It also occurred in the area that was known to be the least predictable - sandy conditions in Sandy Hill after all. That unpredictable nature of soils was one of the reasons the tunnel was shortened in the first place.
     
     
  #842  
Old Posted Mar 12, 2014, 2:07 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,801
Quote:
Originally Posted by J.OT13 View Post
Unanticipated soil conditions? Really? REALLY?
Apparently we have armchair geotechnical engineers on this forum....
     
     
  #843  
Old Posted Mar 12, 2014, 4:22 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,131
Quote:
Originally Posted by Badlands View Post
Really? REALLY? LOL. I guess only you and Ken Gray can see underground. Goodness, we are all going to die.

It is a minor setback in the grand scheme of things. Bring on Phase 2.
I am 100% for the downtown tunnel If anything, they fell short of what I would have liked to see; a third CBD station, 150 meter centre platforms and huge mezzanine concourses with views of the platforms. Basically, I wanted Montreal's subway stations.

What I'm saying is, we ALL knew that Sandy Hill has sandy soil conditions. They even shorten the tunnel by 500 meters knowing that it might cause a problem as gjhall mentioned.

Quote:
Originally Posted by bradnixon View Post
Apparently we have armchair geotechnical engineers on this forum....
You don't need to be a engineer to know that tunneling in sand isn't ideal. All I'm saying is I wasn't expecting a collapse, but the soil conditions aren't a surprise.
     
     
  #844  
Old Posted Mar 13, 2014, 5:18 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
Construction Summary
Week of March 9




Central Segment

Tunnel

West Portal (Jawbreaker) (approximately 320 metres)
  • Mining as well as shotcreting and reinforcing the tunnel is ongoing.
  • Tunneling advances east under Queen Street, past Bay Street.

Central Shaft (Chewrocka) (approximately 28 metres)
  • Shotcreting and tunnel reinforcements continue as mining advances in the running tunnel.
  • The gantry crane continues removing tunneling debris.
  • Dewatering system installation has been completed.

Gantry crane testing at central shaft


East Portal (Crocodile Rouge)

Tunneling operations were suspended at the East Portal due to a roadway collapse on Waller Street. The cause continues to be investigated.

For weekly updates on tunnel excavation progress please visit the Roadheader page.

East Segment

Maintenance and Storage Facility (MSF)

Some site activities such as equipment mobilization and snow clearing will begin this week. Construction on the MSF building is scheduled to begin this spring and is anticipated to be completed in summer 2015.

Civic Works

Highway 417 Widening and Structure Rehabilitation

Roadworks
  • Boring and tunneling operations continue near Vanier Parkway.

Boring at Vanier Parkway


Signage
  • Underground installation of cables and pads to power the three message signs continues.

Structures
  • Widening, reconstruction and rehabilitation of various bridge structures is progressing as planned along the highway

Hurdman Bridge
  • Installation support points and erection of girders are ongoing on the south side of the bridge.
  • Installation of deck soffit formwork* continues.

Removing infill at Hurdman Bridge


St. Laurent Boulevard Overpass
  • Widening and rehabilitation work continues with abutment work and removals.

Vanier Parkway Overpass – work progresses in preparation of the rapid bridge replacement.
  • Refacing work at the north and south abutments and wing walls** is ongoing.
  • Preparatory work for the rapid bridge replacement is ongoing in the staging area.

Refacing work at Vanier Parkway


Belfast Road Underpass – work progresses in preparation of the rapid bridge replacement.
  • Piling activities are ongoing to support temporary structure.
  • Refacing, pouring and concrete repairs on the north and south abutments continue.

Lees Avenue Underpass – work progresses in preparation of the rapid bridge replacement.
  • Installation of falsework*** for the temporary structures in the staging area is scheduled this week.
  • Installation of rebar on retaining walls and of the metal protective system continue.

Coventry Bridge
  • Installation of caissons, reinforcing steel and concrete placement continues at the north ramp.

