Quote:
Originally Posted by Olden Retreiver View Post
TBM Alice was launched at the Port Moody portal in March 2014, and the tunnel was supposed to take about a year to complete.

http://tranbc.ca/2014/03/26/the-evergree...ke-it-a-boring-job/#sthash.l6cwW7Xk.dpbs
A year probably including finishing work. But the breakthrough at the South tunnel portal was supposed to happen last December.
     
     
  #8282  
Old Posted May 9, 2015, 3:46 AM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,711
Paging queetz to come in and defend EGRT...
     
     
  #8283  
Old Posted May 9, 2015, 4:10 AM
finalcoolman finalcoolman is offline
Registered User
 
Join Date: Nov 2004
Posts: 262
The proof thanks to archive.org.

Scroll down to: "Tunnel boring machine (TBM) breakthrough at south portal" near the very bottom.

The tunnel was supposed to be 'done' as in the TBM was finished digging last December. The "TBM removal and transition tunnel finishing work" was made it a 'year'. Ofcourse that has been long taken down from the website.

https://web.archive.org/web/20140816152736/http://www.evergreenline.gov.bc.ca/upcoming/Burnaby.htm
     
     
  #8284  
Old Posted May 9, 2015, 4:43 AM
Metro-One's Avatar
Metro-One Metro-One is offline
Registered User
 
Join Date: Sep 2008
Location: Japan
Posts: 18,025
I am not surprised by the delays, that area is an extremely difficult area geologically, a hodgepodge of glacial till.
__________________
Bridging the Gap
Check out my Flickr: https://www.flickr.com/photos/30634635@N03/with/29495547810/ and Youtube channel https://www.youtube.com/channel/UCV0_0h9qKlhxXFxuAey_q6Q
     
     
  #8285  
Old Posted May 9, 2015, 10:26 AM
Olden Retreiver Olden Retreiver is offline
Registered User
 
Join Date: Nov 2013
Posts: 263
Quote:
Originally Posted by Metro-One View Post
I am not surprised by the delays, that area is an extremely difficult area geologically, a hodgepodge of glacial till.
And EGRT did not know this?
     
     
  #8286  
Old Posted May 9, 2015, 12:20 PM
Metro-One's Avatar
Metro-One Metro-One is offline
Registered User
 
Join Date: Sep 2008
Location: Japan
Posts: 18,025
Quote:
Originally Posted by Olden Retreiver View Post
And EGRT did not know this?
Yes, they did, but what glacial till entails is having large variation in geology over very short distances. They literally would have had to drill sample holes every 5 meters or so along the entire distance to know exactly (almost exactly) what they would be dealing with. So anyone with a basic understanding of geology is not surprised to see delays along this route.
__________________
Bridging the Gap
Check out my Flickr: https://www.flickr.com/photos/30634635@N03/with/29495547810/ and Youtube channel https://www.youtube.com/channel/UCV0_0h9qKlhxXFxuAey_q6Q
     
     
  #8287  
Old Posted May 9, 2015, 1:53 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,711
Quote:
Originally Posted by Metro-One View Post
Yes, they did, but what glacial till entails is having large variation in geology over very short distances. They literally would have had to drill sample holes every 5 meters or so along the entire distance to know exactly (almost exactly) what they would be dealing with. So anyone with a basic understanding of geology is not surprised to see delays along this route.
So they should have built more contingency into the plan?

Tunnel boring seems to be one of the last mysteries of this planet. Nobody can predict it properly.
     
     
  #8288  
Old Posted May 9, 2015, 2:41 PM
Kisai Kisai is offline
Registered User
 
Join Date: Jun 2014
Location: Burnaby
Posts: 1,154
Quote:
Originally Posted by WarrenC12 View Post
So they should have built more contingency into the plan?

Tunnel boring seems to be one of the last mysteries of this planet. Nobody can predict it properly.
Nah. Weather and Earthquakes is still not long-term predictable. We can go "Earthquake, big one, next 300-500 years", but that's not going to make everyone move out of Richmond for the next two centuries "just in case"

With the Evergreen Line TBM, from what's been said before, they have to change the cutting blades with changing soil conditions, and you can't really plan enough in advance. This is why we didn't have full TBM on the Canada Line, because it would have resulted in a unpredictable schedule.

