Old Posted Jul 14, 2026, 1:10 AM
SpongeG's Avatar
SpongeG SpongeG is offline
Registered User
 
Join Date: Jun 2006
Location: Coquitlam
Posts: 40,076
some photos

Photos: Vancouver's Broadway subway megaproject adding rails, testing trains
The $2.83-billion project continues forward while out of sight to the public.
Brendan Kergin Vancouver is Awesome
July 13, about 2 hours ago



3 / 10 The final pieces of rail between the incoming Arbutus station and VSS-Clark Station were installed in May.Ministry of Transportation / Flickr

more at the source here
__________________
belowitall
Reply With Quote
     
     
  #3782  
Old Posted Jul 14, 2026, 1:53 AM
officedweller officedweller is online now
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,715
Quote:
Originally Posted by jollyburger View Post
Cambie along Broadway seems close to ready for the paving.
Drove past today and they were tamping the gravel baselayer with the vibrator machine.
Concrete bus pad and curbs are all in place.
Reply With Quote
     
     
  #3783  
Old Posted Jul 14, 2026, 7:14 AM
bluefox's Avatar
bluefox bluefox is offline
Registered User
 
Join Date: Aug 2013
Posts: 423
Quote:
Originally Posted by SpongeG View Post
some photos

Photos: Vancouver's Broadway subway megaproject adding rails, testing trains
The $2.83-billion project continues forward while out of sight to the public.
Brendan Kergin Vancouver is Awesome
July 13, about 2 hours ago


3 / 10 The final pieces of rail between the incoming Arbutus station and VSS-Clark Station were installed in May.Ministry of Transportation / Flickr

more at the source here
"VSS-Clark"? Does the author of the article not live here?
Reply With Quote
     
     
  #3784  
Old Posted Jul 14, 2026, 5:21 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,710
All the fencing is coming down around the section of Cambie that needs to get paved.



https://trafficcams.vancouver.ca/cambieBroadway.htm
Reply With Quote
     
     
  #3785  
Old Posted Jul 15, 2026, 3:56 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,710
^^ Tar sprayed down over the roadbase.

Walkaround Main

Video Link


City Hall

Video Link
Reply With Quote
     
     
  #3786  
Old Posted Jul 15, 2026, 2:31 PM
madog222 madog222 is offline
Moderator
 
Join Date: Jan 2014
Posts: 4,182
Paving Cambie today.
Reply With Quote
     
     
  #3787  
Old Posted Jul 15, 2026, 3:00 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is online now
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,633
I don't know what is preventing them from opening the right turn at Main/Broadway and re-opening the left turn lanes off Main onto Broadway. The final alignments are all there.
Reply With Quote
     
     
  #3788  
Old Posted Jul 15, 2026, 4:50 PM
AlessioSBT AlessioSBT is online now
Registered User
 
Join Date: May 2024
Posts: 116
I know I already said this but I am a little bit worried by the fact that on main I don't see any tree.
I remember seeing them in the project I really hope this is not a way to cut expenses and time becasue broadway without trees would be very very far from the "great street" plan they had in mind.
Reply With Quote
     
     
  #3789  
Old Posted Jul 15, 2026, 4:56 PM
officedweller officedweller is online now
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,715
May be too hot this time of year to plant trees.
****
Just realized that the new traffic light at 8th and Ash is to support the detour during the Broadway closure for deck removal.
Reply With Quote
     
     
  #3790  
Old Posted Jul 15, 2026, 5:21 PM
Sheba Sheba is offline
Registered User
 
Join Date: Jan 2015
Location: BC
Posts: 4,591
Quote:
Originally Posted by officedweller View Post
May be too hot this time of year to plant trees.
I'm the person who deals with the landscapers for my building, and yes now is the totally wrong time to plant trees. Depending on the temperature they might start doing that in Sept.
Reply With Quote
     
