Quote:
Originally Posted by RWSMADCONC
The "new" Comcast will run 3978 CY neat, probably more like 4100 at the end of the day. The first Comcast was about 25% bigger, and took about 10 hours with 3 pumps way back on October 1, 2005. Expect pretty much the same deal here.
|
I didn't express it very well, but what I meant to say was that this CITC pour,
combined with the pour tomorrow night at FMC, would probably be one of the largest--if not THE largest--amounts of concrete ever poured in Philly over a period of a week or so.
As always, though, thanks for those details.

We're talking about 400-500 truckloads of concrete just for this one CITC pour.