I guess we won't have to wait long for Phase 2.
Quote:
CESLP and the Developer have entered into an amendment to the Infrastructure Agreement
dated March 2, 2026 (the “Amendment Agreement”) which, among other things, memorializes a
revised schedule of target dates for Phase 1 and Phase 2. The revised schedule contemplates
occupancy dates for Phase 2 towers in 2029, and thatthe Developer will not be permitted to
amend the target occupancy date for any Phase 2 tower to a date that is later than December 1,
2030, unless otherwise agreed by CESLP.
|
Quote:
CESLP still expects the Developer to proceed with Phases 3 and 4; however, the Developer has
not yet communicated a proposed timeline to CESLP.
|
https://docs.bcuc.com/documents/proceedings/2026/doc_86346_b-7-ceslp-late-response-bcuc-ir1.pdf
In-Service Dates for the energy system
Tower 4 Oct 2028 (still rental office 4,158 m2)
Tower 5 April 2029
Tower 6 March 2029
Tower 7 August 2029