HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation


Closed Thread

 
Thread Tools Display Modes
     
     
  #4521  
Old Posted May 9, 2017, 10:33 PM
HighwayStar's Avatar
HighwayStar HighwayStar is offline
Registered User
 
Join Date: Jul 2014
Location: PHX (by way of YOW)
Posts: 1,200
Quote:
Originally Posted by PHrenetic View Post
Good Day....
I would have to hazard an opinion that they are to accommodate the greater range of temperature fluctuations experienced in Ottawa than in almost any other location in the world, from -40c to +35c at average extremes, which means a heck of a lot of contraction/expansion in the rails / OCS / signal cables / etc that no one else commonlly sees. IMHO.
EnJoy!
Edmonton? Calgary? Moscow?

Hard to tell by googling the pictures... but they would be comparable systems.
     
     
  #4522  
Old Posted May 9, 2017, 11:23 PM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,822
Quote:
Originally Posted by HighwayStar View Post
Edmonton? Calgary? Moscow?

Hard to tell by googling the pictures... but they would be comparable systems.
This is the first cold weather application of the citadis
     
     
  #4523  
Old Posted May 10, 2017, 2:37 AM
Beedok Beedok is offline
Exiled Hamiltonian Gal
 
Join Date: Jun 2012
Posts: 6,793
Quote:
Originally Posted by HighwayStar View Post
Edmonton? Calgary? Moscow?

Hard to tell by googling the pictures... but they would be comparable systems.
Ottawa is both colder in winter and hotter in summer than Moscow. Not by a huge amount, but a bit.
     
     
  #4524  
Old Posted May 10, 2017, 11:05 AM
HighwayStar's Avatar
HighwayStar HighwayStar is offline
Registered User
 
Join Date: Jul 2014
Location: PHX (by way of YOW)
Posts: 1,200
Quote:
Originally Posted by Beedok View Post
Ottawa is both colder in winter and hotter in summer than Moscow. Not by a huge amount, but a bit.
Well.. if you want to get really picky.. Regarding average temperatures, the above statement is true, however the record cold AND record high temperatures in Moscow both exceed Ottawa's extremes... Same for Edmonton by the way.

Only Calgarys record high is lower than Ottawa... all of which kind of makes us look kind of moderate by comparison

Of course, point being that Ottawa is not the first to install an LRT in this climate, though the point about being the first Citadis is well taken.
     
     
  #4525  
Old Posted May 10, 2017, 11:22 AM
eltodesukane eltodesukane is offline
Registered User
 
Join Date: Dec 2011
Posts: 1,144
Ottawa 2016 temperature
     
     
  #4526  
Old Posted May 12, 2017, 3:46 AM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Eastern Ontario
Posts: 12,377
New report on LRT timelines.

May 24th, 2018 is the scheduled date for the handover of the LRT from RTG to the City. RTG is reportedly on track to meet that date, and they face financial penalties if they don't.

June 24th, 2018 is looking likely for revenue service, as I predicted earlier. It gives the City a month to do final quality assurance and lines up with OC Transpo's scheduled service changes.
     
     
  #4527  
Old Posted May 16, 2017, 2:00 AM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Good Day....just a spotter report :
OCS wire puller on the westbound track on the bridge over Riverside Drive, between Tremblay and Hurdman stations.
EnJoy!
     
     
  #4528  
Old Posted May 17, 2017, 2:26 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,518
Construction Update
Week of May 8


Station construction advances along the alignment. This week, steel beams are delivered at Tunney’s Pasture Station to begin the next phase of construction, walls are being formed and poured at Lees Station and crews mobilize to begin final platform finishes at Cyrville and Blair stations.



Tunney's Pasture Station rebar and station wall concrete work

West Stations


Tunney’s Pasture Station
Station construction continues to progress with the construction of the retaining wall and installation of steel beams. Work on the foundation also occurs and includes construction of footings and ongoing rebar and formwork.

Bayview Station
Backfilling and final grade beam installation occurs this week and crews continue working on columns and the upper concourse slab.

