Construction Update
Week of May 1
Guideway activities continue to progress along the alignment this week, with crews pulling sections of rail at Bayview Station and in the running tunnel moving west to Lyon Station. At the integrated station entrances in the downtown core, structural steel is installed for the head house at Lyon Station west entrance and walls have reached ground level at the Rideau Station east entrance.
Work on stairs and structural steel installation at Pimisi Station
West Stations
Tunney’s Pasture Station
Work is ongoing at the station, including construction on the retaining wall on the south side of the station, in addition to the north side elevator walls, installation of beams for the station foundation and concrete work for the walls in the concourse area.
Bayview Station
Station construction progresses this week and includes backfilling, mechanical and electrical work, installation of steel columns, waterproofing of pits, and work on grade beams.
Pimisi Station
Progress continues to be visible with ongoing steel installation, slab on grade concrete pours and work on stairs. Crews install rebar for the concourse slab on the west side of the station. Backfilling and conduit work also occur.
Architectural work is ongoing in Lyon Station cavern
Central Stations
Lyon Station cavern
Architectural work is ongoing in the cavern, including door frames, installation of blocks and elevator guard rails, tiling and painting on stairs. Crews also drill dowels in the sub platform area.
Lyon Station west entrance
Integrated entrance construction advances with the installation of steel for the roof, delivery and installation of escalators, and final reinstatement of utilities at the beginning of the week. Formwork and slab pours are ongoing at the east vent shaft.
Lyon Station east entrance
This week, crews continue installing masonry at the retail concourse level and structural steel at the ground level. On the mezzanine, rebar and formwork installation occur as part of concrete activities, and work on elevators and escalators and rough-ins are ongoing. At the HVAC shaft, sections of concrete work are completed and curing takes place this week.
Structural steel installation at Lyon Station west entrance
Parliament Station cavern
The station cavern continues to take shape with crews installing rebar and formwork on the pillars in preparation for the next section of concrete pours. Architectural work also occurs this week and includes installation of the structural steel columns and work on stairs.
Parliament Station west entrance
Integrated entrance work is ongoing and includes hoe-ramming, rock removals, rock support and rock bolt installation. Crews also complete saw cutting for a breakthrough to the HVAC shaft.
Parliament Station east entrance
Crews continue waterproofing, installing rebar, forming walls and pouring concrete for walls and slabs at the concourse level. Dowels are installed on the lower pits.
Rideau Station cavern
Work on the invert occurs this week, and includes waterproofing and concrete pours in sequence. Dowels are installed for the station columns and footings and rebar for the arch final lining. Shotcrete final lining activities also continue this week, in addition to construction of the station walls.
Rideau Station west entrance
Mining of the bench for the future entrance escalator is ongoing.
Rideau Station east entrance
Progress of concrete work continues to be visible with crews pouring walls at ground level this week. Rebar and falsework are installed on the ground level slabs, and concrete work occurs for the escalator pits. At the HVAC shaft, shoring and backfilling are completed and crews also install beams this week.
Structural steel installation and work on stairs at uOttawa Station
East Portal
Construction of the ramp advances with ongoing rebar installation, formwork and concrete pours for walls and slabs. Crews also continue line drilling and excavation on the north side of the ramp, and install tiebacks, rock bolts and whaler beams.
uOttawa Station
Station construction advances with mechanical and electrical work, concrete pours for the service trenches, installation of structural steel and work on stairs.
Work on the ancillary building and progress of structural steel at Hurdman Station
East Stations
Lees Station
Crews ramp up construction at the ancillary building, including concrete pours, masonry and mechanical rough-ins. Rebar is also installed at the concourse area this week, followed by concrete pours in the next weeks.
Hurdman Station
Crews continue installing structural steel, frame stairs and begin working on the roof of the stairs. Wiring, concrete activities and station signage work are also ongoing.
Glazing is ongoing at Cyrville Station
Tremblay Station
Station construction continues to progress. This week, crews begin installing porcelain and composite panels, work on elevators and rough-ins and continue initial landscaping work.
St-Laurent Station
This week, duct work, ceiling panel, station signage installation and finishing work in the communications room are also ongoing. Masonry is completed at the plenum, and work on the head house HVAC shaft occurs.
Glazing is ongoing at Blair Station
Cyrville Station
Crews continue glazing the next section of elevators this week, work on station signage and install porcelain panels on sections of wall. Final heat tracing and installation of precast concrete on stairs also take place.
Blair Station
Construction continues at the station and includes final soffit installation, glazing at the lower concourse area and the installation of aluminium doors.
Installing dowels, poles and ready to pull rail west of Bayview Station
Guideway and Trackwork
Concrete pours for plinths are ongoing east of Tunney’s Pasture Station and rail is pulled in sections at Bayview Station. In the tunnel, track teams continue pulling rail and installing dowels in sections moving west to Lyon Station. Final concrete lining pours are also ongoing east of Parliament Station to west of Rideau Station. Ballast installation is ongoing at Lees Station, and rail crews mobilize to begin pulling rail. Crews also continue installing ballast at Lees Station, which will be followed by concrete tie installation. Rail is being pulled on the Rideau River Bridge and tamping is ongoing at Hurdman Station. Systems teams are also installing Overhead Catenary System wires near St-Laurent Station.
Installing Overhead Catenary System wires near St-Laurent Station
Upcoming Construction Activities
In the coming weeks, the following construction activities are scheduled to occur:
- Hoe ramming as part of work on the western section of the guideway.
- Blasting begins at the Lyon west vent shaft.
- Ongoing overnight work at the Rideau Station west and east entrances, and at the East Portal.
- Ongoing structural steel installation at uOttawa Station requiring overnight lane restrictions.
- Final work on the pedestrian tunnel at uOttawa Station.
- Fencing installation on guideway just west of Tremblay Station.
- Hydro connection work to Hurdman Station requiring lane restriction on Riverside Drive.
- Manhole work as part of guideway activities at intersection of Riverside Drive and Tremblay Road, requiring lane restrictions.
- Systems installation along the guideway, including Overhead Catenary System poles and wires.
http://www.ligneconfederationline.ca/news/construction-update-122/