Quote:
Originally Posted by thefourthtower
|
Thanks for posting 4th Tower.
Here's a good pic from the leader post article:
http://www.leaderpost.com/news/regina/Stadium+time+budget+Video/10215896/story.html
Quick Facts:
* On any given day four excavators are on site. They’ve removed 160,000 cubic metres of material so far, or 55 per cent of what’s going to be removed in total. About 75 per cent of the excavation will be complete by the end of 2014.
* Four rigs on site have completed 70 per cent of the piling work. That task is expected to be complete in October.
* Eighty per cent of the main floor foundation work on the east side of the stadium site is finished, said Hamelin. Soon, crews will install columns and suspended slabs. It won’t be long before people walking on * * Elphinstone Street will be able to see a structure rising above the construction fence.
* The construction site hole, for the stadium’s sunken bowl, is currently six metres deep. The west side will eventually be 10 metres deep to accommodate two additional levels: A floor for events and a mezzanine with locker rooms, kitchens and storage.
* Between 90 and 100 tradespeople are working on the site daily. That will jump to 180 by November. About 80 per cent of workers are local.
* The two cranes towering over the site are 65.5 metres and 61 metres, respectively. Two more cranes will be erected in October.