On the other hand, cut-and-covering likely wasn't a good option for this alignment because it would have left the road inaccessible since there's no other road for people to go down to get to their homes.

Incidentally... Google Maps now has the Evergreen line's tracks on their 2D vector maps, but not the stations.
     
     
  #8289  
Old Posted May 9, 2015, 6:46 PM
SOSS SOSS is offline
Registered User
 
Join Date: Jan 2014
Posts: 661
Cut and cover was also ruled out because of depth and alignment under homes. It does t just run under clarke.
     
     
  #8290  
Old Posted May 9, 2015, 6:51 PM
Olden Retreiver Olden Retreiver is offline
Registered User
 
Join Date: Nov 2013
Posts: 263
To imply that no one at EGRT has a "basic understanding of geology" is the harshest indictment of the consortium I've read on this forum. Ever.
__________________
Confidence is that uplifting feeling you have immediately before you fully comprehend the situation.
     
     
  #8291  
Old Posted May 9, 2015, 10:38 PM
queetz@home's Avatar
queetz@home queetz@home is offline
Go Rotem! Die Bombardier!
 
Join Date: Jul 2001
Location: Ortigas
Posts: 3,679
Quote:
Originally Posted by Olden Retreiver View Post
To imply that no one at EGRT has a "basic understanding of geology" is the harshest indictment of the consortium I've read on this forum. Ever.
I am usually at odds with Olden Retriever but he is absolutely right on this. Anybody who thinks no one in EGRT knew about the geology is the most self-concieted armchair analyst. EGRT knew about the risks but ultimately, the riskier the road, the greater the profit. No doubt their contracted price is based on the amount of risk, and I'm sure they have enough contengencies to ensure that they will come out of this project profitable with zero collateral damage (far better than say, Canada Line with one death and a bunch of businesses screwed).

Plus I don't believe anybody here that say "I am not surprised by these delays" or "I knew the geology would make it hard" and so on. This is simply a "Nostradamus effect" of claiming to have predicted something that has already happened. This thread has been going on for years, and if you really made the call that there will be delays on the tunneling because of this or that factor, then I suggest you link the previous, uneditted post saying so. Otherwise, its all BS.
     
     
  #8292  
Old Posted May 10, 2015, 12:16 AM
Metro-One's Avatar
Metro-One Metro-One is offline
Registered User
 
Join Date: Sep 2008
Location: Japan
Posts: 18,025


I love it when people completely misinterpret a comment.

I wasn't saying that EGRT had no geological understanding, I was saying that those bitching about the delays EGRT is having have no geological understanding.
Essentially, those members on this forum.
Hence someone who does have a basic understanding is not surprised to see such delays, get it?

Again, you would need to drill sample holes every few meters to know what you were dealing with and to be able to give a more precise timeline, which of course is nearly impossible to do. (and a waste of time itself).

Therefore, they could only add so much contingency time to the schedule.
__________________
Bridging the Gap
Check out my Flickr: https://www.flickr.com/photos/30634635@N03/with/29495547810/ and Youtube channel https://www.youtube.com/channel/UCV0_0h9qKlhxXFxuAey_q6Q
     
     
  #8293  
Old Posted May 11, 2015, 12:27 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,782
And that's why the Province is smart enough to allocate that risk to EGRT in the Contract!
     
     
  #8294  
Old Posted May 11, 2015, 11:13 AM
Olden Retreiver Olden Retreiver is offline
Registered User
 
Join Date: Nov 2013
Posts: 263
Quote:
Originally Posted by officedweller View Post
And that's why the Province is smart enough to allocate that risk to EGRT in the Contract!
Don't be too sure about that- "geological risk" usually remains with the client in jobs such as this, despite what one might think from a face-value reading of the contract summary.

I expect queetz is exactly right in his May 9th post, and the tunnelling consortium wil come out of this smelling (relatively) of roses, and with their wallets fully intact.
__________________
Confidence is that uplifting feeling you have immediately before you fully comprehend the situation.
     