Caisson installation at Coventry


Notes:

* Formwork refers to a mold in which concrete is poured.
** Wing walls refers to a wall at the abutment of a bridge, extending beyond the bridge to restrain soil to unnatural slopes.
*** Falsework refers to a temporary support structure.
     
     
  #845  
Old Posted Mar 13, 2014, 5:42 PM
EdFromOttawa EdFromOttawa is offline
Registered User
 
Join Date: Sep 2013
Posts: 365
whatever happened to that great map showing the current locations of the tunnelling operations?
     
     
  #846  
Old Posted Mar 13, 2014, 6:42 PM
c_speed3108 c_speed3108 is offline
Registered User
 
Join Date: May 2007
Posts: 1,859
Quote:
Originally Posted by EdFromOttawa View Post
whatever happened to that great map showing the current locations of the tunnelling operations?
http://www.confederationline.ca/en/the-build/downtown-tunnel/map/
     
     
  #847  
Old Posted Mar 13, 2014, 7:19 PM
OTSkyline OTSkyline is offline
Registered User
 
Join Date: Jun 2012
Posts: 2,828
I feel like the western tunnel will reach the central shaft in no time, it is flying! The other two digs are a different story
     
     
  #848  
Old Posted Mar 13, 2014, 8:03 PM
Radster Radster is offline
Registered User
 
Join Date: Oct 2007
Location: Chelsea
Posts: 997
Quote:
Originally Posted by OTSkyline View Post
I feel like the western tunnel will reach the central shaft in no time, it is flying! The other two digs are a different story
Not really, as the western roadheader will soon reach Lyon station and will take quite some time boring the space for the station before it moves on further east towards the central shaft.

But if that roadheader does finish at the central shaft in good time, it could go help the central roadheader in boring the Parliament station, while the central roadheader continues boring eastwards without stopping to do the Parliament station. This could help make up some lost time caused by the delay on the east portal.

Thats how I see it anyway.
     
     
  #849  
Old Posted Mar 13, 2014, 9:19 PM
DarkArconio DarkArconio is offline
Registered User
 
Join Date: Mar 2010
Posts: 182
I thought about whether that was possible, but the challenge would likely be that a 2nd road header in the back would block trucks carrying refuse from the one in front. So probably unlikely. But perhaps they can move forward with other wiring and rail infrastructure while the other parts of the tunnel are finished.
     
     
  #850  
Old Posted Mar 13, 2014, 10:00 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,702
I think they'll just send Jawbreaker to another job elsewhere in the world. there's no point paying the rental on three machines when there's only room for two left on the job. Things will probably go faster when they no longer have to use the central shaft and Chewrocka's tailings can go out the LeBreton portal. By the looks of this video, it seems like hauling the stuff out is what holds things up:

     
     
  #851  
Old Posted Mar 14, 2014, 4:26 AM
Catenary Catenary is offline
Registered User
 
Join Date: Dec 2012
Posts: 1,403
Quote:
Originally Posted by Kitchissippi View Post
I think they'll just send Jawbreaker to another job elsewhere in the world. there's no point paying the rental on three machines when there's only room for two left on the job. Things will probably go faster when they no longer have to use the central shaft and Chewrocka's tailings can go out the LeBreton portal. By the looks of this video, it seems like hauling the stuff out is what holds things up:
I don't think the video depicts the manner in which all of the material is removed, not that it isn't still a limiting factor in the speed of tunneling. That video was shot very early on, when the conveyor would have been dumping material onto concrete if not for the loader below. They do not remove material from the tunnel at night, so it would not surprise me to see the roadheader simply pile the material behind it once the floor of the tunnel is rock. Then a scooptram can shuttle it back out of the tunnel. This way the scooptram can grab and go and the roadheader can just keep running.
     
     
  #852  
Old Posted Mar 15, 2014, 12:31 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
The LRT contract is the ‘deal of the year,’ if you’re in the P3 business

Posted by: David Reevely
March 14, 2014. 3:57 pm • Section: City Hall


The city touts this award, which apparently involved a gala dinner in New York City, that named Ottawa’s contract with Rideau Transit Group the “deal of the year” among North American public-private partnerships in 2013. It’s given by a trade publication called Project Finance.

