Old Posted Feb 10, 2019, 2:47 PM
McC's Avatar
McC McC is offline
Registered User
 
Join Date: Apr 2010
Posts: 3,057
Quote:
Originally Posted by Truenorth00 View Post

I can envision the the city lacked the experience to write a contract with sufficient teeth and maybe lacks quality lawyers for the scope involved.
I thought Infrastructure Ontario handled this part for exactly this reason? IIRC, the procurement won an award from a big P3 industry association; you can have fun with hideously-cynical imaginations of why the P3 industry would think this was a model procurement...
     
     
  #9342  
Old Posted Feb 10, 2019, 3:13 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is online now
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,691
It would seem to me that any delay at this point would be due to the city insisting on certain standards set in the contract. It's pointless to open the line if there are deficiencies that could affect optimal performance, especially if it would require a shutdown to mitigate an issue. A breakdown can not only erode the public's perception and confidence in the system, it could also cost OC Transpo a lot of money to respond to.
     
     
  #9343  
Old Posted Feb 10, 2019, 4:02 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
It would depend on what these deficiencies are, I guess. If it's possible to open the lines at peak periods only and do the corrections evenings and weekends, let's do that for now. Rush hour needs the line, bad.
     
     
  #9344  
Old Posted Feb 10, 2019, 4:10 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Quote:
Originally Posted by CityTech View Post
It would depend on what these deficiencies are, I guess. If it's possible to open the lines at peak periods only and do the corrections evenings and weekends, let's do that for now. Rush hour needs the line, bad.
Good Day.

Much as we might hate it, I do not think that would be a good idea. Despite the bally-hoo of 'safety' as an excuse, it still remains true, and then there is the even larger bear of 'liability' - both for costs and safety. Trying to run a partial service would also be complex (for OC, that is... <snort>) and lead to some confusion as to which what where at what time for some people.

IMHO.
     
     
  #9345  
Old Posted Feb 10, 2019, 5:17 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by PHrenetic View Post
Good Day.

Much as we might hate it, I do not think that would be a good idea. Despite the bally-hoo of 'safety' as an excuse, it still remains true, and then there is the even larger bear of 'liability' - both for costs and safety. Trying to run a partial service would also be complex (for OC, that is... <snort>) and lead to some confusion as to which what where at what time for some people.

IMHO.
I guess it all depends on on what we learn Tuesday. Difficiencies in terms of the contract aren't necessarily safety or operational. There can be aesthetic or other minor difficiencies as well that wouldn't affect the line operations, but can still cause contractual headaches between lawyers over who pays for what.
     
     
  #9346  
Old Posted Feb 10, 2019, 5:58 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
^ I mean the landscaping work that remains obviously can't be done until spring but that wouldn't prevent the line from opening. But because the landscaping is in the contract, it might be legally complicated to do the handover while it remains incomplete. Perhaps that's the cause of all of the drama, trying to figure out how that could work. If landscaping is literally the only stuff outstanding by March 31, it would be ridiculous to delay handover & opening solely over that. That's stuff they can easily work around an operating line (perhaps having certain parts of the station exteriors closed on weekends to do the work).
     
     
  #9347  
Old Posted Feb 10, 2019, 6:15 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is online now
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,691
It will take more than the landscaping no doubt. If there is no assurance and demonstration that the line can operate optimally, I don't think the city should accept a handover. Would you buy a deficient car with the chore of having to send it to the mechanic every weekend until it's done to your satisfaction?
     
     
  #9348  
Old Posted Feb 10, 2019, 8:44 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by Kitchissippi View Post
It will take more than the landscaping no doubt. If there is no assurance and demonstration that the line can operate optimally, I don't think the city should accept a handover. Would you buy a deficient car with the chore of having to send it to the mechanic every weekend until it's done to your satisfaction?
Even if it is just the landscaping, once you've accepted the line with minor issues there is no more leverage over RTC. They could leave blemishes and incomplete landscaping for months or even years (it's happened elsewhere) while lawyers fight it out.
     
     
  #9349  
Old Posted Feb 10, 2019, 8:55 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
I wonder if RTG is trying to do blackmail of sorts, by offering to handover the line with some remaining work and/or trying to force the city into dropping its requests for compensation for the delays, with the implication of delaying the handover further if the city refuses.
     
