent with the EA with the old Chiarelli plan, which was to add a 2nd underpass at Walkley rather than widen the existing one. This could likely be done without affecting operations. At only $15-20M, it is unfortunate they couldn't find a way to squeeze this in to give us 10-minute frequency from day 1. Maybe there is hope of doing this earlier than 2038...

The new bus access they will be building at Raven Rd sounds like it will be a great improvement, not just for the R2 detour bus, but also for the buses that access Carleton from Bilings Bridge (104 and 111).
Reply With Quote
     
     
  #1231  
Old Posted Mar 8, 2019, 2:44 PM
lrt's friend lrt's friend is offline
 
Join Date: Dec 2006
Posts: 12,814
Thank you for sharing. That is really good detailed information. It is too bad they won't do the Walkley overpass replacement now instead of waiting another 20 years given the relatively low cost compared to the overall cost of Phase 2. This would materially improve the Trillium Line for existing users and would have addressed my specific question that I had posed a week ago.
Reply With Quote
     
     
  #1232  
Old Posted Mar 8, 2019, 3:34 PM
CityTech CityTech is offline
 
Join Date: May 2016
Posts: 2,798
Only $20M? Thats ridiculous. We already blew the budget by just over a billion, $20M for a major improvement in service (12m to 10m headways) is nothing.

Its cheap enough that the city could do it at any time really. We should be lobbying council hard to tack it on the contract. Thats a small enough item that we could negotiate its addition to the SNC contract even after its signed. This isn't done yet.
Reply With Quote
     
     
  #1233  
Old Posted Mar 8, 2019, 3:39 PM
Multi-modal Multi-modal is offline
 
Join Date: Jul 2014
Posts: 1,154
Quote:
Originally Posted by CityTech View Post
Thats a small enough item that we could negotiate its addition to the SNC contract even after its signed. This isn't done yet.
I replied to Shawn Menard explaining some of the many advantages of implementing this relatively low-cost change, including:
  • The ability to decrease headways from 12 minutes to 10 minutes, and therefore improve user experience by decreasing average waiting time from 6 minutes to 5 minutes
  • Possible increase in overall Trillium Line travel speed (as trains will not have to proceed slowly from Walkley Station to the Brookfield Siding switch
  • Possible increase in ridership due to improved user experience as noted in the above two points
  • An improved Walkley Station, with option for an enlarged Station plaza off Walkley Road (a twin to Gladstone Station)
  • Increased operational flexibility
  • Future proofing the Trillium Line past 2038
  • Cost savings, as replacing the overpass will be more expensive if it has to be done in 2038 during Trillium Line operation "with minimal operational impact (weekend and overnight work, for example)"
I hope others alert their Councillors to this low-cost improvement opportunity.
Reply With Quote
     
     
  #1234  
Old Posted Mar 8, 2019, 4:58 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
 
Join Date: Mar 2012
Posts: 29,160
Thanks for the info. Very informative.

What I don't understand is how in 2015 they thought they could achieve an 8-minute frequency (and failed), yet today, double tracking at Walkley, which was not part of the scope in 2015 or today, would only achieve a 10-minute frequency. Who was responsible for this massive waste of money in 2015 and have they been fired since then?
Reply With Quote
     
     
  #1235  
Old Posted Mar 8, 2019, 5:01 PM
LRTeverywhere LRTeverywhere is offline
 
Join Date: Oct 2018
Posts: 326
I have also just contacted Shawn Menard, I made sure to mention the improvements having a consistent 10 min frequency on the line would be for bus transfers that could be timed to it. I mentioned the cost savings of doing it now rather than later as well as the disruption to both Walkley road and a more used trillium line
Reply With Quote
     
     
  #1236  
Old Posted Mar 8, 2019, 5:11 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
 
Join Date: Mar 2012
Posts: 29,160
One thing that really bothered me listing to the council meeting from March 6 was how City Staff refused to answer the simple question of whether or not it would be possible for bidding proponents to win the contract without meeting the 70% evaluation threshold.

Diane Deans asked about 10 times, and the answers was always "can't say due to confidentiality, can't release scoring (which was never asked but always part of their response)".

When Lieper re-formulated the question (instead of did they, he used a theoretical could a), they blinked and sort of answered, but quickly back-tracked and returned to their one liner. McKenney asked again later, using something closer to Leiper's wording with the same broken record response.