Pimisi Station
Crews continue installing structural steel and conduits at the station, and pouring concrete for slabs.



Lyon Station cavern progress of architectural work

Central Stations


Lyon Station cavern
Crews prepare to install hardware on doors this week, and continue guardrails, tiling on the south side of the platform, and painting stairs and sections of the ceilings.

Lyon Station west entrance
Crews continue installing structural steel for the head house and working on stairs; including forming and pouring concrete, followed by curing. Forming of the roof of the elevator shaft as part of work on elevators is also ongoing. At the east vent shaft, walls are poured and cured in phases.

Lyon Station east entrance
Integrated entrance construction advances and includes the installation of structural steel and masonry on the concourse and ground levels, and concrete work and curing on the mezzanine level. Work on elevators, installation of escalators, rough-ins and the HVAC also occur. Concrete work is ongoing at the HVAC shaft.



Rock removal and shoring advances at the Parliament Station

Parliament Station cavern
Arch concrete lining work is ongoing and includes waterproofing and rebar installation on the cavern walls. In addition, architectural work takes place in the cavern, and formwork and concrete pours also occur for the pillars.

Parliament Station west entrance
Crews continue with shoring activities and rock removals this week. Sections of shotcrete are also removed to begin the next phase of station construction this week.

Parliament Station east entrance
Entrance construction continues to advance with the installation of dowels, rebar and formwork for the lower pits, and mud slab work for the stairs. Rebar and concrete pours occur for the stair walls, and concourse walls are formed and poured.




Rideau Station cavern
This week, crews work on the invert, install rebar and formwork, begin concrete pours for the columns and continue waterproofing walls on the north side of the cavern.

Rideau Station west entrance
Mining of the entrance escalator occurs this week.

Rideau Station east entrance
Crews install falsework and rebar on the ground level slabs, stairs and escalator pits. They will also begin concrete pours by end of the week and install rebar on the south and west walls.



Structural steel installation at uOttawa Station

East Portal
This week, crews install tiebacks, rock bolts and whaler beams, and continue forming and pouring concrete for the ramp’s east walls.

uOttawa Station
The next section of structural steel installation occurs, along with platform slab construction. Crews also begin roofing work and framing for the concourse panels, and complete duct banks and mechanical work at the station.



Ongoing structural steel installation and concrete work at Lees Station

East Stations


Lees Station
Construction progresses at the station and includes ongoing installation of masonry at the ancillary building. Rough-ins, installation structural steel sections and concrete works for the upper concourse slab also occur.

Hurdman Station
This week, crews finalize work at the south escalator, continue concrete work for the suspended slabs and station signage, and begin the new phase of communications systems work in the secondary building

Tremblay Station
The next phase of station activities progresses with ongoing porcelain and composite panel installation, rough-ins, work on elevators and chipping of the parapet at the west ring road. At the entrance plaza, landscape work progresses.



Initial landscape work continues at the Tremblay Station entrance

St-Laurent Station
This week, crews begin the next phase of work on the stairs, including the installation of precast concrete. Work on the head house HVAC shaft and on station signage, wiring for the doors, escalator cladding, painting and final porcelain panel installation are also ongoing.

Cyrville Station
Crews mobilize to begin final finishes for the platform, including installation of precast concrete on the stairs and of the last section of porcelain panels. Glazing and work on the station signage is also ongoing for the next weeks.

Blair Station
Construction advances at the station. This week, crews mobilize to begin final finishes on the platform, continue installing precast concrete stairs, work on the windscreen in the pedestrian bridge area and glazing at the lower concourse area.



Installing dowels and pulling rail in tunnel moving west to Lyon Station cavern

Guideway and Trackwork


Construction of plinths and trackwork is ongoing east of Tunney’s Pasture Station to Bayview Station. Trackwork is advancing in the tunnel, including dowel installation, moving west to Lyon Station. From Lees Station to Hurdman Station, crews pull rail, install concrete ties and continue ballast tamping in sections. Overhead Catenary System wires and final work also occur west of St-Laurent Station.



