Hamilton’s stadium is “substantially complete”
|
Thought I'd post the whole article and accompanying photo for historical posterity when the link to the article no longer works. I think it turned out pretty well for the money.
Hamilton’s stadium is “substantially complete”
Matthew Van Dongen Hamilton Spectator May 8/2015

John Rennison/Hamilton Spectator
Hamilton can finally take over its $145 million stadium next week – and now the race is on to get it event-ready.
An independent certifier for Infrastructure Ontario alerted the city Friday evening that the long-delayed construction project has achieved "substantial completion."
That means the city finally gets the keys – 10 months later than expected – and beleaguered contractor Ontario Sports Solutions gets $89 million of withheld payments.
"There will still be minor work needed on the stadium, but it will not impact Pan Am / Parapan Am Games readiness or the stadium's ability to shine on the international stage," said IO vice-president John McKendrick in an e-mail. "Sufficient performance security has been withheld from the total payment to Ontario Sports Solutions to ensure any outstanding work is completed within the project's original budget."
An e-mail to councillors Friday said staff will reviews the terms of the notice from the provincial oversight agency and update council on the next steps.
But time is running out to ready the stadium for a planned public open house May 21 – not to mention an international soccer match planned between the women's teams from Canada and England for May 29.
Public works head Gerry Davis earlier warned council it could take weeks to train staff, test-drive stadium equipment and ready the building for public use.