Says the City of Ottawa:

Quote:
The award recognizes the innovative project financing structure developed by Rideau Transit Group in their successful bid to design, build, finance and maintain the 12.5 kilometre light rail system, including the fleet of 34 Alstom CITADIS Spirit trains.

“Last November, the Confederation Line was recognized with the 2013 Gold Award for Transportation Innovation from the Canadian Council for Public-Private Partnerships,” said Mayor Jim Watson. “This new award provides even more proof that our partnership with RTG has made us P3 leaders, not just in Canada, but across the continent. Together we are transforming Ottawa’s transportation network and we have established new standards of excellence for large-scale infrastructure procurement.”
I note that it’s Rideau Transit Group that gets the award. And, sure, good for them. But it’s not an award for protecting taxpayers or for the city’s getting a great deal or anything.

You need to register with Project Finance to see how they describe the award, which I did. It’s all about what a good deal this is for the lenders involved. For instance:

Quote:
The project’s construction risk allowed bank lenders to prove that they remain relevant to PPPs in Canada, though banks lent alongside a private placement, the financing route of choice in Canadian infrastructure…

The bank debt came from three lenders – Scotiabank, Bank of Tokyo-Mitsubishi UFJ and Sumitomo Mitsui Banking Corporation. The five-year revolving credit facility and the long-term private placement were both aggressively priced. The 34.5-year private placement has an average life of 22 years and priced at 230bp over the 30-year government of Canada bond. The bank debt priced at 145bp over CDOR on drawn amounts, but is not exposed to operational risk, since it will be repaid with government milestone payments.
Hooray for the banks’ proving they remain relevant? I guess? It’s actually not entirely clear to me what makes this a “deal of the year” other than its size. By any measure, a $2.1-billion construction deal plus a multi-billion-dollar maintenance component is huge.

The piece does note something I don’t think I’d heard before, which is that Rideau Transit Group was created with $75 million in equity from its major partners: 40 per cent from SNC-Lavalin, 40 per cent from ACS Infrastructures and 20 per cent from EllisDon.

http://blogs.ottawacitizen.com/2014/03/1...of-the-year-if-youre-in-the-p3-business/
     
     
  #853  
Old Posted Mar 19, 2014, 3:17 AM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
How much extra we’re paying for the LRT’s ‘fixed cost’

Posted by: David Reevely
March 16, 2014. 9:03 pm • Section: City Hall


Via Vancouver’s Frances Bula, who refers to it in an essay on how the P3 deal that produced that city’s Canada Line from the airport to downtown, here’s an interesting paper on the “second wave” of public-private partnerships Canada has seen lately, and what distinguishes them from the first wave. The paper’s undated but it was apparently presented at a conference last June, so as these things go it’s pretty current.

First wave of P3s? you ask. Buh?

Try this: The first wave featured things like the new building for the Royal Ottawa. The second wave includes our LRT. Although they have the same “public-private partnership” label and involve private money invested in public infrastructure, the private involvement serves very different purposes.

The paper by U of T’s Matti Siemiatycki argues that we grew accustomed to public-private partnerships seeming like bad deals thanks to a first wave of partnerships that were fundamentally about augmenting inadequate public funds for public purposes. How do you get more money to spend on something? You borrow it. When you get down to it, the first wave of P3s we saw, beginning in about 2000, amounted to borrowing private money in a way that was not borrowing in the strictest sense, so governments could deny they were doing it. But they were paying more, over time, to get their hands on funding right away, and that’s borrowing by another name. This wave of public-private partnerships made it possible for governments to do things they couldn’t immediately afford, and there’s value in that, but they made the projects more expensive than they would otherwise have been.