Installing Overhead Catenary System poles on guideway west of Bayview Station

Upcoming Construction Activities


In the coming weeks, the following construction activities are scheduled to occur:
  • Hoe ramming as part of work on the western section of the guideway.
  • Delivery and installation of the Traction Power Sub Station east of Pimisi Station.
  • Ongoing overnight work at the Rideau Station west and east entrances, and at the East Portal.
  • Next stage of work at uOttawa Station requiring overnight lane restrictions.
  • Final work on the pedestrian tunnel at uOttawa Station.
  • Hydro connection work to Hurdman Station requiring lane restriction on Riverside Drive.
  • Manhole work as part of guideway activities at intersection of Riverside Drive and Tremblay Road, requiring lane restrictions.
  • Fencing installation on guideway just west of Tremblay Station.
  • Glazing at Tremblay Station.
  • Systems installation along the guideway, including Overhead Catenary System poles and wires

http://www.ligneconfederationline.ca/news/construction-update-123/
     
     
  #4529  
Old Posted May 17, 2017, 3:33 AM
Admiral Nelson Admiral Nelson is offline
Registered User
 
Join Date: Jun 2009
Posts: 518
With all the structural steel going up this is looking tantalizingly close. Give it 6 months and much of it will look visually complete.
     
     
  #4530  
Old Posted May 17, 2017, 12:34 PM
eltodesukane eltodesukane is offline
Registered User
 
Join Date: Dec 2011
Posts: 1,144
Are those completion dates still valid?

     
     
  #4531  
Old Posted May 17, 2017, 12:46 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by acottawa View Post
This is the first cold weather application of the citadis
This is the first application of the Citadis Spirit in any climate. I know someone who until very recently worked for Alstom and he said the different lines of Citadis trains share little in common other than the name. This is especially true for the Citadis Spirit, as it has to conform to North American design standards. Even the wiring harnesses had to be redesigned to use North American gauge wire instead of European.
     
     
  #4532  
Old Posted May 18, 2017, 8:41 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Good Day...

stage2lrt.ca documents update : Belfast Yard Expansion – Community Information Session –  Presentation/Boards – May 17, 2017

http://www.stage2lrt.ca/wp-content/uploads/2015/06/Belfast-Expansion-Meeting-May-17-2017-ENG.pdf

Seems to be a minor revision and update of the MSF expansion details, and 3 photo updates of Tremblay (2) and St.Laurent (1) stations. No big deal.

EnJoy!
     
     
  #4533  
Old Posted May 19, 2017, 1:38 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,518
Westin hotel parent sues city, RTG over alleged sinkhole damages

Jon Willing, Ottawa Citizen
Published on: May 18, 2017 | Last Updated: May 18, 2017 5:54 PM EDT


The City of Ottawa and Rideau Transit Group owe at least $100,000 to the company that runs The Westin Ottawa hotel because of damages related to the massive sinkhole almost one year ago, a lawsuit claims.

The lawsuit, filed this week by the U.S.-based Starwood Capital Group, describes how the busy hotel had to be evacuated on June 8, 2016 after receiving an order from the RCMP, forcing the cancellation of events booked in the facility.

On that morning, a chunk of Rideau Street just east of Sussex Drive opened up without warning, swallowing a van that was parked on the side of the road and exposing a broken watermain that spewed water into the gaping hole.

No one was reported injured, but nearby businesses, including the hotel and the attached Rideau Centre, had to be evacuated while engineers made sure people could safely return to the buildings.

According to Starwood’s lawsuit, the Westin hotel on Colonel By Drive had a 98-per-cent occupancy when the sinkhole happened.

The evacuation order ended in the late afternoon, but the hotel still had problems with the water and natural gas supply for several days after the sinkhole, the lawsuit says.

“Several banquets and catered events which were scheduled to take place at the hotel on June 8, 2016 were cancelled on account of the evacuation order as well as a number of room reservations which were cancelled or could not be fulfilled,” the lawsuit says.

On top of that, the company says it racked up “significant out-of-pocket expenses” to compensate staff and customers because of the inconveniences.

