Quote:
Originally Posted by FrankieFlowerpot
Say 12 weeks to put the seats, handrails to vomitories etc in based what they did at Commonwealth stadium - which means all the seating slabs need to be in place by April 12 (I'm counting back from July 18th - they will need to have a test event at the stadium before allowing a full event there - BMO Field let TFC fans into the stadium a week before it opened and they watched a game on the video board - had concessions open etc).
Meaning 6/7 weeks to get all the slabs up there.
|
The way they have been going at it, it could be three. It looks like almost half has been done in one week. And I think they are working today (Saturday). Yup, they are putting slabs in as I post! Fingers crossed.
Tim Hortons Field Hamilton March 1/2014
Notice you can see the new slab (looks like a white bar) on the right next to the vomitory opening prior to being placed in the bottom row.
End of the day