Construction Update
Week of December 7
Asphalt paving occurs on the Preston Street detour
The Preston Street detour will allow transit, commuters, pedestrians and cyclists to use Preston Street during the Booth Street closure and construction of Pimisi Station.
Construction continues along the Preston Street detour, and includes asphalt paving and installation of street light poles. Shelter installation is ongoing this week by OC Transpo.
Rebar and support system installation in the Lyon Station cavern
Jawbreaker
Cavern reinforcement is ongoing with rockbolt, rebar installation, shotcrete and support system.
Mining in drifts is anticipated to continue until end of December.
Ongoing formwork in the Parliament Station cavern
Chewrocka
Construction of a lower level support system is ongoing, including formwork, storm sewer and conduit installation.
Crocodile Rouge
Rideau Station cavern excavation has begun.
Tunnel reinforcement is ongoing with shotcrete and rockbolt installation.
Scotiabank building demolition on Rideau Street
Internal abatement of the existing
Scotiabank building continues in advance of building demolition scheduled to being in January 2015.
Belfast Yard administration and maintenance building construction continues
Masonry work, cladding and panel installation for the
Belfast Yard building envelop and roofing are ongoing through winter.
Construction of the internal components continue during the winter months.
Verona temporary support system at the Belfast Yard connector
Works on the Belfast Yard connector are ongoing with the removal of the steel bridge under the VIA Rail tracks scheduled for end of week.
Caisson drilling north of the existing Hurdman Station
Elevated guideway work for the future
Hurdman Station is ongoing with caisson drilling north of the existing Hurdman Station.
St. Laurent Boulevard off-ramp paving and curb construction
Drilling median foundations, installing electrical and light poles advances from
Cyrville Road to Nicholas Street.
Paving occurs at St. Laurent and Lemieux streets, and Vanier Parkway.
Sewer crews continue to work in the median lane throughout winter.
Ongoing reconstruction of median span at Hurdman Bridge
Reconstruction of the median span at the
Hurdman Bridge is ongoing, with panels on the abutments and girder installation.
The east and west multiuse pathway closures continue.
Demolition of removed Vanier Parkway overpass
Vanier Parkway Overpass
Demolition of the old Vanier Parkway Overpass continues at the staging area while final works occur on the overpass.
Ongoing ceiling system works on the Coventry Pedestrian Footbridge
Construction of the Coventry Pedestrian Footbridge ramps
Electrical and plumbing works are ongoing at the
Coventry Pedestrian Footbridge and concrete pours continue for the next weeks on the stairs and landings on the north and south sides.
Albert at Preston looking west
Complete sidewalk reinstatements on
Albert Street between City Centre Avenue and Preston.