     
  #8295  
Old Posted May 11, 2015, 3:45 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,711
Any contract experts know the milestone dates and penalties for missing?
     
     
  #8296  
Old Posted May 11, 2015, 10:20 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,782
In this case the contractor bears the tunnelling risk:

Quote:
Originally Posted by officedweller View Post
WRT the Evergreen Line, it proceeded as a Design Build partially Finance contract.

Here's the Partnerships BC analysis of the contract (click "Project Report"):

http://www.partnershipsbc.ca/projects/pr...on/evergreen-line-rapid-transit-project/

A redacted copy of the DBF Contract and schedules is at that link under "Procurement Documents".

Here are the excerpts from that report which states that the private contractor accepted tunnelling risk
and will pay a financial penalty for each day that substantial completion is delayed past July 29, 2016.

The recent unexpected problems with soil conditions while tunnelling - which will delay the project
- are the responsibility of the private contractor consortium.

Note that the private contractor is building a single bore tunnel - which is an "innovation" versus
the Province's reference plan which was for a twin-bore project. This was said to speed up the schedule.
So in this case, had the Province proceeded with its own plan, the soil condition delays may have been encountered twice,
with a twin bore, rather than once with a single bore.

The current projected opening date is in Fall 2016
(Construction started in February 2013, with property acquisition and utility relocation undertaken by the Province before that.)
The contract requires TransLink to open within 1 month after substantial completion
- so backtracking 1 month to substantial completion, the contractor's penalties are for at least a month.

Here's the Press Release about the delayed opening and that the Contractor is responsible for the cost of the delay:

http://www.evergreenline.gov.bc.ca/documents/NewsReleases/2015TRAN0016-000182.pdf




http://www.partnershipsbc.ca/files-4/documents/PBCEvergreen.pdf


http://www.partnershipsbc.ca/files-4/documents/PBCEvergreen.pdf
]
     
     
  #8297  
Old Posted May 11, 2015, 10:30 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,711
So there is a milestone for completion and operation, delaying some payments. But that's typical of just about any contract. Many are 25%/50%/25% with 25% on contract signing, 50% on the beginning of usage, and the remaining 25% at some defined number of days after usage begin.

There are no hard completion dates that trigger penalties from what I read there.

Payments reduced if performance is not maintained... that's typical. Although it might be a finger pointing exercise if certain issues crop up around Lougheed that impact the Evergreen and Millennium lines. W
     
     
  #8298  
Old Posted May 11, 2015, 10:41 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,782
Top page - 2nd bullet, right column.
- Substantial Completion by July 29, 2016, or penalties will accrue for each day of delay
     
     
  #8299  
Old Posted May 12, 2015, 4:58 AM
red-paladin red-paladin is offline
Vancouver Moderator
 
Join Date: Sep 2008
Location: Burnaby
Posts: 3,626
Thanks for clearing it up officedweller.
     
     
  #8300  
Old Posted May 12, 2015, 9:43 AM
xd_1771's Avatar
xd_1771 xd_1771 is offline
(daka_x)
 
Join Date: Aug 2010
Location: Metro Vancouver, Canada
Posts: 1,740
From the new leaked report on SkyTrain, discussion on the main Metro Van Transit thread. Pulled this from the report:

Quote:
Extremely important: our new Mark IIIs arrive end-year. Another part of the report says they will enter service within this year, ahead of the opening of the Evergreen Line.
Quote:
Evergreen Extension construction will continue and testing and commissioning of the system will commence in 2015. The first MKlll trains are scheduled to arrive in the latter half of 2015
Quote:
Other 2015 priorities to enhance customer service include:
....
....introduce he first MKlll trains into service once testing and commissioning is complete
Gonna bring this over as well: I also found a picture of the mockup Mark III vehicle in a Bombardier report:
Quote:
Originally Posted by xd_1771 View Post
FIRST LOOK: Bombardier MARK III SKYTRAIN PROTOTYPE (Innovia Metro 300) was under construction at Bombardier's Kingston testing facility as of 2014.
Say hello to the next generation


Screenshot taken from Bombardier document http://www.bombardier.com/content/dam/We...Testing_Services_Brochure_2014_05_V1.pdf
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 10:18 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.