It’s all the fault of the city and RTG, the company says.

None of the allegations has been tested in court.

“The City of Ottawa does not comment on matters before the courts,” city solicitor and clerk Rick O’Connor said in an email.

RTG spokeswoman Kathryn Keyes said the consortium also doesn’t comment on legal matters.

Among the 15 allegations directed at RTG, Starwood claims the construction consortium designed the LRT project “without adequate structural support and bracing to prevent against the formation of the sinkhole.”

Starwood attempts to pin blame on RTG for allegedly not inspecting the LRT construction and supervising the work of construction employees. The LRT builder should have known, “or with reasonable diligence could have known,” that the design and construction was deficient, the lawsuit says.

There are also 10 allegations levelled at the city, including claims that the city failed to supervise the contractor and make sure Rideau Street in the area of the sinkhole “was in a reasonable state of repair in the circumstances.”

Starwood says it suffered property damage, a loss of profits and an accumulation of other expenses because of the “negligence” by the city and RTG.

The company says it doesn’t yet know the precise value of the damages.

The city released a report in April that investigated the cause of the sinkhole, but the lawsuit doesn’t reference the report.

The report, which was completed for the city by McMillen Jacobs Associates, says the LRT tunnelling work under Rideau Street disturbed the soft soil.

The city and RTG knew about the ground conditions in the area.

When the city released the report, it revealed it had received 32 claims for compensation from property owners and businesses affected by the sinkhole.

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/news/local-news...s-city-rtg-over-alleged-sinkhole-damages
     
     
  #4534  
Old Posted May 20, 2017, 7:59 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by rocketphish View Post
Among the 15 allegations directed at RTG, Starwood claims the construction consortium designed the LRT project “without adequate structural support and bracing to prevent against the formation of the sinkhole.”

Starwood attempts to pin blame on RTG for allegedly not inspecting the LRT construction and supervising the work of construction employees. The LRT builder should have known, “or with reasonable diligence could have known,” that the design and construction was deficient, the lawsuit says.

There are also 10 allegations levelled at the city, including claims that the city failed to supervise the contractor and make sure Rideau Street in the area of the sinkhole “was in a reasonable state of repair in the circumstances.”
These alogations sound more like those from a 2 bit, late night television lawyer. You would think a big company like Starwood would have the money to hire a decent lawyer who would build a decent case and not throw out random alogations like mud, in the faint hope that one will stick.
     
     
  #4535  
Old Posted May 21, 2017, 2:02 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,518
Construction Update
Week of May 15


Along with the LRT stations, where progress is visible from Tunney’s Pasture to Blair, the guideway continues to take shape. Overhead Catenary System poles west of Bayview Station moving east continue to be installed, as well as concrete ties just west of Pimisi Station. Crews also continue pulling rail in the running tunnel moving east to Lyon Station.



Concrete work and structural steel installation at Bayview Station

West Stations


Tunney’s Pasture Station
Concrete pours occur for the foundation walls and slabs. Shoring begins for the concourse slab this week and steel beam installation also takes place.

Bayview Station
Construction advances and includes work on the west side of the station for the platform slabs. Rebar and formwork installation is also ongoing as part of concrete work. Crews pour remaining concourse slabs.



Progress at the Pimisi Station upper concourse

Pimisi Station
Concrete slab pours and installation of structural steel are ongoing. Mechanical and electrical rough-in work, as well as falsework, is ongoing for the west upper concourse. Waterproofing of walls will commence.



Progress of work at Parliament Station east entrance

Central Stations


Lyon Station cavern
Architectural work progresses in the cavern with ongoing block wall and ceiling work, installation of doors and hardware, and mechanical and electrical rough-ins in the HVAC room.

Lyon Station west entrance
The integrated entrance continues to take shape with ongoing concrete works on the ground floor, as well as forming and pouring over the elevator shaft. Crews continue waterproofing and drilling for dowels at the east vent shaft. Blasting activities and rock removals occur at the Lyon west vent shaft.

