  #3161  
Old Posted Aug 24, 2025, 5:58 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,211
Broadway is back to four lanes between Main and Quebec, it had been down to two lanes for about three months for utility work at the lane beside the Lee Building.
Reply With Quote
     
     
  #3162  
Old Posted Aug 26, 2025, 9:12 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,211
Backfilling of the cut and cover section between Maple and Cypress will begin soon.

Full notice: https://www.broadwaysubway.ca/app/upload...se-of-work-begins-at-Arbutus-Station.pdf
Reply With Quote
     
     
  #3163  
Old Posted Aug 27, 2025, 2:59 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,782
Posted August 21st:


These are the ventilation shafts for Arbutus Station! They will connect to two large tunnel ventilation fans, which will help move air through the subway tunnels.
https://x.com/broadwaysubway_/status/1958586240824955192

Posted August 26th:


At Broadway-City Hall Station, a crew member prepares rebar for a wall that will support the station’s underground roof.
Below this roof is where elevators, escalators and stairs will be located, connecting the Millennium and Canada lines.

https://x.com/broadwaysubway_/status/1960402069753328086

Posted August 19th:


Concrete for these stairs at Mount Pleasant Station was recently poured.
The stairs will connect the ground-level station entrance to the concourse level below. Up and down escalators have now been installed next to the stairs.

https://x.com/broadwaysubway_/status/1957865293511815611
Reply With Quote
     
     
  #3164  
Old Posted Aug 27, 2025, 3:12 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,790
I guess they did some airflow modeling and decided they needed the raised roof there since the ventilation fans at Emily Carr are placed there.

SkyTrain tunnels at the Great Northern Way – Emily Carr site by B.C. Ministry of Transportation and Transit, on Flickr
Reply With Quote
     
     
  #3165  
Old Posted Aug 29, 2025, 9:20 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,782
South Granville Station


At South Granville Station, crews are constructing the last section of floor for the concourse level.
When the floor is completed, South Granville Station will be connected to the neighbouring building, where there will be an integrated station entrance!

https://x.com/broadwaysubway_/status/1961138013775249459
Reply With Quote
     
     
  #3166  
Old Posted Sep 4, 2025, 2:50 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,782
From twitter Sept 2nd:


Near GNW-Emily Carr Station, this birds-eye view shows the elevated guideway transitioning to underground tunnel as it approaches the station.
Can you see the tunnel getting wider towards the right? This widening creates space for the centre platform in between the tracks.

https://x.com/broadwaysubway_/status/1962970081513607539
Reply With Quote
     
     
  #3167  
Old Posted Sep 4, 2025, 3:39 AM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,211
Note that track has since been installed in this section.
Reply With Quote
     
     
  #3168  
Old Posted Sep 4, 2025, 4:13 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,790
Reply With Quote
     
     
  #3169  
Old Posted Sep 25, 2025, 9:34 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,782
From Project twitter

Sept 25:


At Mount Pleasant Station, walls are being built for the concourse level of the station.
In this photo, a mason worker is building a wall that will separate the public areas and the service rooms.

https://x.com/broadwaysubway_/status/1971269774807081311

Sept 23:


Can you see the orange cover at Mount Pleasant Station, just below Broadway? This is a waterproofing layer that will help keep the future station dry.
Fun fact: crews are installing more than 13,000 square meters of waterproofing for this station!

https://x.com/broadwaysubway_/status/1970547514018287939
Reply With Quote
     
     
  #3170  
Old Posted Sep 26, 2025, 10:50 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,790
Quote:
Over the last few months, crews have completed a major milestone: track installation is now fully connected from VCC–Clark Station through to Broadway–City Hall Station.
https://www.broadwaysubway.ca/construction/current-work/
Reply With Quote
     
     
  #3171  
Old Posted Oct 7, 2025, 3:06 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,790
Quote:
Backfilling has begun at Arbutus Station, the first station on the Broadway Subway Project to reach this milestone.
Backfilling is the process of filling the space between the station roof and the surface with soil. This work will result in
increased trucking activity, some traffic impacts, and intermittent noise as material is delivered into the excavation,
moved into place and then compacted.
Quote:
• Backfilling activities will take place between Maple and Cypress streets.
• The first phase of backfilling is expected to continue through October and is weather
dependent. Additional phases of backfilling will continue after permanent utility work is
completed.
• Intermittent elevated noise related to delivery, moving, and compacting of material, and related
activities.
• Dust mitigation measures will be implemented throughout the work.
• Approximately 12,000 cubic meters of soil will be placed, enough to fill five Olympic-sized
swimming pools.
https://www.broadwaysubway.ca/construction/current-work/
Reply With Quote
     
