Quote:
Originally Posted by The Jabroni
Isn't there a city by-law currently preventing overnight construction without special permits or something?
|
this is the usual boilerplate wording in paving contracts
Further to 3.10 of CW 1130, the Contractor shall require written permission forty-eight (48)
hours in advance from the Consultant for any Work to be performed between 2000 hours and
0700 hours, or on Saturdays, Sundays, Statutory Holidays and or Civic Holidays.
I think that this clause is usually used for cutting the expansion joints in green concrete but also can be used for after hours water main and sewer cut overs during overnight low flow times.
I am sure if the city needed 24 hour construction it would be explicitly worded in the tender documents as being permitted.