What can we glean from this information?
The portion of the lines (1 & the future 3) between Tunney’s Pasture and uOttawa (including the curved ramp between Rideau and uOttawa) is less of a problem than the portion between uOttawa and Blair. The west gets one evening of shut-down, while the east gets three. I suspect that there are a number of reasons for that, including; the curves around Hurdman; and the age of St. Laurent station and its associated underpasses.
I would guess that the “rail replacement at specific locations” would be swapping some of the rails in curves for harder rails. I expect that without the help of the guide rails to take part of the load on curves, the outside rails are wearing faster than originally anticipated.
[Recall that our tracks were laid with a guide rail to help the trains maneuver curves by having the guide rail push on the inside surface of the wheel flanges. This is common in North America because it splits the cornering loads between two rails, allowing for softer (cheaper) rails to be used. However, the
resilient wheels that are installed on our trains are not designed to take force on the inside face of the flange. Thus, we needed to pull the guide rails back to become non-contact guard rails. That puts all of the turning force onto the face of the outside rail, causing accelerated wear of our soft rails.]
I suspect that the “station maintenance and seasonal cleaning” might involve noisy equipment (maybe a pressure washer, for example) so it is preferred to use those earlier in the evening, while the noise by-law permits it. Yes, it could be exempted from the by-law, but if that is not necessary due to a short shut-down, then all the better.
As for the rest of the list of jobs, I would think that some of them (like the “ongoing upgrades of the supporting wires”) could take place during the night hours, but, since the line is being shut-down anyway, those tasks are done faster during the longer block of time.
Although I would like it if there were no annual shut-downs, I do appreciate that OC Transpo is trying to group the work so as to minimize the number (and duration) of shut-downs that do happen.
No talk of rail grinding this year. Odd.