  #1421  
Old Posted Nov 30, 2014, 1:41 PM
Philly-Drew's Avatar
Philly-Drew Philly-Drew is offline
Φιλαδέλφεια
 
Join Date: Feb 2005
Location: NoLibs
Posts: 1,395
Summers, can you add this link to the first post of the thread? That would make it nice and easy to find from any device.

Thanks In Advance!
__________________
"Imagine all the people, living life in peace." :Lennon
Reply With Quote
     
     
  #1422  
Old Posted Nov 30, 2014, 4:08 PM
Philly Fan Philly Fan is offline
Registered User
 
Join Date: Feb 2013
Posts: 2,524
Quote:
Originally Posted by Philly-Drew View Post
Summers, can you add this link to the first post of the thread? That would make it nice and easy to find from any device.

Thanks In Advance!
Great idea!
Reply With Quote
     
     
  #1423  
Old Posted Nov 30, 2014, 6:12 PM
Plokoon11 Plokoon11 is offline
Registered User
 
Join Date: Jun 2007
Posts: 1,698
Building Philly believes the concrete mat is ready to be poured. He also has pictures!
Reply With Quote
     
     
  #1424  
Old Posted Nov 30, 2014, 6:17 PM
Jawnadelphia's Avatar
Jawnadelphia Jawnadelphia is offline
Registered User
 
Join Date: May 2014
Location: Wilmington, Delaware
Posts: 2,906
From earlier today..

[IMG]http://[url=https://flic.kr/p/pXQRg5][/url]Untitled by TallCoolOne2014, on Flickr[/IMG]

[IMG]http://[url=https://flic.kr/p/piqeKW][/url]Untitled by TallCoolOne2014, on Flickr[/IMG]

[IMG]http://[url=https://flic.kr/p/pXYQ2x][/url]Untitled by TallCoolOne2014, on Flickr[/IMG]

[IMG]http://[url=https://flic.kr/p/qfm58A][/url]Untitled by TallCoolOne2014, on Flickr[/IMG]
Reply With Quote
     
     
  #1425  
Old Posted Nov 30, 2014, 9:17 PM
Lincolndrive's Avatar
Lincolndrive Lincolndrive is offline
Realtor
 
Join Date: Mar 2006
Location: Philadelphia
Posts: 619
To be fair, I have no idea when the concrete mat will actually be poured...there is still more work to come prior to the pour but I can't imagine it will be that long from now, can you? In my completely unprofessional and very amateur opinion, we are less than 2 weeks out. Time will tell.

One thing is for sure, it will be a lot of concrete.

Quote:
Originally Posted by Plokoon11 View Post
Building Philly believes the concrete mat is ready to be poured. He also has pictures!
Reply With Quote
     
     
  #1426  
Old Posted Dec 1, 2014, 6:20 PM
summersm343's Avatar
summersm343 summersm343 is offline
Moderator
 
Join Date: Oct 2011
Location: Philadelphia
Posts: 18,469
^^

Update from Lincolndrive over at BuildingPhilly



https://www.facebook.com/BuildingPhilly
Reply With Quote
     
     
  #1427  
Old Posted Dec 3, 2014, 8:36 PM
RWSMADCONC RWSMADCONC is offline
Registered User
 
Join Date: Feb 2013
Posts: 54
Quote:
Originally Posted by Lincolndrive View Post
To be fair, I have no idea when the concrete mat will actually be poured...there is still more work to come prior to the pour but I can't imagine it will be that long from now, can you? In my completely unprofessional and very amateur opinion, we are less than 2 weeks out. Time will tell.

One thing is for sure, it will be a lot of concrete.
Tentative schedule is next Saturday (12/13) 1AM
Reply With Quote
     
     
  #1428  
Old Posted Dec 4, 2014, 12:09 AM
Plokoon11 Plokoon11 is offline
Registered User
 
Join Date: Jun 2007
Posts: 1,698
^ Thank you for the information!
Reply With Quote
     
     
  #1429  
Old Posted Dec 4, 2014, 2:15 PM
boxbot's Avatar
boxbot boxbot is offline
Registered User
 
Join Date: Feb 2014
Location: Delco., Pa.
Posts: 842
Quote:
Originally Posted by RWSMADCONC View Post
Tentative schedule is next Saturday (12/13) 1AM
You guys really are working around the clock. Excellent!
Reply With Quote
     
     
  #1430  
Old Posted Dec 4, 2014, 2:35 PM
Philly Fan Philly Fan is offline
Registered User
 
Join Date: Feb 2013
Posts: 2,524
Quote:
Originally Posted by boxbot View Post
You guys really are working around the clock. Excellent!
I assume it's related to the volume of concrete involved. For a job this size, they probably have to essentially devote the entire output of the concrete plant to this job exclusively while this pour is occurring, not to mention the number of concrete trucks on the road and in center city required for this pour. Makes sense to start it at 1AM on a Saturday.
Reply With Quote
     
     
  #1431  
Old Posted Dec 4, 2014, 2:47 PM
boxbot's Avatar
boxbot boxbot is offline
Registered User
 
Join Date: Feb 2014
Location: Delco., Pa.
Posts: 842
Quote:
Originally Posted by Philly Fan View Post
I assume it's related to the volume of concrete involved. For a job this size, they probably have to essentially devote the entire output of the concrete plant to this job exclusively while this pour is occurring, not to mention the number of concrete trucks on the road and in center city required for this pour. Makes sense to start it at 1AM on a Saturday.
I'm impressed they were able to source enough to start this pour and the FMC tower's at nearly the same time.
Reply With Quote
     