Lyon Station east entrance
This week, installation of the station elevators is ongoing. In addition, framing for glazing is being installed at the retail concourse level. Concrete work takes place on the mezzanine level and final concrete works occur at the HVAC shaft.

Parliament Station cavern
Crews waterproof and install rebar on the station’s end walls, arches and starter walls. Duct bank concrete work between the station and the intermediate shaft gets underway.

Parliament Station west entrance
Integrated entrance construction advances with pouring of mud slabs, installation of columns for elevators and ongoing mechanical and electrical work.

Parliament Station east entrance
Concrete work includes pouring of the north and east walls and the mud slab this week.



Ongoing structural steel installation at uOttawa Station

Rideau Station cavern
Construction of the station cavern continues to advance, with final lining work occurring on the arch and the invert. Waterproofing and rebar installation also continue.

Rideau Station west entrance
Excavation of the west entrance is now completed. Waterproofing on the invert begins.

Rideau Station east entrance
Integrated entrance construction continues to advance with ongoing formwork for escalator pits and installation of rebar and formwork for exterior walls.

East Portal
Work continues with rebar installation and concrete pours on the west and east walls of the ramp.

uOttawa Station
The station continues to take shape with ongoing concrete work. Roofing and framing for upcoming porcelain panel installation of the concourse level progresses. Next phase of steel installation to commence. Construction also begins on the station plaza this week.



Structural steel installation continues at Hurdman Station

East Stations


Lees Station
Installation of masonry on the ancillary building advances at the station, along with rebar, formwork and concrete pours in cycles for the upper concourse area. Crews are mobilizing to begin work on the service trench connecting the station and the ancillary. Mechanical and electrical rough-ins at concourse level are ongoing. The next phase of structural steel work also takes place this week.

Hurdman Station
Progress continues to be visible at the station with ongoing framing and structural steel installation, escalator and electrical work. Concrete pours for the suspended slabs are continuing. Installation of the south escalator will occur. Interior finishing at the bus operator building is continuing.

Tremblay Station
Crews continue installing composite and porcelain panels and working on elevators to prepare for the arrival of the machines. Initial landscaping also occurs and includes parapet work at the west ring road. Concrete construction is ongoing, including curbs. Elevator installation and painting of structural steel is ongoing. Skylight framing and glazing to commence.



Initial work for skylight framing at Tremblay Station

St-Laurent Station
Final platform finishes, precast concrete on the stairs and work on doors and escalator cladding are ongoing. Masonry is being completed. Platform level electrical and sprinkler installation at the concourse is ongoing.

Cyrville Station
Construction includes glazing, work on precast stairs, and station signage. Concrete pour for platform topping and landscaping to commence. Sign and conduit work is progressing.

Blair Station
Crews install railings and precast concrete on stairs. Glazing activities and final finishes on the platform are ongoing. Porcelain panel, door and hardware installation is ongoing. Testing and commissioning of mechanical equipment is underway. Light fixture installation and interior finishing continues.



Trackwork advances along guideway in the west

Guideway and Trackwork


The guideway continues to take shape along the alignment: Overhead Catenary System poles are being installed just west of Bayview station moving east to Pimisi Station, rails are being pulled and dowels installed in the tunnel moving east. In addition, trackwork activities occur just east of uOttawa Station to Hurdman Station, including pulling rail and ballast tamping. System crews have completed the installation of wires to allow the test track and vehicle testing to advance in the east section of the alignment.



Progress of track and dowel work in tunnel west of Lyon Station

Upcoming Construction Activities


In the coming weeks, the following construction activities are scheduled to occur:
  • Hoe ramming as part of work on the western section of the guideway.
  • Delivery and installation of the Traction Power Sub Station east of Pimisi Station.
  • Ongoing overnight work at the Rideau Station west and east entrances and at the East Portal.
  • Next stage of work at uOttawa Station requiring overnight lane restrictions.
  • Final work on the pedestrian tunnel at uOttawa Station.
  • Hydro connection work to Hurdman Station requiring lane restriction on Riverside Drive.
  • Manhole work as part of guideway activities at intersection of Riverside Drive and Tremblay Road, requiring lane restrictions.
  • Fencing installation on guideway just west of Tremblay Station.
  • Glazing at Tremblay Station.
  • Systems installation along the guideway, including Overhead Catenary System poles and wires.

http://www.ligneconfederationline.ca/construction/construction-update-124/
     
     
  #4536  
Old Posted May 22, 2017, 5:35 AM
Admiral Nelson Admiral Nelson is offline
Registered User
 
Join Date: Jun 2009
Posts: 518
Remarkable progress on Campus station in past few months. May 20.

