Structure to soon rise at New Mosaic Stadium site
Construction is on schedule as four cranes move onto the Evraz Place grounds
Reported by Kevin Martel
First Posted: Sep 18, 2014 12:59pm
Regina’s new Mosaic Stadium is starting to take shape and it won’t be long before the public will be able to see a structure.
Right now it’s hard to see much of anything besides construction crews and materials. One thing that might catch your eye
are a pair of gold tower cranes in the northeast and southeast corners of the site, standing 215 feet and 200 feet respectively. Two more cranes will be added next month; all four will remain at the site until October 2015.
PCL Construction District Manager Sean Hamelin said on any given day there are over 100 people working on the $278 million project on the grounds of Evraz Place, with four excavators and 30 trucks hauling soil off the site. About 64 Olympic sized swimming pools worth of material have been hauled away so far' that’s about half of the total excavation work.
Hamelin said everything is on budget and on time despite recent rainfall.
“It’s been boring which is great for us. There have been no surprises,” he said.
If everything continues to go on schedule, Hamelin outlined how you’ll be able to see part of the building very soon.
“You’ll start to be able to see some significant, what we call super structure, within the next few months.”
Hamelin said a significant amount of the structure should be erected over the winter. He’s hoping for the weather to be mild but even if we don’t luck out, he explained how they can still put up insulated tarps and use propane and natural gas heaters to protect concrete.
“There’s no question the excitement in our city is real when you see the cranes in the air, you see the bowl being dug, the cement going in and the structure going up,” said Mayor Michael Fougere.
The stadium is expected to be finished by August 2016 with the first Saskatchewan Roughrider game in June 2017.
You can follow the stadium’s construction progress yourself through a camera at ReginaRevitalization.ca.