     
  #1432  
Old Posted Dec 4, 2014, 3:10 PM
Philly Fan Philly Fan is offline
Registered User
 
Join Date: Feb 2013
Posts: 2,524
Quote:
Originally Posted by boxbot View Post
I'm impressed they were able to source enough to start this pour and the FMC tower's at nearly the same time.
Good point. When RWSMADCONC first posted about the FMC pour tomorrow night and the CITC pour next Friday night, I thought to myself that this must be one of the largest amounts--if not THE largest amount--of concrete ever poured in Philly at about the same time.
Reply With Quote
     
     
  #1433  
Old Posted Dec 4, 2014, 7:16 PM
kraggman's Avatar
kraggman kraggman is offline
Always Lookin' Up
 
Join Date: Jan 2007
Location: Right Coast
Posts: 477
This is gonna be one helluva concrete truck convoy. Hopefully someone gets pics.
Reply With Quote
     
     
  #1434  
Old Posted Dec 4, 2014, 10:14 PM
RWSMADCONC RWSMADCONC is offline
Registered User
 
Join Date: Feb 2013
Posts: 54
Quote:
Originally Posted by Philly Fan View Post
Good point. When RWSMADCONC first posted about the FMC pour tomorrow night and the CITC pour next Friday night, I thought to myself that this must be one of the largest amounts--if not THE largest amount--of concrete ever poured in Philly at about the same time.
The "new" Comcast will run 3978 CY neat, probably more like 4100 at the end of the day. The first Comcast was about 25% bigger, and took about 10 hours with 3 pumps way back on October 1, 2005. Expect pretty much the same deal here.
Reply With Quote
     
     
  #1435  
Old Posted Dec 4, 2014, 11:29 PM
Philly Fan Philly Fan is offline
Registered User
 
Join Date: Feb 2013
Posts: 2,524
Quote:
Originally Posted by RWSMADCONC View Post
The "new" Comcast will run 3978 CY neat, probably more like 4100 at the end of the day. The first Comcast was about 25% bigger, and took about 10 hours with 3 pumps way back on October 1, 2005. Expect pretty much the same deal here.
I didn't express it very well, but what I meant to say was that this CITC pour, combined with the pour tomorrow night at FMC, would probably be one of the largest--if not THE largest--amounts of concrete ever poured in Philly over a period of a week or so.

As always, though, thanks for those details. We're talking about 400-500 truckloads of concrete just for this one CITC pour.
Reply With Quote
     
     
  #1436  
Old Posted Dec 4, 2014, 11:45 PM
GarCastle GarCastle is offline
Registered User
 
Join Date: Feb 2006
Posts: 469
Quote:
Originally Posted by Philly Fan View Post
I didn't express it very well, but what I meant to say was that this CITC pour, combined with the pour tomorrow night at FMC, would probably be one of the largest--if not THE largest--amounts of concrete ever poured in Philly over a period of a week or so.

As always, though, thanks for those details. We're talking about 400-500 truckloads of concrete just for this one CITC pour.
I was curious what the Convention Center expansion involved. Obviously a thin pour but on a massive scale. Apparently it was 70,000 CY of concrete overall, no details on how much per "pour" though. It's probably out there on some site for any that want to dig. :^)

Cheers,
G.
__________________
"I don't need the city, it never cared for me." - Neuroticfish.
Reply With Quote
     
     
  #1437  
Old Posted Dec 6, 2014, 2:57 PM
summersm343's Avatar
summersm343 summersm343 is offline
Moderator
 
Join Date: Oct 2011
Location: Philadelphia
Posts: 18,469
Update from Lincolndrive at Building Philly



https://www.facebook.com/BuildingPhilly
Reply With Quote
     
     
  #1438  
Old Posted Dec 8, 2014, 1:29 AM
volguus zildrohar's Avatar
volguus zildrohar volguus zildrohar is offline
I Couldn't Tell Anyone
 
Join Date: Apr 2002
Location: The City Of Philadelphia
Posts: 15,933
According to the article in today's Inquirer the pour will be on 12/13. I remember the pour for Comcast Center back in '05 with those trucks going on into the night. I'll have to find some of my photos from back then. Philly Skyline has some as well.
__________________
je suis phillytrax sur FLICKR, y'all
Reply With Quote
     
     
  #1439  
Old Posted Dec 9, 2014, 3:43 PM
1487 1487 is offline
BANNED
 
Join Date: Jun 2014
Posts: 3,401
Quote:
Originally Posted by volguus zildrohar View Post
According to the article in today's Inquirer the pour will be on 12/13. I remember the pour for Comcast Center back in '05 with those trucks going on into the night. I'll have to find some of my photos from back then. Philly Skyline has some as well.
im surprised no one posted the link to that article, it was very informative. Lots of interesting illustrations about the design and structure of the building.
Reply With Quote
     
     
  #1440  
Old Posted Dec 9, 2014, 7:21 PM
kraggman's Avatar
kraggman kraggman is offline
Always Lookin' Up
 
Join Date: Jan 2007
Location: Right Coast
Posts: 477
Quote:
Originally Posted by 1487 View Post
im surprised no one posted the link to that article, it was very informative. Lots of interesting illustrations about the design and structure of the building.
Would like to see that too. On the Inquirer site they want you to pay to read online.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture
Forum Jump



Forum Jump


All times are GMT. The time now is 6:11 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.