Councillor calls for independent review after new issue keeps O-Train LRT service closed in east end
Coun. Tim Tierney wants an independent review of the latest issue to halt OC Transpo's LRT trains in the east of Ottawa.
By Aedan Helmer, Ottawa Citizen
Published Mar 13, 2026 | Last updated 17 minutes ago
Coun. Tim Tierney is renewing his call for an independent third-party review after a new issue with the LRT’s overhead power lines partially shut down service following Wednesday’s ice storm.
The power line snapped after a buildup of ice from the storm on March 11 and OC Transpo said crews would continue with “labour intensive” work to restore Line 1 service in the eastern section of the rail system.
“Shortly after the start of service (Friday) morning, Line 1 experienced two power issues near Tremblay and Blair stations and a short piece of the overhead catenary system (OCS) was damaged and fell at Blair Station,” said OC Transpo interim general manager Troy Charter in an update to council.
Charter said initial reports indicated the freezing rain on Wednesday resulted in the new issues with the power lines.
Line 1 service continued to operate between Tunney’s Pasture and uOttawa stations Friday, with replacement buses running between Lyon and Blair stations in place of the trains.
Rideau Transit Maintenance completed inspections between Lees and Blair stations and had started to tow three stopped trains back to the rail yard, Charter wrote in the memo on Friday afternoon.
Repair work on the overhead power lines at Blair Station was scheduled to begin when all the vehicles have been removed, Charter said, followed by inspections and testing of the OCS “to ensure no further corrective work is required.”
Passenger service would then resume following the inspections and testing.
Tierney visited Blair Station shortly after 9 a.m. on Friday and said he was surprised to see no crews onsite from the city or from RTG.
“I saw wires hanging down off the trains and not one person from RTG or anybody, just a series of yellow tape roping off the train. It was a ghost town for 45 minutes,” Tierney said Friday.
“That’s concerning, and that’s why my continued push is for the province to help us with their commitment and get a third party, somebody independent of RTG, to do this evaluation. I’ve been calling on this for at least a year,” Tierney said.
“Every day with this train, it’s like something else doesn’t work. Let’s strap lube, grease, scrape, do something different,” he said.
“I’m not comfortable with that. I feel we need someone with an engineer stamp that will come in and will actually sign off on something that will tell us where the challenges are. And the only way to achieve that is have the province step up and get this resolved.”
On Wednesday, OC Transpo staff reported electrical “arcing” on trains between Hurdman and Lees stations.
On Thursday, Charter said Rideau Transit Maintenance (RTM) had completed the removal of ice buildup across the power system, except near Lees Station, and continued to work to remove a stopped train.
“All efforts are being made to restore Line 1 service,” Charter wrote on Friday. “This process is labour intensive and is expected to take most of the day.”
https://ottawacitizen.com/news/new-issue-stalls-return-of-lrt