Quote:
Originally Posted by xd_1771
New paper I found at Thales Signalling
...
- The SkyTrain Evergreen Line system will be capable of running one train every 93 seconds in both directions (this is a litte less than 75 seconds with the Expo Line - which is a Waterfront switch limitation or otherwise they'd be doing 60s frequencies - but appropriate considering the crossover switching on the Evergreen)...
|
Not doing the weave and installing switches just east of Lougheed, by Whitespot where the steel curve is at different elevation happens, like originally planned, to save money, means a 18s longer minimum train headway?
ie Expo line max 48 trains per hour, Evergreen max 38 (38.7) trains per hour.
So has not doing the weave reduced the maximum capacity, ie pphpd, by 24%? If this connects through to Broadway (and eventually UBC) and the Millenium Line eventually ends at Lougheed (no inter-lining) once connecting to SFU are addressed, then does it reduce the max capacity along Broadway by 24% as well?