But now, Siematycki argues, our governments are using public-private partnerships for another purpose: to transfer risk. In the case of the Ottawa LRT, the city is paying a premium for a fixed-price contract that includes $300 million in private financing for the construction project. This is the part everybody in the business seems to think is really clever. Rideau Transit Group borrows the money from banks, mainly, and pays it back as the city government pays it slightly inflated milestone payments for getting chunks of the project done. It means RTG has a significant amount of skin in the game, as they say, because it owes $300 million right off the bat, a debt it can only cover it if hustles. Which hustling also happens to benefit the city government and the people of Ottawa. Win-win.

It costs extra, but we get something important for that premium. It’s a lot like hedging the price of an important but volatilely priced commodity, like fuel: You pay extra, but you’re protected from big spikes that could cost you even more.

As I wrote in a story just after the RTG deal was revealed in December 2012:

Quote:
According to the report, the effective interest rate on the arrangement works out to 6.32 per cent, even though the city could go out and borrow the initial $300 million at less than four per cent if it cared to, because interest rates are low and the city has excellent credit. That would be $165 million cheaper, according to Jensen, all other things being equal.

Instead, the city would like to have a private lender involved on the grounds that it’ll demand financial discipline from the builders. “It is the private funding component that allows for fixed price contracts and full risk transfers. It holds the private sector accountable through the introduction of lenders who provide oversight and private sector discipline,” Jensen wrote.

Municipalities have a poor track record of managing the costs of major projects, he acknowledged, and that’s the point: The $165 million extra is minimal if it slashes the risk of a much larger overrun.
Unless it isn’t. Back to Siematycki’s paper, which cites some of his own previous statistical work on projects led by Infrastructure Ontario (as Ottawa’s LRT is) showing that that cost certainty that’s so important has come at a really heavy price in other cases. P3s are popular, he writes, but…

Quote:
A review of the official ex ante value for money studies commissioned by governments across Canada show that PPPs are an expensive way of delivering infrastructure. In Ontario, ex ante value for money reports produced for the province’s PPP agency show that the base construction, financing and operation costs and transaction costs of delivering 28 infrastructure projects was estimated at $7.2 billion through PPPs compared with $5.5 billion if traditional procurement was used, a difference of $1.7 billion or 30%.
Ottawa’s not paying that big a premium, clearly, but $165 million is nothing to sneeze at. On the one hand, it’s basically good that City Hall’s not saying, “Yes, big infrastructure projects have frequently become money pits but that isn’t going to happen to us because we’re different in some way we can’t clearly articulate.” On the other, it sure would be nice if we could figure out what public authorities have historically gotten wrong, so we don’t have to overpay by a substantial but certain amount just to make sure we don’t end up overpaying by even more.

http://blogs.ottawacitizen.com/2014/03/16/how-much-extra-were-paying-for-the-lrts-fixed-cost/
     
     
  #854  
Old Posted Mar 21, 2014, 4:42 PM
IntoTheCore IntoTheCore is offline
Registered User
 
Join Date: Jul 2009
Posts: 119
This just popped up on my newsfeed:

http://www.cbc.ca/news/canada/ottawa/dow...eviously-excavated-pit-1.2581643?cmp=rss

"A technical analysis found that the previous excavation was filled with "poor quality, un-compacted backfill."
     
     
  #855  
Old Posted Mar 21, 2014, 5:34 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
Sinkhole due to old construction pit, says RTG

By MATTHEW PEARSON, OTTAWA CITIZEN March 21, 2014


The cave-in near Sandy Hill last month is being blamed on an old construction pit the builders of the city’s rail system didn’t know about, but the incident hasn’t shaken the confidence of the top bureaucrat overseeing the project.

Deputy city manager Nancy Schepers says the Rideau Transit Group’s quick response to the Feb. 20 incident — which included containing the site, filling the hole to prevent secondary damage, restoring water service to affected residents nearby and contacting the necessary city departments — actually reassured her.

“If anything, this makes me feel more confident because they had an incident and their processes worked. We all have processes in terms of, ‘how do you respond to an incident?’ and we really don’t want to test them.”

