City of Ottawa
October 25, 2013
- Inside the south stands, drywall is being put up in the offices, locker rooms and other spaces and the walls are being painted in the lower levels
- The first pieces of the Veil, the iconic wooden surround at the south stands, began this week
- Most of the precast concrete risers that the seats will be attached to, have now been installed
- At the north stands, seat installation continues
- The new roof materials are being laid down over the north stands
- At the upper concourse in the north stands, new sections of concrete floor are being poured
The stadium has a new look when viewed from the Rideau Canal
New seats continue to be installed at the north side stands. This is expected to continue during November
The south stands are coming together as more of the bleachers are installed, and the new stair case is built
From the air, it’s obvious how much work is occurring on a daily basis at Lansdowne