     
  #9350  
Old Posted Feb 11, 2019, 4:56 PM
zzptichka zzptichka is offline
Registered User
 
Join Date: Dec 2015
Location: Outaouias
Posts: 2,381
Bus shelter at Pimisi. Not sure about this one. It's going to be crowded here in the morning and it takes so much space...

     
     
  #9351  
Old Posted Feb 12, 2019, 3:52 AM
Catenary Catenary is offline
Registered User
 
Join Date: Dec 2012
Posts: 1,403
Quote:
Originally Posted by zzptichka View Post
Bus shelter at Pimisi. Not sure about this one. It's going to be crowded here in the morning and it takes so much space...

I spotted Enseicom installing those last week, but I assumed they were the Confederation Line standard units like Tunney's, Blair and Hurdman have. Interesting to see a different design without the doors or provisions for heating.
     
     
  #9352  
Old Posted Feb 12, 2019, 2:19 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Misery loves company:


CBC.ca: Valley Line Southeast LRT behind schedule, Edmonton council told.
https://www.cbc.ca/news/canada/edmonton/edmonton-valley-line-southeast-lrt-1.5015144
     
     
  #9353  
Old Posted Feb 12, 2019, 2:42 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,032
FEDCO meeting has started. Manconi presenting a 3D video tour of Lyon Station as part of the Ready4Rail campaign. Just one problem: NO GOD DAM VIDEO FEED!!!!! Live stream is AUDIO ONLY!!!! It's been broken since yesterday at least.

https://www.youtube.com/watch?v=ZMrSxhtqnVo
     
     
  #9354  
Old Posted Feb 12, 2019, 2:45 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,032
Lyon Station 3D tour is available on the Ready4Rail website. We don't get the fancy video presented at FEDCO however.

http://www.octranspo.com/ready4rail/my_station#lyon_360
     
     
  #9355  
Old Posted Feb 12, 2019, 2:52 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,800
Quote:
Originally Posted by J.OT13 View Post
FEDCO meeting has started. Manconi presenting a 3D video tour of Lyon Station as part of the Ready4Rail campaign. Just one problem: NO GOD DAM VIDEO FEED!!!!! Live stream is AUDIO ONLY!!!! It's been broken since yesterday at least.

https://www.youtube.com/watch?v=ZMrSxhtqnVo
All committee meetings are audio-only. Only full Council meetings have video.
     
     
  #9356  
Old Posted Feb 12, 2019, 2:55 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,032
Quote:
Originally Posted by bradnixon View Post
All committee meetings are audio-only. Only full Council meetings have video.
I thought I remembered seeing a few FEDCO meetings with video, but I could be wrong? Why wouldn't they have video? At the very least, show the presentations.
     
     
  #9357  
Old Posted Feb 12, 2019, 3:04 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,800
RTG has stated they still believe they can meet March 31.
     
     
  #9358  
Old Posted Feb 12, 2019, 3:36 PM
kevinbottawa kevinbottawa is offline
Registered User
 
Join Date: May 2010
Location: Toronto
Posts: 2,260
Quote:
Originally Posted by bradnixon View Post
RTG has stated they still believe they can meet March 31.
Just saw on Twitter John Manconi is skeptical they'll make the March 31st deadline.
     
     
  #9359  
Old Posted Feb 12, 2019, 3:44 PM
daud's Avatar
daud daud is offline
Registered User
 
Join Date: Jun 2012
Location: Ottawa
Posts: 763
Quote:
Originally Posted by kevinbottawa View Post
Just saw on Twitter John Manconi is skeptical they'll make the March 31st deadline.
I'd really like to know what is going on. Its all a bit vague based on what I see on Twitter. There's no smoking gun-just seems to be a lot of small stuff.

Is the city getting nit picky? Are there serious deficiencies?
     
     
  #9360  
Old Posted Feb 12, 2019, 4:14 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
RTG is confident on March 31 but Manconi isn't. Sole issue at this point is actually fleet availability. Only 24 of 34 trains have been given final certification.

Train testing is going very well apparently. Station construction not a concern, will be done within weeks. Parliament is fully complete.

City expects to know for sure March 5th.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 1:09 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.