     
     
  #4537  
Old Posted May 24, 2017, 3:40 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,518
Countdown to Confederation Line: Contractor to turn over $2.1B LRT line in one year

Matthew Pearson, Ottawa Citizen
Published on: May 23, 2017 | Last Updated: May 23, 2017 4:33 PM EDT




In exactly one year — May 24, 2018 — the city’s light-rail contractor, Rideau Transit Group, is expected to hand over the keys to Ottawa’s brand new, $2.1-billion Confederation LRT Line.

Nearly five years in the making, it will be the busiest LRT line in North America on its first day of service, say boastful politicians and senior city officials.

As the countdown to the Confederation Line’s launch begins, there are outstanding questions about the single largest infrastructure project in the city’s history.

When will the Confederation Line actually open?

There is no precise date. It will be sometime after May 24, 2018, the day the city officially takes ownership of it.

As Steve Cripps, director of O-Train Construction wrote in a memo this month: “The city does not expect to receive the trains one day and fill them with passengers the next.”

Once in the city’s possession, there will be testing of the LRT line’s various elements: the vehicles, power supply and distribution, the tracks and switches, the train communication, the control and radio systems, the tunnel ventilation, the fare gates, as well as the elevators, escalators and the fire alarms at all 13 stations.

Meanwhile, transitioning from a public transit network served predominantly by buses to a system comprised of two rail lines and buses requires “meticulous planning,” Cripps wrote. That job falls to OC Transpo, which has already launched a Ready for Rail PR campaign to help riders get the information they need to transition to a new transit routine that, for many, will involve transferring from bus to rail (or vice versa) to complete the trip.

The city expects to announce by the end of 2017 the first day passengers will be able to ride the Confederation Line.

Is the project behind schedule?

Yes and no.

“On any given day, some parts of the project are ahead of schedule, some are on time and some are behind,” Cripps wrote.

But after last June’s sinkhole on Rideau Street threw a wrench into the works, RTG developed a modified construction schedule and has confirmed to the city that it will meet the May 2018 deadline. If that changes, RTG must tell Cripps’ office and he’ll have the unenviable task of advising council.

If the contractor misses the deadline, the agreement imposes “significant financial consequences,” including the deferral of a $202-million payment and a reduction in the 30-year maintenance contract.

What’s been the fallout of the sinkhole?

A report into the cause of the sinkhole, released in April, confirmed that LRT tunnelling work under Rideau Street disturbed the soft soil.

The city has received 32 claims for compensation from property owners and businesses affected by the sinkhole. The city, meanwhile, claimed $1.4 million for emergency remediation work, plus another $780,000 for other costs, such as legal and consultant fees.

It was all sent to the LRT project’s insurance company to sort out. The insurer hadn’t made a decision on the claims as of Friday, the city said.

Then last week, another wrinkle: The company that owns The Westin Ottawa Hotel filed a $100,000 lawsuit that names both the city and RTG. The suit claims several banquets and events had to be cancelled and that the hotel racked up “significant out-of-pocket expenses” to compensate staff and customers because of the inconveniences. The allegations have not been tested in court.

How safe is the tunnel and other Confederation Line construction sites?

The toppling of a crane last month near the LRT tunnel’s entrance on the University of Ottawa campus prompted the question.

No one was injured, but workers on scene were overheard expressing concerns for their safety. “After this, you can be assured there’s a few more of those workers that are reluctant to go into the tunnel for fear they could be injured,” said Sean McKenny, president of the Ottawa and District Labour Council, on April 26.