“There was a test and, quite frankly, they did it perfectly,” Schepers said.



Her comments come a month after a section of road about eight metres by eight metres collapsed just south of Laurier. Waller is closed there for the rail project and isn’t travelled, though the city closed the nearby intersection briefly while the cause of the collapse was investigated. Nobody was injured.

Leaking pipes, typically water mains, are the most frequent cause of sinkholes, as slow trickles of water wear away at underground soil and then the surface falls in all at once.

But the only pipe running through the area is a small sewer and there was no indication that there was anything wrong with it until the collapsing ground broke it.

Now, according to a report sent to city council Friday, RTG says its investigation of the cave-in found that the “tunnel crossed beneath a previously excavated construction pit” that was underneath the known city utilities, and likely extended from bedrock to the surface.

The shape of the old pit closely matched the shape of the six-metre deep sinkhole that opened up, and material from the pit turned out to be “indicative of poor quality, un-compacted backfill,” the report said.

Although it’s possible that similar surprises might arise in the future, the report said the city carried out an extensive geotechnical investigation before awarding the construction contact and RTG conducted further testing once it was selected to build the $2.1-billion LRT project.

The Waller sinkhole is considered a localized anomaly that wasn’t caught by the borehole investigations. RTG had drilled a borehole within 15 metres of the sinkhole, and along the underground ramp leading to the tunnel, and the soil conditions in those locations were consistent.

“There was no indication that anything was going to change,” said Peter Lauch, RTG’s technical director.

Lauch said RTG is reviewing its borehole logs and drawings to see where any other such anomaly could potentially occur and might, in some instances, drill additional boreholes, such as those recently completed on Laurier Avenue, to confirm the strength of the ground.

“This was an anomaly that couldn’t have been predicted unless you happen to have a borehole right at that location,” Schepers said, adding it would be pure speculation to guess why that underground pit was there in the first place.

“Who knows when that happened. We certainly weren’t aware of it, and clearly RTG was also not aware of it,” she said.

While tunnelling work on at the eastern portal of the LRT tunnel has been held up now for four weeks, work on the western and central shafts has continued. In fact, it’s ahead of schedule, with tunnelling equipment on the western portal soon to reach the future location of Lyon station, the westernmost stop downtown.

Tunnelling at the eastern end began again on Friday and will soon reach bedrock, which is a much more predictable material.

Lauch said a “sequential excavation method” is being used to do the tunnelling work. “You move forward every day and you assess on a daily basis what transpired with that tunnelling to make sure it’s consistent with what you assume,” he explained.

Unlike what it has done previously, RTG will dig out the bottom layer of the tunnel underneath Laurier Avenue first and then go over it a second time to dig out the top layer, making sure to leave at least two metres of bedrock between the top of the tunnel and the surface of the ground.

Cost over-runs caused by the delay are still being compiled, but Lauch said the incident — as well as damage to city utilities — is covered by insurance.

The incident did not cause damage to nearby buildings, he said.

Before work began, RTG installed specialized vibration monitors along the line and has so far received no negative results, meaning none of the monitors has sent out a warning that the level of movement exceeds a previously-determined value.

Expected to be completed by spring of 2018, the Confederation Line will run from Tunney’s Pasture station in the west to Blair Road in the east. Thirteen stations will dot the 12.5-kilometre route, including three located underground in the new, 2.5-km downtown tunnel.

[email protected]

Twitter.com/mpearson78

http://www.ottawacitizen.com/news/Sinkhole+construction+says/9646176/story.html

Last edited by rocketphish; Mar 22, 2014 at 11:11 PM. Reason: Added the "More to come..."
     
     
  #856  
Old Posted Mar 22, 2014, 11:12 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
City hall, Rideau Transit Group forthright about sinkhole

By Joanne Chianello, Ottawa Citizen March 21, 2014


OTTAWA — Here at city hall, we give thanks for small mercies.

