Quote:
Originally Posted by West Peachtree
Is there a plan for Spring St and West Peachtree St to be converted from one way to two way, as well?
If so, is there a working timetable for two way conversions for Spring and West Peachtree? They each seem to be working efficiently as is, in my opinion.
Maybe the two way conversion applies only, as you say, to "cross streets" as we saw on 7th and 8th and 13th - among others.
https://www.midtownatl.com/about/midtown...16/7th-street-converts-to-two-way-access
With all the development in progress (CODA, ANTHEM, Northside Hospital, Arts Center vicinity), and planned, (Cousins' 8th @ West, Midtown Union, Selig's 1105 West Peachtree, etc) though, could there be a change planned these next 5- 10 years for Spring and West Peachtree ?
Does anyone know the long term vision for Spring street and West Peachtree street?
|
Last I heard was from Midtown Alliance's Transportation, where both were to remain one way streets, w/ a complete streets improvement including separated bikeways. West peachtree was planned to be converted two ways only between:
"North Ave to Pine St"
Part of Spring Street Improvements (at least engineering & design) are already under way at the northern section.
https://www.midtownatl.com/about/program...ements/spring-street-improvement-project
BK-01 West Peachtree Street Complete
Street (Pine Street to Peachtree Street)
West Peachtree currently has a northbound bike lane
extending from North Avenue to 12th Street. The narrow
width and placement of the current bike lane between onstreet
parking and fast moving vehicles makes for an unsafe
facility. This project retains the one-way operation north of
North Avenue and repurposes one travel lane to create a
buffered northbound cycle track. South of North Avenue,
West Peachtree would convert to two-way operation with
bike lanes in each direction. This project also includes
sidewalk improvements, bus shelters, and other traffic
calming strategies. When demand for car travel decreases
in the future, it is recommended that West Peachtree Street
be fully converted to two-way operation.
BK-02 Spring Street Complete Street (17th to
Linden Avenue)
Spring Street, the southbound complement to West
Peachtree Street, is in need of significant improvements
to the pedestrian environment. Redevelopment is finally
occurring on this corridor but there are major safety and
comfort issues that need to be addressed. This project
includes new sidewalks with pedestrian amenities and
repurposes one travel lane to create a buffered southbound
cycle track. When demand for car travel decreases in
the future, it is recommended that Spring Street be fully
converted to two-way operation.