So they can't answer this simple question purely related to the process and not individual scores, yet last week, they were able to divulge, voluntarily I might add, that East-West Connectors' bid was hundreds of millions less than their competitors. Wouldn't that be a much bigger breach of confidentiality?
Reply With Quote
     
     
  #1237  
Old Posted Mar 8, 2019, 5:21 PM
lrt's friend lrt's friend is offline
 
Join Date: Dec 2006
Posts: 12,814
Quote:
Originally Posted by Multi-modal View Post
I replied to Shawn Menard explaining some of the many advantages of implementing this relatively low-cost change, including:
  • The ability to decrease headways from 12 minutes to 10 minutes, and therefore improve user experience by decreasing average waiting time from 6 minutes to 5 minutes
  • Possible increase in overall Trillium Line travel speed (as trains will not have to proceed slowly from Walkley Station to the Brookfield Siding switch
  • Possible increase in ridership due to improved user experience as noted in the above two points
  • An improved Walkley Station, with option for an enlarged Station plaza off Walkley Road (a twin to Gladstone Station)
  • Increased operational flexibility
  • Future proofing the Trillium Line past 2038
  • Cost savings, as replacing the overpass will be more expensive if it has to be done in 2038 during Trillium Line operation "with minimal operational impact (weekend and overnight work, for example)"
I hope others alert their Councillors to this low-cost improvement opportunity.
There is a bigger advantage of doing it now.

That is transfers between the Trillium Line and local bus routes. I am not a regular user of the Trillium Line but I have already been burned ie just missed a transfer by one minute and left waiting 29 minutes for the next local bus.

12 minute frequency does line up with 30 minute local bus schedules well. The user is left guessing about how to time the start of their trip.

If we get this down to 10 minutes, timed transfers will be easy to schedule and the chances of a missed transfers greatly reduced.

With rail service, timed transfers are most important. The user experience is critical if we hope to gain ridership.
Reply With Quote
     
     
  #1238  
Old Posted Mar 8, 2019, 5:29 PM
Multi-modal Multi-modal is offline
 
Join Date: Jul 2014
Posts: 1,154
Quote:
Originally Posted by J.OT13 View Post
One thing that really bothered me listing to the council meeting from March 6 was how City Staff refused to answer the simple question of whether or not it would be possible for bidding proponents to win the contract without meeting the 70% evaluation threshold.

Diane Deans asked about 10 times, and the answers was always "can't say due to confidentiality, can't release scoring (which was never asked but always part of their response)".

When Lieper re-formulated the question (instead of did they, he used a theoretical could a), they blinked and sort of answered, but quickly back-tracked and returned to their one liner. McKenney asked again later, using something closer to Leiper's wording with the same broken record response.

So they can't answer this simple question purely related to the process and not individual scores, yet last week, they were able to divulge, voluntarily I might add, that East-West Connectors' bid was hundreds of millions less than their competitors. Wouldn't that be a much bigger breach of confidentiality?
I was OK with staff answers on this (and wish Councillors had spent more time on other things once it became clear staff were entrenched in their position). Saying whether or not all the bidders achieved over 70% is akin to giving the public a range or where the the bids fell (above 70% or below 70%), and they could not do that.

You are right though, they probably shouldn't have said that East-West Connectors' bid was hundreds of millions less than their competitors.
Reply With Quote
     
     
  #1239  
Old Posted Mar 8, 2019, 5:31 PM
Multi-modal Multi-modal is offline
 
Join Date: Jul 2014
Posts: 1,154
Quote:
Originally Posted by lrt's friend View Post
There is a bigger advantage of doing it now.

That is transfers between the Trillium Line and local bus routes. I am not a regular user of the Trillium Line but I have already been burned ie just missed a transfer by one minute and left waiting 29 minutes for the next local bus.

12 minute frequency does line up with 30 minute local bus schedules well. The user is left guessing about how to time the start of their trip.

If we get this down to 10 minutes, timed transfers will be easy to schedule and the chances of a missed transfers greatly reduced.

With rail service, timed transfers are most important. The user experience is critical if we hope to gain ridership.
Good point, I forgot about this. (Also credit to LRTeverywhere - welcome to the forum!). Even more reason to pressure our elected and unelected officials regarding this.
Reply With Quote
     
     
  #1240  
Old Posted Mar 8, 2019, 5:54 PM
PHrenetic PHrenetic is offline
 
Join Date: Jun 2016
Posts: 1,029
Quote:
Originally Posted by Multi-modal View Post
I was OK with staff answers on this (and wish Councillors had spent more time on other things once it became clear staff were entrenched in their position). Saying whether or not all the bidders achieved over 70% is akin to giving the public a range or where the the bids fell (above 70% or below 70%), and they could not do that.

You are right though, they probably shouldn't have said that East-West Connectors' bid was hundreds of millions less than their competitors.
Good Day.

I believe she was asking (and never got an answer) if all bidders met the RFP minimum 70% margin.
There is no contractually confidential information to be revealed (unless the answer was no) in answering the question.
Therefore, one could infer that the answer was indeed no, which is what she stated in her reasoning for her vote.

Something I also noted in the presentations over this last week......
the City has once again reserved all communications with and to the public (and to Council ?) concerning Phase 2, to the City.
So, we a re right back into the total (in effect) blackout of ANY information as to the contract, plans, construction, deadlines, etc.
IE: .......No Lessons Learned !

NoJoy!
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 10:51 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.