So when the sinkhole report from the consortium building our light-rail system was released Friday morning — almost exactly a month to the day of when the giant hole appeared — we were appreciative that it didn’t appear after the close of the business.

Even better, both city and Rideau Transit Group officials were available for a sit-down interview within a couple of hours of the report’s being sent to councillors.

This is as it should be, of course. As Mayor Jim Watson often reminds us, the $2.1-billion LRT project is the largest infrastructure initiative in the history of our city. So it makes sense that officials should be available to discuss something as worrisome as the sinkhole. But that’s not always the case (owing to a penchant for clamming up that forms the basis of complaint in this column fairly regularly), so credit where credit is due.

But perhaps the willingness to reach out on the part of officials is simpler: this report is basically good news. Why wouldn’t the city and RTG want to talk about it?

The Waller Street sinkhole was “unexpected,” said RTG. (In an earlier report, the crater was described as “unanticipated.”) Well, obviously. No one ever suspected the construction consortium would have ignored actual evidence and bored through ground that was likely to collapse. What RTG means by the statement is that it absolutely expected sandy soil conditions in Sandy Hill; it was prepared for the challenges of tunnelling through metres of so-called “overburden soil” before reaching the more stable rock.

What it did not expect, though, was a “previously excavated construction pit” filled with “poor quality, uncompacted” material.

Should RTG or the city have known about the pit? In a perfect world, yes. And it certainly leads us to wonder about the quality of past infrastructure work in Ottawa when an eight-metre-square, six-metre-deep hole was allowed to be filled in with substandard material.

But, according to RTG’s technical director Peter Launch, a bore hole had been drilled about 15 metres away showing only the normal sandy conditions found in the rest of the area (a condition for which the company was prepared). And none of the other dozens of drilled holes along the tunnel route indicated the presence of the type of loose back-fill found in this old construction pit.

More importantly — and this is the point that deputy city manager Nancy Schepers was at pains to make — the sinkhole showed how prepared RTG is for an unexpected event.

Workers were aware of “excessive loose and wet material starting to fall” at about 9.40 p.m. on Feb. 20. They quickly moved to stabilize the area. Minutes later, they closed it off to traffic, hours before the sinkhole reached the surface. No one was hurt.

RTG will be covering the costs of any delay, as well as the damage done to municipal pipes and traffic signals. And, as the Citizen’s Matthew Pearson reports, the consortium has a plan to continue tunnelling — cautiously. It’s about as reassuring a response, so far, as anyone could reasonably expect in a scenario that initially gave everyone a sinking feeling.

[email protected]">jchian...awacitizen.com

twitter.com/jchianello
© Copyright (c) The Ottawa Citizen

http://www.ottawacitizen.com/news/Joanne...nsit+Group+forthright/9647915/story.html
     
     
  #857  
Old Posted Apr 3, 2014, 5:42 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
Construction Summary
Week of March 16




Central Segment

Tunnel


West Portal (Jawbreaker) (approximately 345 metres)
  • Mining and tunnel reinforcements are ongoing as tunneling advances east under Queen Street, past Bay Street.

Central Shaft (Chewrocka) (approximately 32 metres)
  • Shotcreting and tunnel reinforcements continue as mining advances east.
  • The gantry crane continues removing tunneling debris.

East Portal (Crocodile Rouge)
  • Tunneling operations were suspended at the East Portal due to a roadway collapse on Waller Street.

East Segment

Maintenance and Storage Facility (MSF)
  • Preliminary site activities such as equipment mobilization, grubbing and snow clearing continue. Construction on the MSF building is scheduled to begin this spring and is anticipated to be completed in summer 2015.

Clearing at the MSF


Civic Works

Highway 417 Widening and Structure Rehabilitation

Roadworks
  • Boring operations continue on the north side of the highway, near Vanier Parkway.
  • Sewer operations resume on the north side of the highway, past Vanier Parkway.
  • Construction of the sound wall near Belfast Rd. begins this week

Signage
  • Work to power the three message signs continues.

