The situation south of Carleton is also quite bad. Many of the bridges and overpasses only support a single track presently and will need to be replaced. I mean, even adjacent to Greenboro, a bridge over the Transitway does not support double tracking. The bridge at Carleton University will likely need a temporary replacement or a total shutdown. You would not want a permanent realignment to build a new bridge adjacent to the current bridge as this may compromise long-term train speeds.
|
There are issues in both directions. North of Carleton is obvious, but south of Carleton there are not only issues at the river and the Transitway at Greenboro, but probably most importantly there's the VIA crossing. Grade separating that diamond would not be easy, as VIA line can't be lowered as it must clear Heron Road. Lowering the Trillium Line would interfere with the nearby Transitway and Sawmill Creek, so if the Transitway were then raised to cross over the Trillium Line, 3 bridges would need replacement. Raising the Trillium line would cause issues with the Airport Parkway overpass. Raising the VIA line and possibly slightly lowering the Trillium line may work, but would likely require replacement of the VIA bridges over the Airport Parkway, Heron Road and Heron Station with taller bridges. If any work was to take place in the area, I would rather see it take place in conjunction with a complete review and rethink of the Transitway Corridor and Heron to Airport Parkway ramps. Those ramps take up a vast amount of valuable real estate, and the Transitway swerves under the VIA line between Billings Bridge and Heron. With the Baseline BRT ending here and the talk of commuter rail in the future, there is an opportunity to rethink the entire area and take all options into account for a future transit hub. There is also the possibility of eliminating the bus Transitway from Heron to Greenboro or even South Keys. This would merge the existing South East Transitway into the Baseline BRT corridor. If the area were cleaned up a bit there is quite a bit of developable land on both sides of Heron Road that would be extremely well-served by transit.
Quote:
Originally Posted by 1overcosc
In Toronto the UPX was built through massive upgrades of a rail line including adding extra tracks, many bridge replacements including new grade separations and replacing at-grade sections with trenched sections... all of this was done while keeping the rails open for GO service, however it required the elimination of midday service during the construction period. It would definitely be possible to retain peak period service on the Trillium Line during a full-scale double tracking project, but possibly not much else.
|
I think the biggest issue with that plan is that there is no real peak period for the Trillium Line. The trains around 8:15 tend to be the busiest of the day, which lines up with the start of 8:30 classes at Carleton and the regular workday elsewhere, but beyond that there is a very steady flow throughout the day. Classes ending at 2:30 or 4 make the trains busy again, but spread the afternoon peak out quite a bit.
I think there is a lot of focus on a complete double tracking of the Trillium line, but we are missing an important intermediate step. If we started double tracking as much as possible, and left the most difficult sections for later, it would be possible to run a very effective and frequent service, much better than today's. Rather than having mostly single track with some passing points, there would be mostly double track with some pinch points.
Bridges at Heron Road and Walkley Road are around 50 years old, and are both simple concrete structures between retaining walls. These will likely need refurbishment or replacement in the next 5-15 or so years, so opportunity exists to make them wide enough to accommodate stations at a lower cost. The Riverside Drive bridge is also getting older, and I do not believe it would accommodate double tracking as it currently stands. If it were also replaced, double track would then exist from just north of Greenboro to the north end of the current Brookfield signal siding, and from north of the Ellwood Diamond to the Rideau River bridge, with both Confederation Heights and Walkley stations being on double tracked sections.
The Trillium Line currently functions well as a largely symmetrical system around Carleton, and this could be maintained. Unless the siding at Carleton needs to lengthened for longer platforms, it doesn't make much sense to change the track in this area. If longer platforms became necessary, then it may be prudent to double track as much from the bridge to the tunnel as is possible while work is already being done, although the Campus Avenue bridge is of the same design as the Riverside Drive bridge and is unlikely to be wide enough for two tracks. North of the tunnel, work would be required to widen the cut from the tunnel entrance to Carling Station, including Prince of Wales bridge replacement. This is likely to be the toughest part of this idea, and would likely require a summer closure of the tracks north of Carleton.
From Hickory st. to the 417, the track would remain single, mirroring the single track over the Ellwood Diamond and Sawmill Creek in the south. Gladstone stations is already planned to be double tracked, with widening of the cut required, mirroring Walkley. Although I propose leaving a single track section north of Greenboro, I would not suggest mirroring this in the north, as the distance from Gladstone to Bayview is too short, and Bayview can easily be a double tracked terminus. It would be necessary to widen the gap in the Somerset to allow this, as only one track can currently fit.
This system would allow a much higher frequency to be obtained, potentially every 5 minutes. Combined with longer trains, I see no reason why it would not have the capacity to accommodate growth well into the future, without the cost of dealing with the Dow's Lake Tunnel, Sawmill Creek, Rideau River, or most of the rock cut. These issues could then be tackled one by one or two at a time as timing and finances permit.