Construction Summary
Week of March 2
Central Segment
TUNNEL
West Portal (Jawbreaker) (approximately 300 metres)
- Mining as well as shotcreting and reinforcing the tunnel is ongoing.
- Tunneling advances east under Queen Street, just past Bay Street.
Roadheader mining advances at west portal
Central Shaft (Chewrocka) (approximately 23 metres)
- Shotcreting and tunnel reinforcements continue as mining advances in the running tunnel.
- The gantry crane continues removing debris.
- Equipment and dewatering system installation continues this week.
Gantry crane testing at the central shaft
East Portal (Crocodile Rouge)
Tunneling operations were suspended at the East Portal due to a roadway collapse on Waller Street. The cause is currently being investigated.
For weekly updates on tunnel excavation progress please visit the
Roadheader page.
East Segment
Maintenance and Storage Facility (MSF)
Some site activities such as equipment mobilization and snow clearing are scheduled to begin as early as mid-March. Construction on the MSF building is scheduled to begin this spring.
CIVIC WORKS
Highway 417 Widening and Structure Rehabilitation
Roadworks- Boring operations continue east of Vanier Parkway.
Signage
- Overnight installation of the overhead variable message signs (at Parkdale Avenue, Walkley Road and Blair Road), which will provide updated information to motorists, have been completed. OPP was onsite to assist during full highway closure.
- Underground installation of cables and pads to power the three message signs continues.
Overnight installation of VMS at Parkdale
Structures
Widening, reconstruction and rehabilitation of various bridge structures is progressing as planned along the highway
Hurdman Bridge
- Installation support points and erection of girders continue this week.
- Installation of deck soffit formwork* occurs.
- Pouring of abutment extensions continues.
Overnight girder installation at Hurdman Bridge
Girder installation at Hurdman Bridge
St. Laurent Boulevard Overpass
- Widening and rehabilitation continues with grade work all week.
Vanier Parkway Overpass – work progresses in preparation of the rapid bridge replacement.
- Steel work and removals are progressing as planned.
- Preparatory work for the rapid bridge replacement is ongoing in the staging area.
Belfast Road Underpass – work progresses in preparation of the rapid bridge replacement.
- Piling activities are ongoing to support temporary structure.
- Refacing, pouring and concrete repairs on the north and south abutments continue.
Lees Avenue Underpass – work progresses in preparation of the rapid bridge replacement.
- Temporary foundation pouring is ongoing.
- Installation of rebar on retaining walls and of the metal protective system continue.
Pouring of temporary foundation at Lees Avenue
Notes:
*Formwork refers to a permanent mold in which concrete is poured.