Structures
  • Widening, reconstruction and rehabilitation of various bridge structures is progressing as planned along the highway

Hurdman Bridge
  • Installation of support points and erection of girders are ongoing on the south side of the bridge.
  • Installation of deck soffit formwork* continues on the south side of the bridge.

Deck work at Hurdman Bridge


St. Laurent Boulevard Overpass
  • Widening and rehabilitation work continues with abutment work and removals.
  • Girder and formwork* installations begin this week.

Vanier Parkway Overpass – work progresses in preparation of the rapid bridge replacement.
  • Refacing work at the north and south abutments and wing walls** is ongoing.
  • Preparatory work for the rapid bridge replacement is ongoing in the staging area.

Belfast Road Underpass – work progresses in preparation of the rapid bridge replacement.
  • Refacing, pouring and localized concrete removals continue.
  • Reconstruction work is ongoing on the abutments.

Lees Avenue Underpass – work progresses in preparation of the rapid bridge replacement.
  • Superstructure construction continues with the installation of falsework*** for the temporary structures in the staging area.
  • Refacing at the north and south abutments continues.

Foundation construction at Lees Ave


Coventry Bridge
  • Pouring of caissons is ongoing this week at the north abutment.

Notes:

* Formwork refers to a mold in which concrete is poured.
** Wing walls refers to a wall at the abutment of a bridge, extending beyond the bridge to restrain soil to unnatural slopes
*** Falsework refers to a temporary support structure.

Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

http://www.confederationline.ca/en
     
     
  #858  
Old Posted Apr 3, 2014, 5:47 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
Construction Summary
Week of March 24




Central Segment

Tunnel


West Portal (Jawbreaker) (approximately 365 metres)
  • The roadheader continues to excavate the layer of rock on the tunnel floor referred as the bench until mid-week.
  • Shotcreting and pouring of the mud slab begins once the bench has been mined.

Central Shaft (Chewrocka) (approximately 48 metres)
  • Shotcreting and tunnel reinforcements continue as mining advances east.
  • Man and material hoist installation continues this week.
  • Ventilation system and scrubber have been installed.

Central shaft mining advances east


East Portal (Crocodile Rouge)
  • As per the March 21 Notice on the project website, work has resumed at the East Portal.

East Segment

Maintenance and Storage Facility (MSF)
  • Preliminary site activities such as equipment mobilization, grubbing and snow clearing continue. Excavation for the MSF building is scheduled to begin this week.

Grubbing continues at the MSF


Civic Works

Highway 417 Widening and Structure Rehabilitation

Roadworks
  • Boring and sewer work continue on the north side of the highway, near Vanier Parkway.
  • Construction of the sound wall footings along the highway, from St. Laurent Blvd. to Vanier Pkwy., is ongoing.
  • Work on the new sound wall along the north side of the highway at Robinson Avenue has begun with construction on the footings.

Signage
  • Work to power the three message signs continues.

Structures

Widening, reconstruction and rehabilitation of various bridge structures is progressing as planned along the highway.

Hurdman Bridge
  • Installation of girders is ongoing on the south side of the bridge.
  • Formwork* on the north side deck continues this week.

St. Laurent Boulevard Overpass
  • Widening and rehabilitation advances with abutment construction and removals.
  • Girder installations continue.
  • Formwork occurs for the deck overhang.

Vanier Parkway Overpass – work progresses in preparation of the rapid bridge replacement.
  • Refacing work at the north and south abutments and wing walls** is ongoing.
  • Preparatory work for the rapid bridge replacement advances in the staging area.

Refacing work at Vanier Parkway


Belfast Road Underpass – work progresses in preparation of the rapid bridge replacement.
  • Refacing, pouring and localized concrete removals continue.
  • Reconstruction work is ongoing on the abutments, including double soldier piling on the south side.

Lees Avenue Underpass – work progresses in preparation of the rapid bridge replacement.
  • Preparations for girder installation and deck work are ongoing in the staging area.
  • North and south abutment work continues with pouring and formwork.

