Quote:
Originally Posted by ThomJames
I think your theory may have merit. I observed the soil-sampling towards the corner of the intersection. (9th and Hope) From my experience sampling is usually done months before permits are pulled, so maybe they are subdividing the project into two phases: Parking lot toward the back of the lot first, with some kind of tower to be built abutting the intersection in the future. If we're lucky, using the same design as previous renderings??
|
Probably worth mentioning that the permit application looks like it was submitted on April 17th, two days before you observed the soil testing. I suppose we'll hear something eventually, so I won't worry until then. Hopefully it's not just a parking structure.
Just next door to the 9th/Hope lot, I witnessed a rare sight this afternoon: people actually working on the Trinity Auditorium/Embassy Hotel.
As is typical of the Chetrit Group, it looked like a skeleton crew.
And another block down 9th street, 888 Olive continues.