     
  #3791  
Old Posted Jul 15, 2026, 5:47 PM
madog222 madog222 is offline
Moderator
 
Join Date: Jan 2014
Posts: 4,182
Plus there's still construction all over, trees going in will be one of the last steps.
Reply With Quote
     
     
  #3792  
Old Posted Jul 15, 2026, 5:49 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,710
From the end of June

Quote:
The installation of green infrastructure along the boulevard, as well as street furniture on the newly widened sidewalks will continue through the summer.
https://www.broadwaysubway.ca/app/uploads/sites/626/2026/06/BSP-MP-Summer-Update-June-24.pdf
Reply With Quote
     
     
  #3793  
Old Posted Jul 15, 2026, 9:28 PM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,790
Quote:
Originally Posted by AlessioSBT View Post
I know I already said this but I am a little bit worried by the fact that on main I don't see any tree.
Trees are done by the Parks Department, and they have their own schedule that's independent of everything else.
Reply With Quote
     
     
  #3794  
Old Posted Jul 15, 2026, 11:18 PM
mcj mcj is online now
Registered User
 
Join Date: Dec 2021
Location: New West
Posts: 1,206
Quote:
Originally Posted by aberdeen5698 View Post
Trees are done by the Parks Department, and they have their own schedule that's independent of everything else.
It's wild how we've had so many mayors/councillors promising efficiency yet city departments don't coordinate with each other and operate independently. I know someone setting up a new business in a renovated building in the CoV and they've had the most strung out experience trying to get the required city departments to come do their job for sewer / water / electrical / paving / sidewalks / street trees etc., every department has zero insight or coordination with another. It's probably easier said than done, but if anyone running in October actually wants to make good on an efficiency promise, it's an obvious one to tackle.
Reply With Quote
     
     
  #3795  
Old Posted Jul 16, 2026, 2:58 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,710
They removed the storm water retention tank (?) next to where they paved so I guess they'll paint lines and open the road in the next day or two. There's fencing/workers at the temporary bus stop next to the station so that might get restored right after as well. The bus stop was moved south to the other side of 10th Ave today.
Reply With Quote
     
     
  #3796  
Old Posted Jul 18, 2026, 7:36 AM
madog222 madog222 is offline
Moderator
 
Join Date: Jan 2014
Posts: 4,182
Line painting tonight for the shifted Cambie SB lanes.
Reply With Quote
     
     
  #3797  
Old Posted Jul 18, 2026, 6:30 PM
s211 s211 is offline
Registered User
 
Join Date: Oct 2008
Location: The People's Glorious Republic of ... Sigh...
Posts: 8,515
Lines painted yesterday on West 8th. Bus lanes were in the middle, not on the sides. That's probably to assist with the tight turns around the side streets?
__________________
If it seems I'm ignoring what you may have written in response to something I have written, it's very likely that you're on my Ignore List. Please do not take it personally.
Reply With Quote
     
     
  #3798  
Old Posted Jul 18, 2026, 7:00 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,710
Quote:
Originally Posted by s211 View Post
Lines painted yesterday on West 8th. Bus lanes were in the middle, not on the sides. That's probably to assist with the tight turns around the side streets?
If the centre lane is stopping short of the intersection to allow the articulated buses to take a right maybe it's just to stop stupid drivers from pulling right up to the intersection?
Reply With Quote
     
     
  #3799  
Old Posted Jul 19, 2026, 1:40 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,710
Looks like they'll repaint the rest of the road for the new configuration.



https://trafficcams.vancouver.ca/cambieBroadway.htm
Reply With Quote
     
     
  #3800  
Old Posted Jul 19, 2026, 3:24 PM
madog222 madog222 is offline
Moderator
 
Join Date: Jan 2014
Posts: 4,182
Lanes look to be more or less finalized on Cambie for the Broadway closure. Centre bus only right turn lanes on Cambie to W 8th and Broadway.




From CoV https://trafficcams.vancouver.ca/cambieBroadway.htm

Last edited by madog222; Jul 19, 2026 at 3:45 PM.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 7:29 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.