Quote:
Originally Posted by Calgarian
Are they going to build the entire parkade at once? I thought building 1 was going to be finished before they demolished the existing parkade.
|
Quoting myself from
further up the same page...
Quote:
Originally Posted by Blue_Cypress
Yes. When complete, the parkade will fill the entire block, but it will be phased. The west side will be completed with the second tower.
|
I suppose there's some ambiguity, so:
Phase 1: East portion of underground parkade, east tower(taller), partial atrium.
Phase 2: Demolish Bow(bay/above ground) parkade. Build west portion of underground parkade, west tower(shorter), and the full atrium, with the "spanish steps."
Phase 1 is proceeding ahead now. Once complete, parking in the above ground parkade structure will be restricted to ~1450 stalls I believe, as part of the terms of the permit, if it is not demolished before then to allow commencement of phase 2.
There was originally some language in the permit requiring the developer to retain the +15/30 from scotia/bay to the above-ground parkade until such time as phase two was clearly going ahead. The direction things went after that was... discouraging.
Here's a phasing plan from the permit application.