Ontario’s Ministry of Labour has issued about 150 orders, ranging from site housekeeping to washroom facilities to improved lighting, which RTG says it has addressed. It also notes its accident rate is lower than the provincial average for heavy civil construction.

The crane incident and a May 2 gas main break on Queen Street are both under review.

John Manconi, general manager of transportation services, has denied suggestions RTG might be pressuring workers to rush in order to meet that deadline. “We are not going to compromise safety to meet a deadline,” he said last month.

What will Albert, Slater and the Mackenzie King Bridge look like without all the buses?

The city just announced a street planning and design study intended to provide options for reallocating the street space made available by removing the dedicated bus lanes, with an emphasis on cycling and pedestrian use.

The long-term plan is to make Albert and Slater “complete streets”, but the city also wants to implement some interim measures until the roads are reconstructed because that work is many years away.

Those measures could include wider sidewalks, enhanced crosswalks, streetscape improvements and some kind of new cycling infrastructure (though nothing specific is mentioned in the May 15 memo from Manconi).

The study will develop functional road designs, preliminary cost estimates and a plan for implementation along Albert and Slater streets between Bay Street and the Mackenzie King Bridge and for the Mackenzie King Bridge to Waller Street, as well as for the full reconstruction of Albert and Slater streets between Bay and Empress Avenue.

Recommendations for interim measures will be implemented after the Confederation Line opens over subsequent years until 2020, subject to funding, the memo said.

Speaking of downtown streets, what’s happening with Gatineau STO buses?

Talks between politicians and transit planners from both sides of the river have been underway for almost two years, and the plan they’ve hammered out, including details about the presence and volume of STO buses on downtown Ottawa streets, should be made public before summer.

“We’re working on an agreement that will be fair to both sides, and we hope to have that announced in the next couple of months,” Ottawa Mayor Jim Watson said in early March.

The announcement hasn’t happened yet, but it was likely delayed by flooding on both sides of the river that has preoccupied Watson and Gatineau Mayor Maxime Pedneaud-Jobin.

Will all the downtown road closures and construction be done by Canada Day, the marquee event this year’s sesquicentennial celebrations?

Sort of.

The city’s agreement with RTG stipulated that streets between the east tunnel portal at the University of Ottawa and the west tunnel portal near LeBreton Flats be restored to pre-construction configuration before Canada Day.

These requirements were reconsidered following the sinkhole; and RTG bumped up its crews, equipment and shifts to stay on schedule. But alas, some surface work will continue “beyond July 2017,” the Manconi memo said.

Work on Queen Street between Bank and O’Connor streets will continue through the summer (the section is actually closed to motorists and cyclists until mid-June)

RTG will, however, take a break from construction activities on Rideau Street on Canada that could hamper either public mobility or enjoyment of the party. And enhanced street cleaning on both Rideau and Queen is intended to make the construction zones a more welcoming environment for all those revellers.

[email protected]
twitter.com/mpearson78

http://ottawacitizen.com/news/local-news...r-to-turn-over-2-1b-lrt-line-in-one-year
     
     
  #4538  
Old Posted May 24, 2017, 5:18 AM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,673
Tremblay station seems so massive for its use since I only ever noticed a handful of people getting off the Transitway here before. I was thinking this station would actually make a good transfer point for exurban buses to Casselman and "Em-var-moges"





Cyrville gets more glass. I like this station for its simplicity, I think it has the cleanest lines of all the 13



     
     
  #4539  
Old Posted May 24, 2017, 6:14 AM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,796
It's too bad the city cant force all bus operators to move to a bus terminal at Tremblay. So much potential.
     
     
  #4540  
Old Posted May 24, 2017, 7:47 PM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,822
Quote:
Originally Posted by Kitchissippi View Post
Tremblay station seems so massive for its use since I only ever noticed a handful of people getting off the Transitway here before. I was thinking this station would actually make a good transfer point for exurban buses to Casselman and "Em-var-moges"
The St Laurent bus station will be way oversized for a half dozen or so local routes. It would be a good place for these exurban services (and wouldn't require new construction).
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 12:30 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.