Lees Ave bridge construction


Coventry Bridge
  • Installation of rebar and pouring of caissons is ongoing this week at the north abutment.

Casisson work at Coventry Bridge


Notes:

* Formwork refers to a mold in which concrete is poured.
** Wing walls refers to a wall at the abutment of a bridge, extending beyond the bridge to restrain soil to unnatural slopes

Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

http://www.confederationline.ca/en
     
     
  #859  
Old Posted Apr 3, 2014, 5:53 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
Construction Summary
Week of March 30




Central Segment

Tunnel

West Portal (Jawbreaker) (approximately 380 metres)
  • As bench mining has been completed, the roadheader continues mining east toward Lyon Street.
  • Shotcreting and pouring of the mud slab continue as mining advances.

Central Shaft (Chewrocka) (approximately 52 metres)
  • Shotcreting and tunnel reinforcements continue as mining advances east.
  • Hoist installation continues this week.

Central shaft mining advances


East Portal (Crocodile Rouge)
  • Tunneling activities continue in two phases; the first phase involves investigative drilling followed by grouting to confirm stable tunnel face conditions. The second phase of tunneling works will start only after all new borehole data is fully analyzed.

For weekly updates on tunnel excavation progress please visit the Roadheader page.

East Segment

Maintenance and Storage Facility (MSF)
  • Tree removals have been completed
  • Preliminary site activities such as equipment mobilization, grubbing, utilities work and snow clearing continue.
  • Excavation for the MSF building foundation has begun.

MSF and connector (Belfast Road)


Civic Works

Highway 417 Widening and Structure Rehabilitation

Roadworks
  • Boring and sewer work progresses on the north side of the highway, near Hurdman Bridge.
  • Construction of the sound wall footings continue along the highway, from St. Laurent Blvd. to Vanier Pkwy.
  • Construction on the new sound wall footings continue along the north side of the highway at Robinson Avenue.

Drilling footings for sound wall (Belfast)


Signage
  • Electric work for the three message signs is ongoing.

Structures

Widening, reconstruction and rehabilitation of various bridge structures is progressing as planned along the highway.

Hurdman Bridge
  • Installation of girders on the north and south side of the bridge have been completed.
  • Formwork* progresses on the north side deck and includes the installation of overhead brackets.
  • Work progresses on the south side with the installation of an access to prepare for pouring of the deck.

Deck work on new girders - north side of Hurdman Bridge


St. Laurent Boulevard Overpass
  • As girder installation has been completed, widening and rehabilitation progresses with backfilling at the northeast and northwest abutments.
  • Formwork continues for the deck overhang on the north and south sides of the bridge.

Vanier Parkway Overpass – work progresses in preparation of the rapid bridge replacement.
  • Pouring concrete refacing on the south side wing wall** and work on the waterproofing trim (coping) commences.
  • Forming top of wing wall and waterproofing trim continues in addition to refacing work on the north side of the bridge.
  • Steel work continues on the north side.

Belfast Road Underpass – work progresses in preparation of the rapid bridge replacement.
  • Forming top of wing wall on the north side and refacing work continues on the south side of the bridge.
  • Reconstruction work is ongoing on the south abutment, including double soldier piling.

Lees Avenue Underpass – work progresses in preparation of the rapid bridge replacement.
  • Construction of the new bridge components including installation of girders, continues in the staging area.
  • North and south abutment work continues with pouring and formwork.

Lees Ave underpass construction advances in staging area


Coventry Bridge
  • Installation of rebar and pouring of caissons continues for the next weeks at the north abutment.

Notes:

* Formwork refers to a mold in which concrete is poured.
** Wing walls refers to a wall at the abutment of a bridge, extending beyond the bridge to restrain soil to unnatural slopes.

Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

http://www.confederationline.ca/en
     
     
  #860  
Old Posted Apr 3, 2014, 5:54 PM
rocketphish's Avatar
rocketphish rocketphish is online now
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,705
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 2:54 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.