In this
Jan 27th update from True North, it says the
consultation and design for project’s centre block ongoing, so we wont have renderings until Architecture49 completes that design work.
The residential tower, developed by SCO and designed by Number Ten (the same partnership behind Wehwehneh), has progressed more quickly than the Centre Block. This is because it was selected for several funding programs, including the Housing Accelerator Fund (HAF). To qualify for this funding, building permits had to be applied for and issued by a specific deadline, which I believe was November 2025. It makes sense at this stage that the tower rendering produced by Number Ten only reflects their portion of the development.
It’s quite possible that the Centre Block façade will remain unchanged, with the bulk of the budget directed toward the internal reconfiguration of the mall. As mentioned earlier, we won’t know for certain until the design work is completed and released publicly.
Quote:
Jan. 27, 2026 – Pihtikwè Skatepark relocation facilitates next phase of major construction activity on multi-family housing tower
Pihtikwè Skatepark relocation facilitates next phase of major construction activity on multi-family housing tower
Construction and demolition activities are on schedule for the 300,000-square-foot, 12-storey Healthcare Centre of Excellence (HCCE), as part of True North Real Estate Development’s (TNRED) redevelopment of Portage Place.
“We would like to acknowledge, congratulate and thank the construction and demolition teams at PCL Construction and Rakowski Cartage & Wreckage for their incredible work, planning and safe removal of structural elements of the former atrium. It’s amazing to see a fresh view of our downtown taking shape, allowing sightlines from Central Park south toward the RBC Convention Centre and setting the stage for vehicular and pedestrian access created by the redevelopment,” said Gavin Johnstone, Chief Operating Officer with TNRED.
Development of the health tower is the first phase of construction/demolition activity for the site which will also include multi-family housing complemented by neighbourhood services, retail, and public and green spaces.
Redevelopment milestones anticipated this year include:
- HCCE deconstruction work to be completed by spring 2026
- Tower crane for new structure work expected on site in spring 2026
- Construction phase of HCCE to begin between late Q1 and early Q2
- Consultation and design for project’s centre block ongoing
- Preparation for construction of multi-family housing project (TN-SCO 92 Inc.) slated to begin Q1, 2026
PCL has diverted more than 75 percent of materials removed from the site from landfills to appropriate recycling streams.
|