     
  #3172  
Old Posted Oct 7, 2025, 6:27 AM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,803
Quote:
Originally Posted by jollyburger View Post
https://www.broadwaysubway.ca/construction/current-work/
Backfilling has begun at Arbutus Station, the first station on the Broadway Subway Project to reach this milestone.
I'll be glad when the entire corridor has returned to normal. They've done a pretty good job of keeping traffic flowing and businesses open, but I always get flummoxed by which of the adjoining streets are closed. I don't travel there often enough to remember, but I do travel there often enough to be annoyed.
Reply With Quote
     
     
  #3173  
Old Posted Oct 7, 2025, 11:43 AM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,178
I do wonder if Vancouver should just bite the bullet and forgo the station boxes for the next phase (whenever that happens). Arbutus-UBC isn't as busy, nor as critical.
Reply With Quote
     
     
  #3174  
Old Posted Oct 7, 2025, 1:42 PM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,803
Quote:
Originally Posted by Migrant_Coconut View Post
I do wonder if Vancouver should just bite the bullet and forgo the station boxes for the next phase (whenever that happens). Arbutus-UBC isn't as busy, nor as critical.
Are you suggesting no stations between Arbutus and UBC? 'Cause I certainly don't think that's such a good idea. The construction is annoying, but being glad that it's over doesn't mean that I think it was the wrong thing to do.
Reply With Quote
     
     
  #3175  
Old Posted Oct 7, 2025, 4:27 PM
gaviscon gaviscon is offline
Registered User
 
Join Date: Nov 2021
Posts: 771
Quote:
Originally Posted by Migrant_Coconut View Post
I do wonder if Vancouver should just bite the bullet and forgo the station boxes for the next phase (whenever that happens). Arbutus-UBC isn't as busy, nor as critical.
I mean if we want the Jericho Lands to be developed to that scale, we need stations in between.

But I guess the stations can be phased if we want to expedite the rail to UBC
Reply With Quote
     
     
  #3176  
Old Posted Oct 7, 2025, 5:24 PM
idunno idunno is offline
Registered User
 
Join Date: Feb 2010
Posts: 956
I don't think "infill underground stations" are of interest from TransLink's side (see 57th Ave Station non-starter)
Reply With Quote
     
     
  #3177  
Old Posted Oct 7, 2025, 5:25 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,790
Quote:
Originally Posted by aberdeen5698 View Post
Are you suggesting no stations between Arbutus and UBC? 'Cause I certainly don't think that's such a good idea. The construction is annoying, but being glad that it's over doesn't mean that I think it was the wrong thing to do.
Maybe he meant covering the pits up with the temporary roadway?
Reply With Quote
     
     
  #3178  
Old Posted Oct 7, 2025, 7:43 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,211
Quote:


Inside Arbutus Station, crews are building the concrete base for the SkyTrain tracks.

Next, workers will install metal fasteners on the completed concrete base, which will hold the rail in place.
https://x.com/broadwaysubway_/status/1975623464347218287
Reply With Quote
     
     
  #3179  
Old Posted Oct 7, 2025, 10:46 PM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,178
Quote:
Originally Posted by aberdeen5698 View Post
Are you suggesting no stations between Arbutus and UBC? 'Cause I certainly don't think that's such a good idea. The construction is annoying, but being glad that it's over doesn't mean that I think it was the wrong thing to do.
Quote:
Originally Posted by gaviscon View Post
I mean if we want the Jericho Lands to be developed to that scale, we need stations in between.

But I guess the stations can be phased if we want to expedite the rail to UBC
Quote:
Originally Posted by idunno View Post
I don't think "infill underground stations" are of interest from TransLink's side (see 57th Ave Station non-starter)
Sorry, typo: station decks. A large part of the delay seems to have been the challenge of keeping Broadway open during construction... and it hasn't helped traffic or local businesses as much as we thought.

Macdonald maybe, but Alma's not so critical that we can't "just" close it off to non-bus traffic and call it a day.
Reply With Quote
     
     
  #3180  
Old Posted Oct 7, 2025, 10:55 PM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,803
Quote:
Originally Posted by Migrant_Coconut View Post
Sorry, typo: station decks. A large part of the delay seems to have been the challenge of keeping Broadway open during construction... and it hasn't helped traffic or local businesses as much as we thought.
So are you suggesting that we should just close down the street where station construction is occurring? I actually think the Broadway construction has been reasonably successful compared to what Cambie experienced from Broadway to King Edward during the construction of the Canada Line. Of course what we have on Broadway is worse than it was before construction started, but I don't see how you can avoid some impact.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 7:22 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.